Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

GENM.TO ·

Generation Completes Optimization Work for the Marathon Project with Improved Mine Plan and Reduced Capex

Corporate Updates

Generation Completes Optimization Work for the Marathon Project with

Improved Mine Plan and Reduced Capex

Highlights:

 Mine plan optimized with reduced strip ratio bringing additional 78k ounces of

palladium, 34k ounces of Platinum and 2M lb of Copper in the first 3 years

 Estimated $190M in additional payable revenues1 and operating cost benefits by the

end of year 3 of operations

 Initial Capital estimate reduced by $89M despite industry-wide inflationary cost

pressures

 Improved Project Economics with a 26% after-tax IRR and 2.1 year after-tax

payback period1

TORONTO--(BUSINESS WIRE)--November 20, 2024--Generation Mining Limited

(TSX:GENM, OTCQB: GENMF) ("Gen Mining" or the "Company") is pleased to provide an

update on the project optimization work (the “Optimization Work”) previously announced on

June 6, 20242 on the Marathon Palladium-Copper Project (the “Marathon Project”) in

Northwestern Ontario. The Optimization Work focused on two key aspects: (1) optimization of

the mine plan to maximize metal production and defer waste stripping in the early years of

operations in order to improve early cash flows and reduce the payback period (“Mine Plan

Optimization”); and (2) review and optimization of the plant design and layout, including sizing

of key equipment, plant footprint and foundations, in order to reduce the initial Project capital

costs (“Initial Capital Optimization”).

Jamie Levy, President and CEO, commenting on the Optimization Work, remarks:

“The optimized mine plan is a notable improvement to the existing plan, with $190 million

in additional payable metal revenues1 and savings from a reduced strip ratio during the

initial 3-years of mine operations.

The other meaningful improvement to the project is the optimized plant design and ancillary

changes recommended by Ausenco, which represent a net savings in total project capital

costs of over $89 million, after taking into account the impact of inflation on certain

construction materials and equipment, and other design change escalations since the end of

2022.

This optimization work by Ausenco and our team represents a meaningful improvement to

the financeability, constructability and economics of our project following several years of

significant inflation in many input costs, and validates the continued robustness of the

Marathon Project.”

The Mine Plan Optimization was carried out by the Company and the Initial Capital

Optimization was performed by the Company in collaboration with Ausenco Engineering

Canada ULC (“Ausenco”). All amounts are reported in Canadian dollars unless otherwise noted

herein.

Mine Plan Optimization

The Company evaluated alternative pit sequencing options that exploit the benefit of the ore

body’s proximity to surface. The results of this work demonstrated the viability of focussing on a

higher grade, lower strip ratio for the initial phase of mining operations. This results in the

deferral of approximately 36 million tonnes of waste stripping during the first three years of

operations while increasing the amount of recovered and payable metals during this period.

Highlights of the Mine Plan Optimization are as follows:

Units Optimization

Work

Technical

Report3 Variance

LOM Throughput

Peak Process Plant Throughput

tpd 27,700 27,700 Nil

Mt/year 10.1 10.1 Nil

Peak Mining Rate

tpd 157,000 115,000 42,000

Mt/year 57 42 +15

Production Data (to end of Y3 of Operations, Incl. Pre-Production)

Total Mined Mt 97 132 (35)

Total Waste Mined Mt 62 98 (36)

Total Ore Mined Mt 35 34 +1

Strip Ratio waste:ore 1.8 2.9 (1.1)

Payable Metal (to end of Y3 of Operations, Incl. Pre-Production)

Palladium k oz 669 591 +78

Copper M lbs 139 137 +2

Platinum k oz 143 112 +31

Gold k oz 43 36 +7

Silver k oz 512 477 +35

The deferral of 36 million tonnes of waste material and increasing payable metal production up

to the end of the third year of operations, including the pre-production period, is estimated to

result in $190 million in additional revenues and cost savings during this period.

As a result of this new sequencing the peak mining tonnage will increase to 57 Mtpa. The costs

associated with this stripping are included in the life of mine operating costs, capital costs and

project economics, discussed below.

