Asanko GOLD Reports Q1 2019 Results
PRESS RELEASE
ASANKO GOLD REPORTS Q1 2019 RESULTS
Vancouver, British Columbia, May 8, 2019 – Asanko Gold Inc. (“Asanko” or the “Company”) (TSX, NYSE
American: AKG) reports first quarter (“Q1”) 2019 operating and financial results for the Asanko Gold Mine
(“AGM”), located in Ghana, West Africa. The AGM is a 50:50 joint venture (“JV”) with Gold Fields Ltd (JSE,
NYSE: GFI), which is managed and operated by Asanko. All amounts are in US dollars unless otherwise stated.
Q1 2019 Asanko Gold Mine Highlights (100% basis)
• Produced 60,425 ounces of gold, on track to meet 2019 guidance of 225,000 – 245,000 ounces
• Generated EBITDA1 of $10.1 million and operating cash flows before working capital changes of $10.5
million
• Held unaudited cash of $16.3 million on hand, $7.1 million in receivables from gold sales and $7.1 million
in gold on hand, as at March 31, 2019
• All-in sustaining cost (“AISC”)1 of $1,123/oz, with 2019 guidance of $1,040 – $1,060/oz maintained
• Net loss after tax of $14.1 million including a loss of $13.3 million associated with adjustments to the
carrying value of ore stockpile inventory
Q1 2019 Quarterly Consolidated Financials for Asanko Gold Inc.
• Net loss of $5.3 million including proportional adjustment to net realizable value of the ore stockpiles at
the AGM of $6.0 million
• Adjusted EBITDA1 of $3.1 million
• Held $8.8 million in cash as of March 31, 2019, with the final $20 million cash payment related to the
Gold Field’s transaction expected no later than December 31, 2019
Commenting on the Q1 2019 performance, Greg McCunn, Chief Executive Officer, said: “The Asanko Gold
Mine delivered a solid operational performance producing 60,425 ounces, in line with our guidance for 2019.
Costs for the quarter were impacted by higher trucking costs as we initiated mining operations at the large
scale Esaase deposit. Commercial trucking contracts are now in place and we expect oxide ore from Esaase
to represent 25-30% of the mill feed on an ongoing basis. In addition, we continued with the waste stripping
of Cut 2 at Nkran. This is nearing completion and as the pushback comes to a conclusion in Q3, we forecast
AISC to decline and maintain our full-year AISC guidance of $1,040 – $1,060/oz.
After a thorough review of our current operations in my first month as CEO, I can see that we are in the final
stages of a two year capital investment program, which included a mill expansion from 3Mtpa to 5Mtpa, a
major pushback of the Nkran pit and the initial development of Esaase.
We are now well positioned to start harvesting the benefits of these major investments as we shift our focus
to maximizing cashflow generation from the AGM over the next 18-24 months while we work with our JV
partner on formulating the long-term development plan for Esaase and optimal life of mine plan for the AGM
complex.”
2
Summary of Q1 2019 Asanko Gold Mine Operational and Financial Results
AGM (100% Basis) Q1 2018 Q4 2018 Q1 2019
Waste mined (‘000t) 11,976 8,370 6,584
Ore mined (‘000t) 853 1,370 1,505
Strip ratio (W:O) 15.7 6.1 4.4
Average gold grade mined (g/t) 1.3 1.5 1.4
Mining costs ($/t mined) 3.23 4.13 4.48
Ore treated (‘000t) 1,269 1,238 1,224
Gold feed grade (g/t) 1.3 1.6 1.6
Gold recovery (%) 93 95 93
Processing costs ($/t treated) 11.17 12.39 11.93
Gold production (oz) 48,229 59,823 60,425
Gold sales (oz) 48,899 61,821 53,421
Average realized gold price ($/oz) 1,314 1,215 1,292
Operating cash costs1 ($/oz) 571 811 878
Total cash costs1 ($/oz) 637 872 943
All-in sustaining costs1 ($/oz) 1,226 1,072 1,123
All-in sustaining margin1 ($/oz) 88 143 169
All-in sustaining margin1 ($m) 4.3 8.8 9.0
Revenue ($m) 64.4 74.2 67.0
Income (loss) from mine operations ($m) 19.5 (0.8) (11.9)
Net income (loss) after tax ($m) 4.7 (3.1) (14.1)
EBITDA1 32.3 17.4 10.1
Cash provided by operating activities 20.1 12.9 8.8
Key Operational Highlights of the AGM (on a 100% basis)
• No lost time injuries (“LTI”) were reported during the quarter, and the AGM has now achieved over 24
months and more than 12.3 million employee hours worked without a single LTI.
