Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

GCOM.V ·

Green Shift Provides Metallurgical Update for the Berlin Deposit with High Recoveries through Membrane Technology

Metallurgy & Processing

Green Shift Provides Metallurgical Update for the Berlin Deposit with High Recoveries

through Membrane Technology

Toronto, Ontario – November 09, 2022 – Green Shift Commodities Ltd. (TSXV: GCOM), (“Green Shift” or the

“Company”) is pleased to announce the results of further test work that show membrane technology being utilized

for testing at the Company’s Berlin Deposit to be highly efficient in separating uranium, battery commodities and

rare earth elements found in the Company’s Berlin Deposit (“Berlin”). Prior test work showed that not only could

membranes significantly reduce the size of the processing plant but could simplify the recovery of phosphoric acid

in comparison to the design modelled in the previous economic assessment of the Project completed in 2013. The

current reported results are from tests undertaken during the second phase of a three -phase testing program ,

completed earlier this year.

Highlights

• The test work was successful in achieving uranium, nickel, vanadium and rare earth element recoveries of

over 95%.

• Phosphoric acid recovery is comparatively lower and other membranes will be tested to improve its

recovery.

• The greater efficiency of membranes in separating rare earth elements could significantly increase the

potential of the Berlin Deposit.

Trumbull Fisher, Director, and CEO commented, “We are very pleased and encouraged by the improved recoveries

achieved by membranes in recovering the green energy metals during metallurgical testing on our Berlin asset.

This asset contains commodities that are critical to the global green movement as we drive towards cleaner sources

of energy and energy storage. In addition, we continue to seek other battery metal assets that would compliment

Berlin’s core commodities and be accretive to our Company’s vision of becoming a go-to source of clean energy

commodities.”

Membrane Efficiency

Test work completed to date demonstrates that membrane separation is a highly efficient process at concentrating

uranium, nickel, vanadium, rare earth elements, molybdenum and zinc from a liquid that was synthesized to match

the pregnant leach solution (“P LS”) – the liquid generated from leaching the mineralized rock - from the Berlin

Deposit. The results show that metals are effectively separated from the PLS. While phosphoric acid recovery is

not as good with the selected membranes , further work will co nsider options to improve this – aiming for a target

range of 80% to 90% recovery.

2

Table 1. Results of membrane test work showing the efficiency of metals and phosphate recovery from a

pregnant liquor solution that simulated a PLS from the Berlin Deposit.

Commodity Percentage Recovery

Option A Option B

Uranium 97.1 99.7

Nickel 97.5 99.9

Vanadium 97.0 99.9

Phosphoric acid 79.3 63.6

Rare Earth Elements 98.5 99.7

Molybdenum 86.5 97.6

Zinc 96.6 99.9

Flow Rate Reduction (%) 90.2 81.2

Next Steps

• In response to the rapid adoption of lithium ferro-phosphate (“LFP”) as safe, reliable batteries by the electric

vehicle industry, it is a priority for the Company to assess the potential cost s/benefits of producing ferro-

phosphate from Berlin. It will be assessed as to whether the phosphate from Berlin can be combined with

iron to form ferro-phosphate for LFP batteries , rather than simply producing phosphoric acid as was

originally contemplated.

• The rapid advances in sensor-based sorting technology requires that this be tested on mineralized material

from Berlin. This technology uses scanners to detect physical and or chemical characteristics of mineral -

bearing components of the crushed rock as it emerges from the mine and uses a jet of compressed air to

remove the mineralized fragments from waste fragments. If this technology works on mineralized material

from Berlin, it could significantly enhance the efficiency, and could potentially lower operating costs, of a

future processing plant.

• Further work is planned to strive to improve the recovery of phosphoric acid from the 63%-70% achieved

so far to a target range of 80% to 90%.

Qualified Person

The information related to membrane systems in this news release has been verified and approved by Johann van

der Westhuysen, MEng, BEng, Managing Director of Synexus (Pty) Ltd, a process engineering services company

that specializes in membrane separation applications in hydrometallurgy. Mr. Van der Westhuysen is registered as

a Professional Engineer (PrEng) (Chemical) with the Eng ineering Council of South Africa and as a Chartered

Chemical Engineer (CEng) with the Institution of Chemical Engineers, Engineering Council of the United Kingdom.