Initial Capital Optimization

The Company engaged Ausenco to perform a review of the Marathon Project’s capital and

operating costs, with a primary focus on the Processing Plant and ancillary infrastructure. This

work benefitted from Ausenco’s extensive experience in plant design and construction of copper

concentrators, most recently at Capstone Copper’s Mantoverde Mine in Chile, as well as their

recent experience working in Northern Ontario at Alamos Gold’s Magino Mine. The goal of the

work was to improve the designs for Project constructability and to decrease initial capital costs

as compared to the estimates disclosed in the Technical Report.

The optimization work included changes to the plant layout and footprint, adjustment of

equipment selections to ensure key equipment is ‘fit for purpose’, and review of the foundation

and structural designs to take advantage of favourable site geotechnical conditions and minimal

overburden across the site.

Total initial capex is now expected to be $961 million4 (“Initial Capital”), or a reduction of $89

million from the amounts previously estimated in the Technical Report, and reflects updated

costing for inflation since the effective date of the Technical Report. The key changes from the

Optimization Work are summarized below:

Capital Costs Impact $M(a) Explanation of Cost and Variance

Equipment and Building Layout (71)

Reduced plant pad footprint (-22%)

Reduced plant volume (-20%)

Reduced concrete (-46%)

Reduced Structural Steel (-30%)

Improved Electrical layout and e-rooms

Equipment Sizing (29) Reduced mill sizing (SAG, Ball, Regrind)

Reduced electrical redundancy

Equipment Deferrals (35)

Pebble crusher and tailings thickener deferred to

sustaining capital

Reduced tailings thickener size

Market Escalation Impacts +50 Inflation in construction labour rates

Inflation in mechanical parts costs

Earthworks and Site Infrastructure +6 Escalation on Earthworks

Offset by optimization of site infrastructure

Mobile Equipment Leases(b) +4 Escalation on mobile equipment costs

Project Indirects (14) Re-estimation of EPCM and some reallocation to direct

costs

Total (89) Overall reduction as compared to Technical Report

Notes:

(a) (negative) numbers represent a reduction from the Technical Report values.

(b) Includes additional leasing deposits and payments during the construction and pre -production phase only.

As part of the initial capital cost review, the processing plant costs were estimated at a Class 3

AACE standard. In addition, the mining fleet was retendered to obtain current market pricing and

the earthworks scope was partially retendered and adjusted for inflation.

Operating Costs

The Project operating costs have been updated and are reflected in the below table.

Unit Operating Costs (Average LOM)

Units Optimization

Work

Technical

Report

Mining

$/t mined 3.43 3.25

$/t milled 12.32 11.45

Processing $/t milled 8.27 8.70

G&A $/t milled 2.53 2.67

Transport & Refining Charges $/t milled 4.22 4.13

Royalty $/t milled 0.10 0.09

Total Unit Operating Cost $/t milled 27.44 27.04

Project operating costs per tonne of ore milled have increased primarily as a result of changes in

mining costs, with an offset from reduced processing costs. Mining costs have been impacted by

escalation in equipment maintenance parts (per manufacturer’s guidance), updated fuel pricing,

mining operating labour rates, and adjustment to truck cycle times under the optimized mining

plan. Processing costs have been updated to reflect consumable pricing and labour cost

estimates. Consumption rates for consumables are largely unchanged.

Capital Costs

The initial capital costs for construction and ramp-up, together with expected sustaining capital

and closure costs, are presented in the table below:

Capital Area Units Optimization

Work

Technical

Report

Variance

Mining Equipment for

Construction(a) $M 61 57(b) 4

Processing Plant $M 280 345 (65)

Infrastructure $M 86 72 14

TSF, Water Management and

Earthworks $M 80 95 (15)

EPCM, General and Owners Cost $M 210 228 (18)

Preproduction, Startup,

Commissioning $M 153 157 (4)

Contingency $M 92 97 (5)

Initial Capital $M 961 1,050 (b) (89)

Preproduction revenue(c) $M (173) (156) (17)

Total $M 788 894 (106)

Sustaining Capital $M 502 424 78

Closure and Reclamation Costs $M 72 72 Nil

Notes:

(a) Mining Equipment acquired for Construction is presented as the cost of equipment deposits and lease payments

during the construction and pre-production period. The remainder of the equipment leasing costs are incurred during

operations and are included in the financial analysis.

(b) The Technical Report presented the capital costs for mining and surface equipment as $117M, the initial capital

sub-total as $1,112M, and a $58M Equipment Financing adjustment. For consistency of presentation, the net cost of

leased mining equipment during the construction and pre-production period, including working capital adjustments,

is presented above.