• Waste stripping of the Cut 2 pushback at Nkran advancing towards final stages, expected to be complete
in Q3 2019.
• Achieved steady state levels of production at Esaase in February 2019, with ore mining rates averaging
147,500 tonnes per month over February and March at an average grade of 1.3 g/t.
• Trucking costs for the quarter were elevated as contractors at Esaase transitioned from road
construction activities to ore haulage activities. Effective April 1, 2019, commercial contracts in place
and ore haulage costs expected to reduce to planned levels of $7.00-$7.50 per tonne hauled.
• Notice of the JV’s intention to halt mining activities at Akwasiso was initiated during the quarter.
JV Financial Performance
• The AGM incurred operating cash costs per ounce1 of $878, total cash costs per ounce1 of $943 and
AISC1 of $1,123 in Q1 2019. These costs include a $248/oz impact associated with adjustments to the
carrying value of ore stockpile inventory and a $32/oz impact due to the Ghanaian Government’s 5%
non-refundable levy on certain goods and services.
3
• Cash costs were higher in Q1 2019, compared to Q1 2018, partly due to fewer waste tonnes being
capitalized to stripping costs. During the quarter, only $2.9 million of stripping costs were deferred
compared to Q1 2018 when the Eastern portion of Cut 2 at Nkran was underway, which resulted in $26.1
million of stripping costs being deferred and excluded from cash costs.
• Cash costs for the quarter were also impacted by unusually high trucking rates at Esaase as contractors
were transitioning from road construction activities to ore haulage activities. These factors were
partially offset by higher gold sales volumes which decreased fixed production costs on a per unit basis.
• AlSC for Q1 2019 were lower compared to Asanko’s AISC for Q1 2018 predominantly due to a $479/oz
reduction in capitalized stripping costs, associated with the Eastern portion of Cut 2 at Nkran, and higher
gold sales volumes which decreased fixed costs on a per unit basis, partly offset by the previously
described higher cash costs. While there are no comparative AISC metrics reported for the AGM on a
standalone basis in Q1 2018, Asanko’s AISC for Q1 2018 included corporate G&A costs of $33/oz.
• Q1 2019 gold sales of 53,421 ounces at an average realized gold price of $1,2 92/oz generating
gold sales of $69.0 millon. Gold sales were impacted by a change in the reporting period, which
shortened the quarter to 83 days instead of the normal 90 days. This is a once-off timing adjustment.
Revenue in Q1 2019 amounted to $67.0 million and includes by-product sales of $0.2 million and is
reported net of $2.2 million of gold sales that were capitalized in relation to Esaase pre-production
activities in January 2019.
• Total cost of sales (including depreciation and depletion and royalties) amounted to $78.9 million, an
increase of $34.0 million from Q1 2018. The increase in production costs was primarily driven by an
adjustment to the carrying value of the AGM’s stockpile inventory to reflect the net realizable value of
stockpiled ore, a one-time contract termination fee relating to one of the JV’s mining contractors, the
introduction of ore trucking from Esaase to the processing facility, as well as higher gold ounces sold.
Additionally, depreciation and depletion during Q1 2019 accounted for $10.1 million of the increase in
cost of sales, compared to Q1 2018, primarily due to the depletion of mineral interests related to Esaase,
which commenced commercial operations in February 2019, while depreciation of right-of-use assets
commenced in Q1 2019 following the capitalization of mining contractor leases in accordance with IFRS
16 – Leases.
• Generated cash flow from operations of $8.8 million and $10.5 milion before working capital changes.
• The JV generated EBITDA1 of $10.1 million in Q1 2019.
