Asanko Gold Mine Construction Update

Mine Development & Operations

Highlights:

  • Phase  1  construction  60%  complete  and  on  schedule  for  first  gold  in  Q1  2016.
  • Full  mining  fleet  mobilized  and  achieving  above  planned  production  levels  +/-­‐  100,000  tonnes  per  day.
  • Pit  dewatering  over  55%  complete  and  water  levels  reduced  by  24.3  metres.
  • Installation  of  SAG  &  Ball  Mills  underway.
  • Project  tracking  budget  with  US$138  million  of  the  US$295  million  capital  cost  spent.

Vancouver,  British  Columbia,  July  13,  2015  –  Asanko  Gold  Inc.  (“Asanko”  or  the  “Company”)  (TSX,  NYSE   MKT:   AKG)  is  pleased  to  provide  a  construction  update  on  the  fully  funded  Phase  1  of  the  Asanko  Gold Mine  (“AGM”  or  the  “Project”)  in  Ghana.    Phase  1  will  be  a  low  cost,  long  life  mine  producing  190,000 ounces  of  gold  per  annum  at  steady  state,  with  the  first  gold  pour  on  track  for  Q1  2016.

Project   construction   remains   on   schedule   with   60%   of   the   overall   project   complete   and   around   2,443 employees  and  contractors  on  site,  as  at  the  end  of  June  2015.    Concrete  civils  are  66%  complete  and  steel, mechanical  and  platework  54%  complete.    All  critical  path  items  are  in  hand  and  on  time.    Procurement  is practically   complete   with   US$286   million   committed   out   of   the   total   capital   budget   of   US$295   million. US$138  million  has  been  spent  up  to  June  30,  2015.    The  latest  videos  and  photographs  are  available  at http://www.asanko.com/projects/photo-­‐gallery.

Peter  Breese,  President  and  CEO,  commented:  “Construction  of  Phase  1  continues  to  advance  according  to   plan  and  budget,  which  is  very  encouraging.    Mining  operations  have  hit  their  stride  with  the  entire  PW   mining   fleet   fully   mobilized   and   current   mining   levels   exceeding   the   plan.   The   plant   site   construction   is   progressing  very  well  and  with  the  Project  now  nearing  2/3rds  completion,  we  remain  confident  that  we  will   be  able  to  deliver  this  project  on  time  and  within  the  capital  budget  of  US$295  million.”      

Construction  Update  

The   primary   crusher   foundations  were  completed  in  June  and  the  structural,  mechanical  and  platework installation  has  commenced.  The  installation  of  the  Jaw  crusher  is  expected  to  be  completed  by  the  end  of July.    The  concrete  work  for  the  run-­‐of-­‐mine  tip  wall  at  the  primary  crusher,  as  well  as  the  reinforced  earth wall  is  still  under  construction  and  due  for  completion  by  the  end  of  Q3  2015.    The  primary  tip  bin  erection has  commenced  and  will  be  completed  in  parallel.

Earthworks  for  the  overland  conveyor  from  the  primary  crusher  to  the  stockpile  tunnel  were  completed  in June  and  the  concrete  precast  sleeper  foundations  are  being  placed.  The  conveyor  installation  is  expected to  commence  this  month.  Concrete  work  on  the  stockpile  tunnel  has  been  completed  and  installation  of the  apron  feeder  and  other  mechanical  equipment  is  scheduled  to  commence  in  mid-­‐July.

The  foundations  for  the  SAG  and  Ball  Mills  were  completed  in  early  June  and  installation  of  the  mills  has commenced  with  a  planned  completion  date  of  November.  Both  the  SAG  and  Ball  Mills  are  on  site,  along with  all  the  major  ancillary  pieces  of  equipment.