(c) See Economic Analysis, below, for additional information on the different metal price assumptions used in the

Optimization Work and the Technical Report.

Economic Analysis

In order to quantify and assess the value of the Optimization Work to the economics of the

Marathon Project, the Company completed an economic analysis using the following key

assumptions:

Key Assumptions(a) Units Optimization

Work

Technical

Report

Palladium Price US$/oz 1,525 1,800

Copper Price US$/lb 4.00 3.70

Platinum Price US$/oz 950 1,000

Gold Price US$/oz 2,000 1,800

Silver Price US$/oz 24.00 22.50

Foreign Exchange $:US$ 1.35 1.35

Diesel Price $/litre 1.10 1.17

Electricity $/kWhr 0.07 0.07

Note:

(a) Metal price assumptions are based on the adjusted 3-year historical trailing averages as of November 1, 2024 for

each of the metals. The 3-year averages are as follows: Palladium - US$1,523/oz, Copper at U$4.02/lb, Platinum at

US$964/oz, Gold at US$1,995/oz and Silver at US$24.02/oz.

The economic analysis of the Optimization Work is based on the same economic model used for

the economic analysis in the Technical Report. The model inputs principally consist of metal

production volumes and metal prices, unit operating costs, capital costs, sustaining capital

expenditures, treatment charges (“TCs”) and refining charges (“RCs”), royalty terms, closure and

reclamation costs, and taxation rates. The economic analysis of the Optimization Work also

includes the impact of the sale of gold and platinum metal under the Precious Metal Purchase

Agreement with Wheaton Precious Metals Corp. (“PMPA”), excluding any delay ounces.

Although current market TCs and RCs are lower, the TCs and RCs in the economic analysis are

unchanged from the Technical Report. The economic analysis does not consider any potential

economic benefits which the Marathon Project may qualify for under any government incentive

programs for critical mineral production.

The following table presents the key outputs of the economic analysis for the Optimization

Work, as compared to the economic analysis contained in the Technical Report, and the

economic analysis contained in the technical report adjusted for the metal price assumptions used

in the Optimization Work.

Financial Evaluation(a) Units Optimization

Work

Technical

Report

(using

Technical

Report

Optimization

Metal Prices)

Pre-Tax Cash Flow (undiscounted) $M 2,877 2,859 3,387

Pre-Tax NPV6% $M 1,555 1,464 1,798

Pre-Tax IRR % 32.8 22.2 31.9

Pre-Tax Payback years 1.9 2.5 2

After-Tax Cash Flow

(undiscounted) $M 1,923 1,929 2,285

After-Tax NPV6% $M 998 935 1,164

After-Tax IRR % 26.3 22.2 25.8

After-Tax Payback years 2.1 2.9 2.3

Note:

(a) The economic analysis was carried out in real terms (i.e., without inflation factors) in Q4 2024 Canadian dollars,

assuming no project construction financing but inclusive of mining equipment leasing.

Project Cash Flows

The table below highlights the estimated cumulative cash flows to the end of year 3 which result

from the Mine Plan Optimization, the Initial Capital Optimization, and the Optimization Work

on sustaining capital and operating cost estimates. This analysis is presented in comparison to the

same analysis performed for (a) the Technical Report, and (b) the Technical Report using the

same metal prices as the Optimization Work.

Cash flows from the project’s start to the end of year 3 of operations are approximately $247

million greater than the Technical Report cash flows and $129 million greater by the end of year

5 at the same metal prices. These cumulative cash flows include the initial capital cost used to

construct the project, including the impact of the PMPA, and therefore the positive cash flow

results support the short payback period.

Financial Evaluation Units Optimization

Work

Technical

Report

(adjusted for

Optimization

Metal Prices)

Technical

Report

Cumulative After-Tax Cash Flow to

End of Y3 $M 232 (15.3) 91

Cumulative After-Tax Cash Flow to

End of Y5 $M 470 341 523

Sensitivities

The Project has significant leverage to palladium and copper prices. The after-tax valuation

sensitivities for the key metrics are shown below.

