Excelsior Mining Receives First Acid Delivery for Copper Production
26427809.2
NEWS RELEASE
Excelsior Mining Receives First Acid Delivery for Copper Production
August 13th, 2019
Excelsior Mining Corp. (TSX: MIN) (FSE: 3XS) (OTCQX: EXMGF) ("E xcelsior" or the “Company”)
confirms the first delivery of acid to the Gunnison Copper Project in southern Arizona. Excelsior remains
on-schedule for first copper production in Q4 2019.
In July, Excelsior completed the construction of three new acid storage tanks and a new acid unloading
facility. The new acid storage tanks have capacity for 7500 ton s of sulphuric acid, providing for excess
operational and purchasing flexibility. Acid deliveries commenced on August 12th and will continue on a
regular basis until the tanks are full and throughout operations.
Roland Goodgame, COO, commented by saying “The new acid deliveries are on schedule and continue
to demonstrate our progress towards operations later this year. The pure sulfuric acid in these tanks is
diluted down to a weak sulfuric acid mining solution via the new acid handling and delivery system. This
weaker acid solution is used in the wellfield operations to lea ch the copper from the naturally fractured
rocks below ground.”
About Excelsior Mining
Excelsior “The Copper Solution Company ” is a mineral exploration and development company that is
advancing the Gunnison Copper Project in Cochise County, Arizona. The project is an advanced staged,
low cost, environmentally friendly in-situ recovery copper extr action project that is fully-permitted to 125
million pounds per year of copper cathode production. The Feasi bility Study projected an after-tax NPV
of US$ 807 million and an IRR of 40% using a US$ 2.75 per pound copper price and a 7.5% discount
rate.
Excelsior’s technical work on the Gunnison Copper Project is supervised by Stephen Twyerould, Fellow
of AUSIMM, President & CEO of Excelsior and a Qualified Person as defined by National Instrument 43-
101. Mr. Twyerould has reviewed and approved the technical information contained in this news release.
Additional information about the Gunnison Copper Project can be found in the technical report filed on
SEDAR at www.sedar.com entitled: “Gunnison Copper Project, NI 4 3-101 Technical Report, Feasibility
Study” dated effective December 17, 2016.
For more information on Excelsior, please visit our website at www.excelsiormining.com.
For further information regarding this press release, please contact:
Excelsior Mining Corp.
Concord Place, Suite 300, 2999 North 44th Street, Phoenix, AZ, 85018.
JJ Jennex, Vice President, Corporate Affairs
T: 604 723 1433
26427809.2
2
www.excelsiormining.com
Cautionary Note Regarding Forward-Looking Information
This news release contains "forward-looking information" concerning anticipated developments and events that may
occur in the future. Forward looking information contained in this news release includes, but is not limited to,
statements with respect to: (i) the results of the Feasibility Study, including operating and capital cost estimates and
the economic benefits from the G unnison Copper Project; (ii) the details of the various construction activities that
are being or will be undertaken on the Gunnison Copper Project and their timeline for completion; (iii) the schedule
for the commencement of commercial production; and (iv) the ability to mine the Gunnison Copper Project using in-
situ recovery mining techniques.
In certain cases, forward-looking information can be identif ied by the use of words such as "plans", "expects" or
"does not expect", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate",
or "believes", or variations of such words and phrases or state that certain actions, events or results "may", "could",
"would", "might", "occur" or "be achieved" suggesting fu ture outcomes, or other expectations, beliefs, plans,
objectives, assumptions, intentions or statements about future events or performance. Forward-looking information
contained in this news release is based on certain fa ctors and assumptions regardi ng, among other things, the
estimation of mineral resources and mineral reserves, the realization of resource and reserve estimates, copper
and other metal prices, the timing and amount of future de velopment expenditures, the estimation of initial and
sustaining capital requirements, the estimation of labour and operating costs, the progress of construction activities,
receipt of and compliance with necessary regulatory ap provals, the estimation of insurance coverage, and
assumptions with respect to currency fluctuations, environm ental risks, title disputes or claims, and other similar
matters. While the Company considers these assumptions to be reasonable based on information currently
available to it, they may prove to be incorrect.
Forward looking information involves known and unknown risks, uncertainties and other factors which may cause
the actual results, performance or achievements of the Company to be materially different from any future results,
performance or achievements expressed or implied by the forward-looking information. Such factors include risks
inherent in the construction of mineral deposits, including risks relating to changes in project parameters as plans
continue to be redefined including the possibility that mining operations may not commence at the Gunnison Copper
Project, risks relating to variations in mineral resources and reserves, grade or recovery rates, risks relating to the
ability to access infrastructure, risks relating to changes in copper and other commodity prices and the worldwide
demand for and supply of copper and related products, ri sks related to increased competition in the market for
copper and related products, risks related to current global financial conditions, uncertainties inherent in the
estimation of mineral resources, acce ss and supply risks, reliance on key pers onnel, operational risks inherent in
the conduct of mining activities, including the risk of acci dents, labour disputes, increases in capital and operating
costs and the risk of delays or increased costs that might be encountered during the construction process, regulatory
risks, financing, capitalization and liquidity risks, risks related to disputes co ncerning property titles and interest,
environmental risks and the additional risks identified in the “Risk Factors” section of the Company’s reports and
filings with applicable Canadian securities regulators.
Although the Company has attempted to identify important factors that could cause actual actions, events or results
to differ materially from those described in forward-lo oking information, there may be other factors that cause
actions, events or results not to be as anticipated, esti mated or intended. Accordingl y, readers should not place
undue reliance on forward-looking information. The forward-looking information is made as of the date of this news
release. Except as required by applicable securities laws, the Company does not undertake any obligation to
publicly update or revise any forward-looking information.