Through this designation, Mr. Van der Westhuysen is a Qualified Person (“QP”) as defined by National Instrument

43-101, Standards of Disclosure for Mineral Projects of the Canadian Securities Administrators. The synthetic PLS

was prepared by, and the membrane test work conducted under the direct control of, the QP. All test samples were

submitted under chain-of-custody for analyses at an accredited laboratory, and all analytical results were received

directly by the QP. The data analysis and the opinions expressed on the data are those of the QP.

For further information o n the Berlin deposit, refer to the technical report entitled “ Technical Report on the Berlin

Uranium – Battery Commodity Deposit, Colombia ” dated April 25, 2022 , which is available under the Company’s

profile on SEDAR at www.sedar.com.

About Green Shift Commodities Ltd.

Green Shift Commodities Ltd . is focused on the exploration and development of commodities needed to help

decarbonize and meet net-zero goals.

3

The Company is developing the Berlin Deposit in Colombia. Apart from uranium, for clean nuclear energy, the Berlin

Deposit contains battery commodities including nickel, phosphate, and vanadium. Phosphate is a key component

of lithium-ion ferro-phosphate (“LFP”) batteries that are being used by a growing list of electric vehicle manufacturers.

Nickel is a component of various lithium-ion batteries, while vanadium is the element used in vanadium redox flow

batteries. Neodymium, one of the rare earth elements contained within the Berlin Deposit, is a key component of

powerful magnets that are used to increase the efficiency of electric motors and in generators in wind turbines.

For further information, please contact:

Trumbull Fisher, CEO, Green Shift Commodities Ltd.

E: [email protected]

Tel: (416) 917-5847

Forward-Looking Statements

This news release includes certain “forward looking statements”. Forward-looking statements consist of statements

that are not purely historical, including statements regarding beliefs, plans, expectations or intensions for the future,

and include, but not limited to, statements with respect to: the potential metallurgical recoveries and results of the

test work; the potential for improving the recovery of phosphate ; the successful reactivation of the Berlin Project;

the future direction of the Company’s st rategy; and other activities, events or developments that are expected,

anticipated or may occur in the future. These statements are based on assumptions, including that: (i) the ability to

achieve positive outcomes from test work; (ii) actual results of our exploration, resource goals, metallurgical testing,

economic studies and development activities will continue to be positive and proceed as planned, ( iii) requisite

regulatory and governmental approvals will be received on a timely basis on terms accept able to Green Shift

Commodities Ltd. (iv) economic, political and industry market conditions will be favourable, and (v) financial markets

and the market for uranium, battery commodities and rare earth elements will continue to strengthen. Such

statements are subject to risks and uncertainties that may ca use actual results, performance or developments to

differ materially from those contained in such statements, including, but not limited to: (1) changes in general

economic and financial market conditions, (2) changes in demand and prices for minerals, (3) the Company’s ability

to source commercially viable reactivation transactions and / or establish appropriate joint venture partnerships, (4)

litigation, regulatory, and legislative developments, dependence on regulatory approvals, and changes in

environmental compliance requirements, community support and the political and economic climate, (5) the inherent

uncertainties and speculative nature associated with exploration results, resource estimates, potential resource

growth, future metallurgical test resu lts, changes in project parameters as plans evolve, (6) competitive

developments, (7) availability of future financing, (8) the effects of COVID -19 on the business of the Company,

including, without limitation, effects of COVID -19 on capital markets, commo dity prices, labour regulations, supply

chain disruptions and domestic and international travel restrictions, (9) exploration risks, and other factors beyond

the control of Green Shift Commodities Ltd. including those factors set out in the “Risk Factors” in our Management

Discussion and Analysis dated May 2, 2022 for the fiscal year ended December 31, 2021 available on SEDAR at

www.sedar.com. Readers are cautioned that the assumptions used in the preparation of such information, although

considered reasonable at the time of preparation, may prove to be imprecise and, as such, undue reliance should

not be placed on forward-looking statements. Green Shift Commodities Ltd. assumes no obligation to update such

information, except as may be required by law.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the

policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this press

release.