Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

GCU.TO ·

Excelsior Mining Announces Updated Technical Report for Gunnison Copper Project and Johnson Camp Mine

Technical Reports (NI 43-101)

NEWS RELEASE

Excelsior Mining Announces Updated Technical Report for

Gunnison Copper Project and Johnson Camp Mine

March 30, 2022

Excelsior Mining Corp. (TSX: MIN) (PFSE: 3XS) (OTCQX: EXMGF) ("Excelsior" or the “Company”)

is pleased to announce the results of its Prefeasibility Study Update (“PFS” or “Report”) on the North Star

Deposit of the Gunnison Copper Project and Preliminary Economic Assessment (“PEA”) on the Johnson

Camp Mine Heap Leach, both located in Cochise County, southeastern Arizona. The Gunnison Project

is designed as a copper in-situ recovery (“ISR”) mine using solvent extraction-electrowinning (“SX-EW”)

to produce copper cathode and the Johnson Camp mine is a heap leach operation. Results of the PFS

and PEA disclosed in this press release are in United States dollars.

GUNNISON PROJECT PREFEASIBILITY STUDY

Highlights of the PFS (United States dollars)

 Net Present Value (“NPV”) of $1,348.5 million after-tax

o at 7.5% discount rate using a life of mine (“LOM”) average copper price of $3.93/lb;

 Internal Rate of Return (“IRR”) of 44.9% after-tax;

 Pre-production capital costs of $45.1 million

o includes 15% contingency, EPCM, freight, mobile equipment, owner’s costs and capital

spares;

 Payback period for pre-production capital of 4.8 years after-tax;

 Average life of mine operating costs of $0.91/lb;

 Total Operating Cash Cost (including royalties, non-income taxes, salvage, reclamation and

closure) of $1.21/lb

 All-In Cost (LOM capital costs plus operating costs) of $1.70/lb;

 Life of Mine: 2,153 million pounds of commercial production over 24 years;

 Staged production profile: initial production rate of 25 million pounds of copper cathode per

annum, followed by an intermediate expansion stage to 75 million pounds per annum and final

expansion stage to full production of 125 million pounds per annum (includes the construction of

an acid plant at full production). The staged production profile makes possible the funding of future

expansions out of cash flow;

 Approximately 15 months of wellfield pre-conditioning (additional operations) to dissolve and

remove calcite, along with the addition of a raffinate neutralization plant to assist with the

flushing and removal of accumulated CO2 gas;

 Requirement for some additional work to reduce risk and optimize process and production.

A detailed sensitivity analysis to copper price, including a comparison to the results of the 2016 Feasibility

Study, is set out below under the heading “Financial Analysis”. In addition, the risks and opportunities

associated with the Gunnison Project are discussed below.

2

Commenting on this Report, President & CEO, Dr. Stephen Twyerould said, “Excelsior is committed to

innovative and environmentally sustainable copper production through our flagship asset, the Gunnison

Copper Project. Production challenges have highlighted the need to re-engineer wellfield ramp-up,

including the introduction of a long period of pre-production CO 2 flushing and calcite removal. Capital

costs, operating costs and the production schedule have been re-estimated to account for wellfield pre-

conditioning and flushing using neutralized raffinate. These changes have been incorporated in the new

PFS, which highlights the value of our Gunnison Project along with the need for additional time and work

before commercial production is achieved. The Company looks forward to undertaking the

recommendations of the PFS and getting back-on-track.”

The PFS was completed by M3 Engineering & Technology Corporation (“M3”) of Tucson, AZ and is

effective as of March 11, 2022. The Technical Report (the “Report”) summarizing the results of the PFS,

and prepared in accordance with National Instrument (“NI”) 43-101, will be filed on SEDAR today.

Financial Analysis

The PFS base case generates an after-tax NPV of approximately $1,348.5 million (at a cash flow discount

of 7.5%) and an IRR of 44.9%. This financial analysis is based on a number of assumptions which will

be fully set out in the Report.