All   seven   CIL   tanks   and   the   cyanide   detoxification   tank   have   been   fully   erected,   painted   and   welded. Interconnecting   steel   and   platework   is   underway   and   due   for   completion   by   the   end   of   Q3   2015.     The mechanical  installation  of  the  agitators  and  inter-­‐stage  carbon  screens  will  follow.    Access  to  Electrical  and Instrumentation  (“E&I”)  and  Piping  contractors  to  this  area  is  expected  to  be  given  at  the  end  of  July.

Steelwork   on   the   pre-­‐leach   thickener   has   been   completed   and   welding   and   platework   are   in   the   final stages,  with  completion  expected  in  the  next  few  weeks.  The  thickener  bridge  is  scheduled  to  arrive  on  site mid-­‐July  and  erection  planned  to  take  place  in  August.

The  reagents  building  and  store  room  are  progressing  well,  all  the  steel  work  is  erected  and  most  of  the tanks  have  been  installed.    Platework  is  over  90%  complete  and  installation  of  the  pipe  and  cable  racks  has commenced.    The  sheeting  for  the  buildings  is  expected  to  arrive  on  site  in  July  and  be  installed  at  that time.

The  Gold  Room  platework  is  over  half  way  towards  completion  and  is  expected  to  be  fully  complete  in October.

The  Tailings  Storage  Facility  (“TSF”)  continues  to  progress  well,  with  over  67%  of  earthworks  complete  and over  60%  of  the  HDPE  liner  installed.    The  northern  portion  is  complete  and  work  is  now  focusing  on  the southern  portion  of  the  facility.  The  TSF  is  on  track  for  completion  during  Q4  2015.    The  tailings  pipeline trench   construction   is   expected   to   commence   in   early   August   and   is   scheduled   to   be   completed   in November.

The   E&I   work   has   commenced   in   the   Reagents   area   and   on   the   pipe   gantries.     All   remaining   major equipment,   such   as   elution   heating,   emergency   generator,   transformers,   medium   voltage   switchgear, gravity  concentrator  and  remaining  structural  steel  is  expected  to  arrive  by  mid-­‐August,  ahead  of  the  final stages  of  installation.    Terracing,  drains  and  buried  services  for  the  entire  plant  site,  including  the  footprint for  the  Phase  2  expansion  project,  are  scheduled  to  be  completed  by  the  end  of  July.    All  other  ancillary services,  such  as  change  house,  workshop,  raw  water  dam  and  pollution  control  dam,  are  on  schedule.

Power  

Bush  clearing  for  the  161kV  line  has  now  been  completed.    Foundation  work  for  the  82  towers  along  the 30km   long   power   line   is   underway,   with   65   tower   foundations   excavated   and   55   tower   foundations completed.    12  towers  have  already  been  erected  and  the  remaining  tower  erection  is  due  for  completion in  October.  The  medium  voltage  substation  is  well  advanced  and  nearing  completion.

In   June   2015   Asanko   signed   a   life   of   mine   power   purchase   agreement   with   the   independent   power producer   Genser   Energy   Ghana   Limited   (“Genser”)   which   has   considerably   de-­‐risked   the   supply   of   long term  power  to  the  mine.    Genser  will  build  and  operate  a  19.2  megawatts  (“MW”)  liquid  fuel  power  plant adjacent  to  the  AGM  site  and  supply  17MW  of  nominal  power  to  Phase  1  on  a  fixed-­‐price,  life-­‐of-­‐mine contract.  Until  the  on-­‐site  power  plant  is  completed,  which  is  expected  by  April  2016,  Genser  will  provide interim   power   via   temporary   generating   facilities.     Bush   clearing   for   the   Genser   power   plant   has   been completed  and  construction  of  the  terrace  is  underway  and  due  for  completion  by  the  end  of  Q3  2015.

Mining  

Pre-­‐stripping  of  the  Nkran  Pit,  the  main  mineral  resource  for  Phase  1  continues  to  advance  according  to schedule.    PW  Ghana  have  now  mobilized  the  entire  mining  fleet,  consisting  of  four  production  shovels,  18 CAT  777,  8  CAT  773  trucks  as  well  as  seven  drill  rigs  in  readiness  for  drill  and  blast  operations,  which  are  due to  commence  during  Q3  2015.    Mining  activities  are  operating  24  hours  a  day  and  production  levels  have reached  100,000  tonnes  per  day,  which  is  approximately  10%  above  the  planned  mining  rates.