Palladium Price

US$/oz 1,000 1,250 1,500 1,525 1,750 2,000

NPV6% ($M) 394 682 969 998 1,257 1,543

Payback (yrs) 4.5 2.5 2.1 2.1 1.9 1.5

IRR (%) 14.8% 20.5% 25.8% 26.3% 30.7% 35.2%

Copper Price

US$/lb 3.00 3.50 4.00 4.50 5.00

NPV6% ($M) 726 863 998 1,135 1,270

Payback (yrs) 2.4 2.2 2.1 2.0 1.9

IRR (%) 21.7% 24.1% 26.3% 28.5% 30.5%

After-Tax NPV 6%

Results

Palladium Price Sensitivity (US$/oz)

1,000 1,250 1,500 1,525 1,750 2,000

Copper

Price

Sensitivity

(US$/lb)

3 112 410 697 726 984 1,274

3.5 255 546 834 863 1,122 1,408

4 394 682 969 998 1,257 1,543

4.5 531 819 1,106 1,135 1,393 1,678

5 666 954 1,242 1,270 1,528 1,812

After-Tax Results OPEX Sensitivity

+30% +15% 0% -15% -30%

NPV 6% ($M) 620 810 998 1,188 1,376

Payback (yrs) 2.4 2.2 2.1 1.9 1.9

IRR (%) 19.9% 23.2% 26.3% 29.2% 31.9%

After-Tax Results CAPEX Sensitivity

+30% +15% 0% -15% -30%

NPV 6% ($M) 779 889 998 1,109 1,218

Payback (yrs) 3.0 2.4 2.1 1.5 1.2

IRR (%) 18.2% 21.7% 26.3% 32.8% 42.8%

Further Opportunities and Next Steps

As part of the Optimization Work, Ausenco identified approximately $75 million of further

optimization opportunities that require additional analysis. The opportunities relate to additional

layout optimizations, adjustments that would require additional processing and metallurgical

testwork, and market re-tendering. Additional work will be required to validate some of the

concepts and to determine if these opportunities can be realized.

The Company anticipates integrating the Optimization work into the Project designs and will

continue to investigate additional construction efficiencies and opportunities, including working

with contractors to incorporate new earthworks details and cost estimates.

The Optimized Mine Plan discussed herein does not result in any material change to mineral

resource and reserve estimates. Future work will determine if any of the 2024 drilling (see July

31, 2024 press release)5 will be incorporated into an updated mineral resource estimate.

The Company is continuing to finalize the provincial construction permits and pursue project

financing opportunities in order to bring the Marathon Project into production.

Footnotes:

1 See “Economic Analysis” in this release for additional information on the metal price

assumptions used in the Optimization Work and the Technical Report.

2 See https://genmining.com/news/2024/generation-mining-continues-with-project-optimizat-

8979/.

3 All references herein to the “Technical Report” refer to the Company’s NI 43-101 technical

report for the Marathon Project entitled, “Amended Feasibility Study Update Marathon

Palladium & Copper Project Ontario, Canada” dated May 31, 2024 with an effective date of

December 31, 2022.

4 Initial capital is the total project capital, inclusive of 10% deposits and lease payments for

mobile equipment during the construction and pre-production phase. The balance of this mobile

equipment cost is amortized during the operations phase.

5 See https://genmining.com/news/2024/generation-mining-receives-key-approval-from-the-f-

9207/.

Qualified Person

The scientific and technical content of this news release was reviewed, verified, and approved by

Drew Anwyll, P.Eng., M.Eng, Chief Operating Officer of the Company, and a Qualified Person

as defined by Canadian Securities Administrators’ National Instrument 43-101 - Standards of

Disclosure for Mineral Projects.

Forward-Looking Information

This news release contains certain forward-looking information and forward-looking statements,

as defined in applicable securities laws (collectively referred to herein as "forward-looking

statements"). Forward-looking statements reflect current expectations or beliefs regarding future

events or the Company’s future performance. All statements other than statements of historical

fact are forward-looking statements. Often, but not always, forward-looking statements can be

identified by the use of words such as "plans", "expects", "is expected", "budget", "scheduled",

"estimates", "continues", "forecasts", "projects”, “predicts”, “intends”, “anticipates”,

“targets” or “believes”, or variations of, or the negatives of, such words and phrases or state

that certain actions, events or results “may”, “could”, “would”, “should”, “might” or “will”

be taken, occur or be achieved, including statements relating to mine planning and pit designs;

the timing and amount of estimated future revenues, the timing and volume of payable mineral

production, the payback period, and financial returns from the Marathon Project.