The base case uses the following parameters over the 24-years of production:

 Copper selling price of:

o Years 1 thru 5: $4.25/lb

o Years 6 thru 15: $4.00/lb

o Years 16 and beyond: $3.75/lb

 Total copper recovery of approximately 48% (based on a combination of metallurgical recovery

and estimated sweep efficiency);

 Average of approximately 9.5 pounds of acid consumed for every pound of copper produced;

 Acid plant construction in year 7 with the price of sulfuric acid prior to that of approximately

$120/ton and the price of sulfur of $120 per ton delivered after that:

 Combined state and federal tax rate of 32.9%;

 Staged production commencing at 25 million pounds per annum, ramping up to 75 million pounds

in year 4, and then to 125 million pounds per annum in Year 7.

 The introduction of an additional year of pre-production calcite removal and neutralized raffinate

flushing for every well to address CO2 flow restrictions.

FINANCIAL ANALYSIS SUMMARY

Pre-Tax Post-Tax

IRR 50.3% 44.9%

Pre-Production Capital Payback (years) 4.4 4.8

NPV (million $) @7.5% 1,777.5 1,348.5

Ratio of New Capital of NPV7.5 0.025 0.033

COST METRICS

Cost/lb Copper

Direct Operating Costs 0.91

Royalties, Taxes, Recl. & Salvage 0.30

Total Cash Cost 1.21

Total initial (pre-breakthrough) capital expenditures (including 15% contingency, EPCM, capital spares,

owner’s costs, mobile equipment and freight) are estimated at $45.1 million. The production wellfield is

estimated at $6.1 million for drilling and wellfield infrastructure and $29.7 million is estimated for the water

treatment plant. Capitalized pre-production costs for the wellfield and water treatment plant total $9.3

million. Initial production of copper cathode is estimated to be 25 million pounds per annum. Total

sustaining capital costs over the life of the mine are $1,026.6 million, which includes production wellfield

3

expansion, SX-EW expansion, acid plant construction and water treatment facilities. The average life of

mine Direct Operating Cash Cost is $0.91/lb and the average life of mine Total Operating Cash Cost

(including royalties, non-income taxes, salvage, reclamation and closure) is $1.21/lb.

The Company has also evaluated an Alternate case without an Acid Plant. This case generated a pre-

tax [email protected]% of $1,585.7 million and an IRR of 51.9% (after-tax: [email protected]% of $1,218.6 million and

IRR of 46.6%). Total initial capital expenditures remain the same as the “Acid Plant” scenario. Total

sustaining capital costs over the life of the mine are $873.1 million, which includes production well-field

expansion, SX-EW expansion and water treatment facilities. Average life of mine Operating Direct Cash

Costs are estimated at $1.24/lb for the “No-Acid Plant” option with an average life of mine Total Operating

Cash Cost of $1.53 per pound.

Sensitivity analysis on copper price is shown in the table below.

Sensitivity Analysis (After-Tax)

Sensitivity Base Case (Acid Plant)

-20% -10% 0 +10% +20%

Cu Price $3.15 $3.54 $3.93 $4.33 $4.72

IRR 30.3% 37.6% 44.9% 52.1% 59.5%

NPV* $821 $1,086 $1,348 $1,609 $1,870

Alternate Case (Non-Acid Plant)

-20% -10% 0 +10% +20%

Cu Price $3.15 $3.54 $3.93 $4.33 $4.72

IRR 31.1% 39.1% 46.6% 54.0% 61.5%

NPV* $691 $957 $1.219 $1,480 $1,741

*million $ at 7.5% discount rate

The impact of the changes compared to the 2016 Feasibility Study can be estimated by comparing the

2022 PFS Base Case at a copper price of $2.75/lb to the Acid Plant case from the 2016 FS at $2.75/lb

copper price (see table below).

2022 Base Case

at $2.75/lb Cu

Price

2016 Acid Plant

Case at $2.75 Cu

Price

Years of Commercial Production 24 24

Total Copper Produced (million lbs) 2,153 2,165

LOM Copper Price (avg $/lb) * $2.75 $2.75

Initial Capital Costs (million $) $45.1 $46.9

Sustaining Capital Costs (million $) $1,026.6 $742

Payback of Capital (pre-tax/after-tax) 7.9/8.0 4.5 / 6.4

Internal Rate of Return (pre-tax/after-tax) 25.8%/23.3% 48.4%/40.2%

Life of Mine Direct Operating Cost ($/pound Cu Recovered) $0.914 $0.65

Acid consumption (lb/lb) 9.53 8.98

Pre-tax NPV at 7.5% discount rate (million $) $769 $1,173

After-Tax NPV at 7.5% discount rate (million $) $590 $808

4

Mineral Resources and Mineral Reserves

Mineral Resource Estimate

The total mineral resource estimate for the North Star Deposit is based on results from 122 drill holes

totalling 158,785 feet and is effective as of October 1, 2016 (unchanged from the original 2016 Feasibility

Study on the Gunnison Project). The estimate is classified as a measured, indicated or inferred mineral

resource, consistent with the CIM definitions referred to in NI 43-101. Excelsior is not aware of any

environmental, permitting, legal, title, taxation, socio-political, marketing or other issues which may

materially affect its estimate of mineral resources.