• The AGM’s net loss after tax for the quarter amounted to $14.1 million, compared to net income of $4.7
million in Q1 2018. The reduction in net income was due mainly to lower mine operating earnings in Q1
2019 as discussed above, partially offset by a reduction in deferred income tax expense and interest
expense, the latter resulting from the settlement of the Red Kite debt in July 2018.
• At quarter end, the JV had unaudited cash of $16.3 million on hand, $7.1 million in receivables from gold
sales and $7.1 million in gold on hand.
Asanko Gold Inc. – Summary Q1 2019 Financial Results
Consolidated Q1 2018 Q4 2018 Q1 2019
Net income (loss) attributable to
common shareholders ($m)
2.1 (0.9) (5.3)
Net income (loss) per share attributable to
common shareholders
$0.01 ($0.00) ($0.02)
Adjusted EBITDA1 ($m) 30.9 6.1 3.1
4
• The Company reported a net loss of $5.3 million in Q1 2019 compared to net income attributable to
common shareholders of $2.1 million in Q1 2018. The reduction in net income for Q1 2019 was
predominantly the result of the reduction in mine operating earnings of the AGM, resulting in the JV
reporting a net loss of $14.1 million, of which the Company recognized its share of $6.4 million. This was
partly offset by the recognition of $1.1 million in service fees (net of withholding tax) earned as
operators of the JV and $2.4 million of finance income relating to the fair value adjustment of the
Company’s preferred share investments in the JV.
• Reported Adjusted EBITDA1 of $3.1 million for Q1 2019 compared to $30.9 million in Q1 2018. The
decrease in Adjusted EBITDA1 was primarily a result of the higher cash costs incurred by the AGM, as
well as a reduction in the Company’s interest in the AGM from 100% to 45%. These factors were partly
offset by an increase in the AGM’s revenue.
2019 Outlook
The Asanko Gold Mine is on track to meet 2019 guidance of 225,000 – 245,000 ounces at AISC1 of $1,040 –
$1,060/oz.
Since the announcement of the JV transaction, Asanko’s technical team, together with input from Gold Fields,
have been reviewing the current Life of Mine plan. This includes a number of scenarios for the long-term
development of the Esaase deposit, utilizing knowledge gained from the recent initiation of minining
operations, as well as the exploration potential of the AGM’s land package, particularly the highly prospective
South Camp tenements. The JV partners are currently considering an optimal work plan and timing required
to deliver an updated Life of Mine plan for the AGM and expect to update the market further in H2 2019.
This news release should be read in conjunction with Asanko’s Management’s Discussion and Analysis
and the Condensed Consolidated Interim Financial Statements for the three months ended
March 31, 2019, which are available at www.asanko.com and filed on SEDAR.
Notes:
1 Non-GAAP Performance Measures
The Company has included certain non -GAAP performance measures in this press release. These non-GAAP
performance measures do not have any standardized meaning. Accordingly, these performance measures are intended
to provide additional information and should not be considered in isolation or as a substitute for measures of
performance prepared in accordance with GAAP. Refer to the Non-GAAP Measures section of Asanko’s Management
Discussion and Analysis for an explanation of these measures and reconciliations to the Company’s reported financial
results in accordance with IFRS.
• Operating Cash Costs per ounce and Total Cash Costs per ounce
Operating cash costs are reflective of the cost of production, adjusted for share-based payments and by-product
revenue per ounce of gold sold. Total cash costs include production royalties of 5%.
• All-in Sustaining Costs Per Gold Ounce
The Company has adopted the reporting of “all-in sustaining costs per gold ounce” (“AISC”) as per the World Gold
Council’s guidance. AISC include total cash costs, corporate overhead expenses, sustaining capital expenditure,
capitalized stripping costs and reclamation cost accretion per ounce of gold sold.
• Adjusted net income attributable to common shareholders
The Company has included the non-GAAP performance measures of adjusted net income (loss) attributable to
common shareholders and adjusted net income (loss) per common share. Neither adjusted net income nor adjusted
net income per share have any standardized meaning and are therefore unlikely to be comparable to other measures
presented by other issuers. Adjusted net income excludes certain non-cash items from net income or net loss to
provide a measure which helps the Company and investors to evaluate the results of the underlying core operations
of the Company and its ability to generate cash flows and is an important indicator of the strength of our operations
and the performance of our core business.
