Gunnison Copper Announces Johnson Camp SX Plant Start-up with First Copper Sales

in September

August 11, 2025

Gunnison Copper Corp. (TSX: GCU) (OTCQB: GCUMF) (FSE: 3XS0) ("Gunnison" or the

“Company”) is pleased to announce that the solvent extraction (SX) plant and electrowinning (EW)

circuit has started with first copper sales expected in September at the Company’s Johnson Camp Mine

("JCM"), in southeast Arizona.

“With the start-up of the SX-EW plant ahead of schedule we have achieved another major step towards

our targeted copper cathode sales in September this year,” states Robert Winton, SVP Operations. He

continues, “the dedicated team at Johnson Camp has executed this startup without incident and in record

time, preparing for our first harvest of Made-in-America copper to be sold in Q3 this year.”

Progress as of the Company’s last update (see Gunnison news release dated July 22nd) includes:

 Leaching of mineralized run-of-mine material started with copper rich solution being pumped to

the SX-EW plant (Figure 1).

 SX Plant started (Figure 2)

 EW Circuit started and being readied for Copper Plating (Figure 3)

Since the Company’s last update, the Company is pleased to report that JCM construction activities,

funded by Nuton LLC, a Rio Tinto venture, continue to progress as planned. The final phase of the leach

pad construction is on schedule. The on-pad crushing circuit, which will be used with the Nuton

Technologies, has been installed and started commissioning activities. The agglomerator and processing

equipment, which will also be used on the Nuton pad, has been placed and the Company is completing

final mechanical and electrical construction of these components. The new LNG (liquid natural gas)

system at the EW plant was fully commissioned and operating in line with electrowinning start-up.

2

Figure 1 – Aerial view showing the first four panels of the run-of-mine leach pad under leach and green

copper solution collecting on the top right-hand corner of the leach pad before being pumped to the SX-

EW plant.

3

Figure 2 – The left image shows green colored, copper rich solution from the leach pad, being pumped

into the lined collection pond near the processing plant, ready for treatment. The right image shows

upgraded, blue colored, copper electrolyte solution produced from the SX plant being readied for

electrowinning and copper cathode production.

4

Figure 3 – This image shows the electrowinning plant being readied by loading stainless steel blank cathodes

into the electrowinning cells, ready for plating pure copper metal onto them later this month.

ABOUT GUNNISON COPPER

Gunnison Copper Corp. is a multi-asset pure-play copper developer and producer that controls the

Cochise Mining District (the district), containing 12 known deposits within an 8 km economic radius, in

the Southern Arizona Copper Belt.

Its flagship asset, the Gunnison Copper Project, has a Measured and Indicated Mineral Resource

containing over 831,6 million tons with a total copper grade of 0.31% (Measured Mineral Resource of

191.3 million tons at 0.37% and Indicated Mineral Resource of 640.2 million tons at 0.29%), and a

preliminary economic assessment (“PEA”) yielding robust economics including an NPV8% of $1.3Billion,

IRR of 20.9%, and payback period of 4.1 years. It is being developed as a conventional operation with

open pit mining, heap leach, and SX/EW refinery to produce finished copper cathode on-site with direct

rail link.

The PEA is preliminary in nature and includes Inferred Mineral Resources that are considered too

speculative geologically to have the economic considerations applied to them that would enable them to

be categorized as mineral reserves. There is no certainty that the conclusions reached in the PEA will be

realized. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

In addition, Gunnison’s Johnson Camp Asset, which is under construction with first copper production

expected in Q3 2025, is fully funded by Nuton LLC, a Rio Tinto venture, with a production capacity of up

to 25 million lbs of finished copper cathode annually.

5

Other significant deposits controlled by Gunnison in the district, with potential to be economic satellite

feeder deposits for Gunnison Project infrastructure, include Strong and Harris, South Star, and eight other

deposits.

For additional information on the Gunnison Project, including the PEA and mineral resource estimate,

please refer to the Company’s technical report entitled “Gunnison Project NI 43-101 Technical Report

Preliminary Economic Assessment” dated effective November 1, 2024 and available on SEDAR+ at

www.sedarplus.ca.

Dr. Stephen Twyerould, Fellow of AUSIMM, President and CEO of the Company is a Qualified Person

as defined by NI 43-101. Dr. Twyerould has reviewed and is responsible for the technical information

contained in this news release.

For more information on Gunnison, please visit our website at www.GunnisonCopper.com

ABOUT NUTON

Nuton is an innovative venture that aims to help grow Rio Tinto’s copper business. At the core of Nuton

is a portfolio of proprietary copper leaching technologies and capability. Nuton has the potential to

economically unlock copper from hard-to-leach ores, including primary sulfides and, in doing so, increase

domestic production of critical minerals to support the energy transition. Nuton technologies can achieve

market-leading recovery rates and boost copper production in new, ongoing and historical operations,

increasing resource utilization and maximizing value.