North Star Resources (Oxide and Transition at 0.05% cut-off)

Category Short Tons (million) Total Copper (%) Pounds of Cu (million)

Measured 199 0.36 1,427

Indicated 674 0.27 3,567

Total M&I 873 0.29 4,995

Inferred 187 0.17 630

Notes:

1. Mineral Resources are inclusive of Mineral Reserves.

2. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

3. Oxidized + Transitional Mineral Resources are reported at a 0.05% total-copper cut-off in consideration

of potential mining by in situ recovery.

The North Star mineral resources were modeled to reflect the detailed lithologic, structural, and oxidation

modeling completed by Excelsior. Copper mineral domains were interpreted on east-west vertical cross

sections on 100-foot spacing, which encompass the 2.3-mile north-south and 1.3-mile east-west extents

of the deposit. These domains were then used to explicitly constrain the estimation of copper grades into

50 x 100 x 25-foot (x, y, z) model blocks using 20-foot composites and inverse-distance interpolation. The

grade estimation is further controlled by the incorporation of search ellipses that reflect the orientations

of modeled structural zones, as well as those of favorable stratigraphic units in areas unaffected by the

structures.

All samples were prepared from manually split half-core sections on-site in Arizona. Split drill core

samples were then sent to Skyline Assayers & Laboratories (“Skyline”) in Tucson, Arizona, an

independent laboratory, for Total Copper and Sequential Copper analyses. Skyline is accredited with

international standard ISO/IEC 17025:2005 General Requirements for the Competence of Testing and

Calibration Laboratories. Analytical results for Total Copper, Acid Soluble Copper, and Cyanide Soluble

Copper were reported. Excelsior has no relationship with Skyline Labs other than Skyline being a service

provider. Standards, blanks, and duplicate assays are included at regular intervals in each sample batch

submitted from the field as part of an ongoing Quality Assurance/Quality Control Program.

Mr. Jeffrey Bickel, C.P.G., with the independent firm Mine Development Associates (MDA) of Reno,

Nevada, is a Qualified Person as defined by NI 43-101 and is responsible for this mineral resource

estimate. He has verified, reviewed and approved the technical disclosure contained in this section of the

news release. Mr. Bickel has verified the data underlying the results by reviewing the drilling, sampling,

assay, and quality assurance and quality control data, as well as the geologic interpretations completed

by Excelsior. Mineral resources that are not mineral reserves do not have demonstrated economic

viability.

5

Mineral Reserve Estimate

The PFS mineral reserve is based on an economic analysis of the mineral resource using a copper price

of $2.75/lb and key parameters developed from prior test work. The economic optimization was

performed on Measured and Indicated Resources at a cut-off grade of 0.05% Total Cu (“CuT”). EBIT

(earnings before interest and tax) was calculated on a resource block-by block-basis using the key

economic and technical parameters. For a column of resource blocks to be included in the reserve, the

capital costs of establishing the wells for those blocks would have to be less than the combine EBIT for

the same blocks. The mineral reserve was estimated after applying engineering and operational design

parameters which removed the thinner and deeper portions of the mineral resource. Internal dilution has

been included in the final mineral reserve estimate. MDA is of the opinion that the mineral reserve

estimate derived in this PFS reasonably quantifies the economical mineralization of the North Star

Deposit. The reserve estimate is as of October 1, 2016 and the mineral reserves presented in the table

below are included in the mineral resource estimate set out above.