5
• Adjusted EBITDA
EBITDA provides an indication of the Company’s continuing capacity to generate income from operations before
taking into account the Company’s financing decisions and costs of amortizing capital assets. Accordingly, EBITDA
comprises net income (loss) excluding interest expense, interest income, amortization and depletion, and income
taxes. Adjusted EBITDA adjusts EBITDA to exclude non-recurring items and to include the Company’s interest in the
adjusted EBITDA of the JV. Other companies and JV partners may calculate EBITDA and Adjusted EBITDA differently.
Qualified Person Statement
Frederik Fourie (Pr.Eng), Asanko Senior Mining Engineer, is the Asanko Qualified Person, as defined by
Canadian National Instrument 43-101 (Standards of Mineral Disclosure), who has approved the preparation
of the technical contents of this news release.
Enquiries:
Alex Buck – Investor & Media Relations
Toll-Free (N.America): 1-855-246-7341
Telephone: +44 7932 740 452
Email: [email protected]
About Asanko Gold Inc.
Asanko’s flagship project, located in Ghana, West Africa, is the jointly owned Asanko Gold Mine with Gold
Fields Ltd, which Asanko manages and operates. The Company is strongly committed to the highest standards
for environmental management, social responsibility, and health and safety for its employees and
neighbouring communities. For more information, please visit www.asanko.com.
Forward-Looking and other Cautionary Information
This release includes certain statements that may be deemed "forward-looking statements". All statements in this
release, other than statements of historical facts, that address estimated resource quantities, grades and contained
metals, possible future mining, exploration and development activities, are forward-looking statements. Although the
Company believes the forward-looking statements are based on reasonable assumptions, such statements should not
be in any way construed as guarantees of future performance and actual results or developments may differ materially
from those in the forward-looking statements. Factors that could cause actual results to differ materially from those in
forward-looking statements include market prices for metals, the conclu sions of detailed feasibility and technical
analyses, the timely renewal of key permits, lower than expected grades and quantities of resources, mining rates and
recovery rates and the lack of availability of necessary capital, which may not be available to the Company on terms
acceptable to it or at all. The Company is subject to the specific risks inherent in the mining business as well as general
economic and business conditions. For more information, investors should review the Company's Annual Form 40-F filing
with the United States Securities Commission and its home jurisdiction filings that are available at www.sedar.com.
Neither Toronto Stock Exchange nor the Investment Industry Regulatory Organization of Canada accepts responsibility
for the adequacy or accuracy of this release.
Cautionary Note to US Investors Regarding Mineral Reporting Standards:
Asanko has prepared its disclosure in accordance with the requirements of securities laws in effect in Canada, which
differ from the requirements of US securities laws. Terms relating to mineral resources in this press release are defined
in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects under the guidelines set
out in the Canadian Institute of Mining, Metallurgy, and Petroleum (the “CIM Council”) Standards on Mineral Resources
and Mineral Reserves (the “CIM Definition Standards”). The Securities and Exchange Commission (the “SEC”) has
adopted amendments to its disclosure rules to modernize the mineral property disclosure requirements for issuers whose
securities are registered with the SEC. As a result of the adoption of the SEC Modernization Rules, SEC will now recognize
estimates of “measured mineral resources”, “indicated mineral resources” and “inferred mineral resources” that are
“substantially similar” to the corresponding terms under the CIM Definition Standards. In addition, the SEC has amended
its definitions of “proven mineral reserves” and “probably mineral reserves ” to be “substantially similar” to the
corresponding CIM Definitions. United States investors are cautioned that while the above terms are “substantially
similar” to CIM Definitions, there is no assurance any mineral reserves or mineral resources that the Company may report
as ”proven reserves”, “probable reserves”, “measured mineral resources”, “indicated mineral resources” and “inferred
mineral resources” under NI 43-101 would be the same had the Company prepared the reserve or resource estimates
under the standards adopted under the SEC Modernization Rules.