The  contractor  has  mined  7.9  million  tonnes  (“Mt”)  from  the  pit  as  at  the  end  of  June,  representing  36%  of the  planned  pre-­‐strip.    Approximately  20,803  tonnes  of  ore  at  a  grade  of  1.87  g/t  have  been  mined  during the  pre-­‐strip  and  have  been  placed  on  the  run-­‐of-­‐mine  pad.    Prior  to  milling  operations  commencing  in  Q1 2016,  it  is  planned  to  have  423,000  tonnes  of  ore  grading  2.09  g/t  on  the  stockpiles.

Pit  dewatering  has  continued  to  advance  ahead  of  the  mining  operations  with  3.36  million  cubic  metres  of the  expected  6  million  cubic  metres  of  water  now  pumped  from  the  Nkran  pit  (approximately  56%).    Since the  start  of  dewatering  in  December  2014,  the  water  level  has  dropped  by  approximately  24.3  metres.

Health  and  Safety    

Following  the  recent  fatal  accident  within  the  pit  all  employees  and  contractors  have  undergone  health  and safety  re-­‐inductions.  In  addition,  Asanko  has  investigated  the  accident  and  completed  a  full  review  of  all  of its   safety   and   health   procedures   and   processes.   Appropriate   remedial   action   plans   have   been   fully implemented.

Procurement    

Procurement  is  practically  complete  with  approximately  US$286  million  committed  to  orders  and  contracts, of   which   US$138   million   has   been   spent   as   at   June   30   2015.   All   remaining   equipment   and   materials deliveries,  none  of  which  are  on  the  project  critical  path,  are  on  schedule.

Partial  Relocation  of  Nkran  Village  

The  partial  relocation  of  the  Nkran  village  (88  building  structures)  continues  to  progress  on  schedule.  Local contractors  are  undertaking  the  construction  of  the  new  buildings,  with  around  450  local  villagers  being employed  on  the  project.  The  construction  of  the  housing  terraces  is  complete  and  51  house  structures have  already  been  built,  with  80%  of  these  houses  currently  being  fitted  with  plumbing  and  electrics.  An additional  37  houses  are  between  foundation  and  lintel  level.    Asanko  is  also  building  a  community  center, a  school  and  a  football  field.  The  relocation  remains  on  track  for  completion  by  the  end  of  Q3  2015.

Funding    

The  Company  has  drawn  the  remaining  amounts  under  the  project  debt  facility  with  Red  Kite  Mine  Finance so  the  full  US$130  million  facility  is  now  drawn.  The  Company  is  fully  funded  to  cash  flow  positive  in  Q2 2016  with  approximately  US$229  million  in  cash  on-­‐hand  as  at  June  30,  2015  plus  a  US$20  million  cost-­‐ overrun  facility  for  total  available  funding  of  approximately  US$249  million.  The  remaining  use  of  funds  is US$209  million  which  includes  US$180  million  for  the  project,  US$23  million  in  working  capital  and  US$6 million  in  corporate  costs  until  commercial  production  is  achieved.    The  Company  therefore  has  a  current funding  buffer  of  US$40  million.

Enquiries:  

For  further  information  please  visit:  www.asanko.com,  email:  [email protected]  or  contact:

Alex  Buck,  Manager  –  Investor  Relations   Wayne  Drier  -­‐  Executive,  Corporate  Development Toll-­‐Free  (N.America):  1-­‐855-­‐246-­‐7341   Telephone:  +1-­‐778-­‐729-­‐0614 Telephone:  +44-­‐7932-­‐740-­‐452   Email:  [email protected] Email:  [email protected]

About  Asanko  Gold  Inc.  