North Star Mineral Reserves (Oxide and Transition at 0.05% cut-off)(1)

Category Short Tons (million) Total Copper (%) Pounds of Cu (million)

Probable 782 0.29 4,505

1. 48% of the total copper reserve is considered recoverable

Mr. Neil Prenn, with the independent firm Mine Development Associates (MDA) of Reno, Nevada, is a

Qualified Person as defined by NI 43-101 and is responsible for reviewing and approving this mineral

reserve estimate. He has verified, reviewed and approved the technical disclosure contained in this

section of the news release. Mr. Prenn has verified the data underlying the results by reviewing the

drilling, sampling, assay, and quality assurance and quality control data, as well as the geologic

interpretations completed by Excelsior.

Risks

A number of risks are highlighted in the Report. Those that are more specific to in-situ mining include:

 Potential for lower than predicted (modelled) sweep efficiency.

 Potential for mineral precipitates to restrict flow paths, porosity, and permeability.

 Potential for gas bubbles to restrict flow paths, porosity, and permeability.

 Flushing with neutralized raffinate to remove CO 2 may be less effective than modelled.

 The observed CO 2 attenuation could be masking other wellfield problems.

 Short circuiting can occur through very permeable structures, reducing overall sweep efficiency

and effecting modelled parameters.

Opportunities

Opportunities at Gunnison are also highlighted in the Report. Those that are related to in-situ mining

include:

 Well stimulation has the potential to alleviate or solve CO 2 gas blocking and greatly improve

porosity, permeability, sweep efficiency and flow rates.

 Grouting, down-hole packers, and down-hole flow control valves have the potential to minimize

short circuiting.

 Wellfield optimization including well spacing, pump sizing, borehole diameter, hole configuration

and down-hole differential flow control have the potential to greatly improve wellfield performance.

 Anticipated copper recoveries could be higher than the estimate of 48 percent of total copper,

which would increase total revenue during the life of the mine.

6

 The conversion of the 187.2 million tons of inferred mineral resources to measured or indicated

categories has the potential to increase mineral reserves.

 The Project has high quality limestone resources that could be used to supplement imported lime

in the water treatment process.

Recommendations

A number of recommendations are included in the report aimed at improving wellfield performance,

reducing risk, and tightening up engineering and design prior to construction of the raffinate neutralization

plant. Excelsior intends to investigate and implement these recommendations prior to further

development which include:

 Metallurgical Testwork Recommendations: Investigating in situ leaching with different lixiviants

as opportunities to leach metals without the formation of gypsum.

 Wellfield Recommendations: Conducting experimentation to ensure that neutralized raffinate is

effective in dissolving CO2 in the subsurface while the engineering, procurement, and construction

is at an early stage to enhance the water treatment design criteria.

 Well Stimulation Trials : Well stimulation trials should be undertaken to determine if the

technique(s) have the potential to alleviate or solve CO 2 blocking, improve connectiveness, and

increase flow rates and sweep efficiency. Given that the results of well stimulation have the

potential to reduce the need for raffinate neutralization or change the design criteria for the

neutralization plant, it should be undertaken before or in parallel with design activities on the water

treatment plant. Well stimulation is allowed under Class III Underground Injection Control permits

but requires EPA approval of the stimulation programs.

 Water Treatment: A scope of work and bid package should be assembled to select a water

treatment vendor to design the water treatment system. Selection criteria should favor rapid, low-

cost solutions to demonstrate that the technology is effective in solving the wellfield challenges.

JOHNSON CAMP HEAP LEACH PRELIMINARY ECONOMIC ASSESSMENT

Economic Analysis

The Johnson Camp Mine (“JCM”) has historically been an open pit, heap leach operation since Cyprus

Minerals opened the property in the 1970’s. The operation includes two open pits, a two-stage crushing-

agglomerating circuit, a fully functioning SX-EW plant capable of producing 25 million pounds of cathode

copper per year, a complete set of PLS and raffinate ponds, and full infrastructure (ancillary facilities,

access, power, water, and communications).

Excelsior is exploring re-opening the Burro and Copper Chief pits for open pit mining to produce run-of-

mine (ROM) material that can be placed on a new leach pad (Pad 5) as a means of extracting copper

from the remaining mineral resources within the two pits. A Preliminary Economic Assessment (PEA) has

been completed by M3 with respect to this planned re-opening.

7

Mining of JCM would be by traditional open pit and the highlights of the PEA financial model are tabulated

below assuming a copper price of $4.25/lb. (Year 1 through 5) and $4.00/lb (beyond Year 5).