With significantly lower energy and water needs than conventional concentrating and smelting, and the

ability to produce copper cathode at the mine site, Nuton offers a reliable source of domestically produced

copper, with a short mine-to-metal supply chain and the ambition to set industry-leading ESG credentials.

One of the key differentiators of Nuton is the ambition to produce the world’s lightest environmental

footprint copper while having at least one Positive Impact at each of its deployment sites, across its five

pillars: energy, water, land, materials and society.

For more information, please visit https://nuton.tech.

For further information regarding this press release, please contact:

Gunnison Copper Corp.

Concord Place, Suite 300, 2999 North 44th Street, Phoenix, AZ, 85018

Melissa Mackie

T: 647.533.4536

E: [email protected]

www.GunnisonCopper.com

Cautionary Note Regarding Forward-Looking Information

This news release contains "forward-looking information" concerning anticipated developments and events that may

occur in the future. Forward looking information contained in this news release includes, but is not limited to,

statements with respect to: (i) the intention to deploy the Nuton® technology at the Johnson Camp mine and future

production therefrom; (ii) the continued funding of the stage 2 work program by Nuton; (iii) the details and expected

results of the stage two work program; (iv) timelines for future production and production capacity from the

Company’s mineral projects; (v) timelines for continued construction at JCM; (vi) the results of the preliminary

economic assessment on the Gunnison Project; and (vi) the exploration and development of the Company’s mineral

projects.

6

In certain cases, forward-looking information can be identified by the use of words such as "plans", "expects" or

"does not expect", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate",

or "believes", or variations of such words and phrases or state that certain actions, events or results "may", "could",

"would", "might", "occur" or "be achieved" suggesting future outcomes, or other expectations, beliefs, plans,

objectives, assumptions, intentions or statements about future events or performance. Forward-looking information

contained in this news release is based on certain factors and assumptions regarding, among other things, Nuton

will continue to fund the stage 2 work program, the availability of financing to continue as a going concern and

implement the Company’s operational plans, the estimation of mineral resources, the realization of resource and

reserve estimates, , copper and other metal prices, the timing and amount of future development expenditures, the

estimation of initial and sustaining capital requirements, the estimation of labour and operating costs (including the

price of acid), the availability of labour, material and acid supply, receipt of and compliance with necessary

regulatory approvals and permits, the estimation of insurance coverage, and assumptions with respect to currency

fluctuations, environmental risks, title disputes or claims, and other similar matters. While the Company considers

these assumptions to be reasonable based on information currently available to it, they may prove to be incorrect.

Forward looking information involves known and unknown risks, uncertainties and other factors which may cause

the actual results, performance or achievements of the Company to be materially different from any future results,

performance or achievements expressed or implied by the forward-looking information. Such factors include risks

related to the Company not obtaining adequate financing to continue operations, Nuton failing to continue to fund

the stage 2 work program, the breach of debt covenants, risks inherent in the construction and operation of mineral

deposits, including risks relating to changes in project parameters as plans continue to be redefined including the

possibility that mining operations may not be sustained at the Gunnison Copper Project, risks related to the delay

in approval of work plans, variations in mineral resources and reserves, grade or recovery rates, risks relating to

the ability to access infrastructure, risks relating to changes in copper and other commodity prices and the worldwide

demand for and supply of copper and related products, risks related to increased competition in the market for

copper and related products, risks related to current global financial conditions, risks related to current global

financial conditions on the Company’s business, uncertainties inherent in the estimation of mineral resources,

access and supply risks, risks related to the ability to access acid supply on commercially reasonable terms, reliance

on key personnel, operational risks inherent in the conduct of mining activities, including the risk of accidents, labour

disputes, increases in capital and operating costs and the risk of delays or increased costs that might be

encountered during the construction or mining process, regulatory risks including the risk that permits may not be

obtained in a timely fashion or at all, financing, capitalization and liquidity risks, risks related to disputes concerning

property titles and interests, environmental risks and the additional risks identified in the “Risk Factors” section of

the Company’s reports and filings with applicable Canadian securities regulators.

Although the Company has attempted to identify important factors that could cause actual actions, events or results

to differ materially from those described in forward-looking information, there may be other factors that cause

actions, events or results not to be as anticipated, estimated or intended. Accordingly, readers should not place

undue reliance on forward-looking information. The forward-looking information is made as of the date of this news

release. Except as required by applicable securities laws, the Company does not undertake any obligation to

publicly update or revise any forward-looking information.