Asanko’s  vision  is  to  become  a  mid-­‐tier  gold  mining  company  that  maximizes  value  for  all  its  stakeholders. The  Company’s  flagship  project  is  the  multi-­‐million  ounce  Asanko  Gold  Mine  located  in  Ghana,  West  Africa. The  mine  is  being  developed  in  phases.  Phase  1  is  fully  financed,  permitted  and  under  construction.    First gold  is  expected  in  Q1  2016,  with  steady  state  production  of  190,000  ounces  per  annum  in  Q2  2016.

Asanko  is  managed  by  highly  skilled  and  successful  technical,  operational  and  financial  professionals.  The Company   is   strongly   committed   to   the   highest   standards   for   environmental   management,   social responsibility,  and  health  and  safety  for  its  employees  and  neighbouring  communities.

Forward-­‐Looking  and  other  Cautionary  Information

This   release   includes   certain   statements   that   may   be   deemed   "forward-­‐looking   statements".   All   statements   in   this   release,  other  than  statements  of  historical  facts,  that  address  estimated  resource  quantities,  grades  and  contained   metals,  possible  future  mining,  exploration  and  development  activities,  are  forward-­‐looking  statements.  Although  the   Company  believes  the  forward-­‐looking  statements  are  based  on  reasonable  assumptions,  such  statements  should  not   be  in  any  way  construed  as  guarantees  of  future  performance  and  actual  results  or  developments  may  differ  materially   from  those  in  the  forward-­‐looking  statements.  Factors  that  could  cause  actual  results  to  differ  materially  from  those  in   forward-­‐looking   statements   include   market   prices   for   metals,   the   conclusions   of   detailed   feasibility   and   technical   analyses,  the  timely  renewal  of  key  permits,  lower  than  expected  grades  and  quantities  of  resources,  mining  rates  and   recovery  rates  and  the  lack  of  availability  of  necessary  capital,  which  may  not  be  available  to  the  Company  on  terms   acceptable  to  it  or  at  all.  The  Company  is  subject  to  the  specific  risks  inherent  in  the  mining  business  as  well  as  general   economic   and   business   conditions.   For   more   information   on   the   Company,   Investors   should   review   the   Company's   annual  Form  20-­‐F  filing  with  the  United  States  Securities  Commission  and  its  home  jurisdiction  filings  that  are  available   at  www.sedar.com.  

Neither  Toronto  Stock  Exchange  nor  the  Investment  Industry  Regulatory  Organization  of  Canada  accepts  responsibility   for  the  adequacy  or  accuracy  of  this  release.  

Cautionary  Note  to  U.S.  Investors  Regarding  Mineral  Reporting  Standards:  

Asanko  has  prepared  its  disclosure  in  accordance  with  the  requirements  of  securities  laws  in  effect  in  Canada,  which   differ  from  the  requirements  of  US  securities  laws.  Terms  relating  to  mineral  resources  in  this  press  release  are  defined   in  accordance  with  National  Instrument  43-­‐101  -­‐  Standards  of  Disclosure  for  Mineral  Projects  under  the  guidelines  set   out   in   the   Canadian   Institute   of   Mining,   Metallurgy,   and   Petroleum   Standards   on   Mineral   Resources   and   Mineral   Reserves.    The  Securities  and  Exchange  Commission  (the  “SEC”)  permits  mining  companies,  in  their  filings  with  the  SEC,   to  disclose  only  those  mineral  deposits  that  a  company  can  economically  and  legally  extract  or  produce.    Asanko  uses   certain  terms,  such  as,  “measured  mineral  resources”,  “indicated  mineral  resources”,  “inferred  mineral  resources”  and   “probable  mineral  reserves”,  that  the  SEC  does  not  recognize  (these  terms  may  be  used  in  this  press  release  and  are   included   in   the   public   filings   of   Asanko   which   have   been   filed   with   securities   commissions   or   similar   authorities   in   Canada).