Mine Life and post mining processing ~5 years

Heap Leach Material Mined 19.64 M ton

Total Copper Grade (CuT%) 0.387%

Acid Soluble Copper Grade (AsCu%) 0.187%

Cu Produced 65.9 M lb

Total Tonnage Mined 34.4 M ton

Initial Capital for new heap leach pad $26.5 million

Initial Mine Capital $14.3 million

Total Operating Cash Cost ($/lb Cu) $2.83

After-Tax NPV/IRR (7.5% discount rate) $7.8M / 13.4%

The table below sets out the sensitivities of the After-Tax NPV and IRR to copper price:

Sensitivity Analysis

Sensitivity -20% -10% 0 +10% +20%

Cu Price $3.40 $3.83 $4.25 $4.67 $5.10

IRR After-Tax (11.2)% (4.8)% 13.4% 29.7% 42.9%

NPV* After-Tax ($38) ($16) $7 $27 $44

*million $ at 7.5% discount rate

The PEA is preliminary in nature and includes inferred mineral resources that are considered too

speculative geologically to have the economic considerations applied to them that would enable them to

be categorized as mineral reserves. There is no certainty that the conclusions reached in the PEA will be

realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

Based on the current pit shell limited mineral resources for the two pits is approximately 61.5 million tons

at a cut-off grade of 0.2% CuT. The amount that is included in the conceptual mine plan over four years

of mining is 19.6 million tons. It is possible that more than the initial 19.6 million tons can be mined from

the JCM open pits if copper prices continue to be favorable.

“With the positive NPV result of the Johnson Camp open pit, heap leach PEA, Excelsior has an

opportunity to increase copper production in the short to medium term with conventional mining and

utilizing our existing Solvent Extraction infrastructure. Infill drilling and capital risk reduction has the

opportunity to further improve JCM economics as we complete the necessary recommendations on our

core Gunnison asset”, says Robert Winton, Sr. VP Operations.

Excelsior management has launched a small drilling program to confirm mineral resources and additional

column leach metallurgical testing to confirm prior test work.

8

Mineral Resources

The JCM Mineral Resources are provided in the table below.

1. The Effective Date of the mineral resources is February 21, 2022.

2. The project mineral resources are comprised of all model blocks at a 0.2 % CuT cut-off that

lie within optimized resource pits.

3. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

4. The estimate of mineral resources may be materially affected by geology, environmental,

permitting, legal, title, taxation, socio-political, marketing, or other relevant issues.

5. Rounding as required by reporting guidelines may result in apparent discrepancies between

tons, grade, and contained metal content.

The estimate is classified as an inferred mineral resource, consistent with the CIM definitions referred to

in National Instrument 43-101. The Johnson Camp Mine mineral resources are entirely classified as

Inferred. This classification is based on the confidence in the underlying data which are largely historical.

Excelsior’s sampling programs in 2016 and 2017 verified the historical data sufficiently to warrant the

Inferred classification, but additional drilling and sampling, as well as more detailed geological modeling,

would be required to allow for higher classification of the project resources.

The JCM copper resources were modeled and estimated using information provided by Excelsior under

Mr. Bickel’s supervision. The information is derived from historical core holes drilled by Cyprus Mining,

Arimetco, Summo USA Corp., and Nord Resources Corp. The drill hole database also includes analyses

performed by Excelsior on the historical core. These data, as well as digital topography of the project

area, were provided to MDA by Excelsior.

Total copper grades, as well as soluble copper ratios, were interpolated using inverse distance, ordinary

kriging, and nearest-neighbor methods. The mineral resources reported herein were estimated by

inverse distance interpolation as this method led to results that most appropriately reflected the drill data

and geology of the deposit. This is particularly true with respect to the estimation of the lowest-grade

areas in the model, where potential over-estimation of volumes could materially impact the resource

estimation at grades close to potential open-pit mining cut-offs. The nearest-neighbor estimation was

completed for the purposes of statistical checking of the various estimation iterations.

The JCM mineral resources have been estimated to reflect potential open-pit extraction and potential

processing by heap leaching. To meet the requirement of the resources having reasonable prospects for

eventual economic extraction, a pit optimization was completed using the parameters summarized in the

table below.

Classification Tons % CuT % CuAs lbs CuT lbs CuAs

Inferred 61,529,000 0.38 0.18 472,167,000 220,189,000