Asanko Gold Mine Construction Update

Mine Development & Operations

Highlights:

  • Phase  1  Project  is  75%  complete  and  slightly  ahead  of  schedule  for  first  gold  in  early  Q1  2016.
  • Mine  operations  running  at  long-­‐term,  steady  state  capacity  with  drilling,  blasting  and  grade  control fully  operational.
  • Nkran  pit  pre-­‐stripping  over  60%  complete  and  proceeding  according  to  plan.
  • Placement  of  major  equipment  completed  including  crusher,  SAG  mill  &  ball  mill.
  • Tailings  storage  facility  95%  complete.
  • Dedicated  power  supply  to  the  mine  to  be  operational  in  November.
  • Partial  relocation  of  Nkran  village  completed  and  formally  handed  over  to  local  community.
  • Procurement  complete,  Project  on  budget  with  US$180  million  of  the  US$295  million  capital  cost  spent.

Vancouver,  British  Columbia,  September  16,  2015  –  Asanko  Gold  Inc.  (“Asanko”  or  the  “Company”)  (TSX,   NYSE  MKT:  AKG)  is  pleased  to  provide  a  construction  update  on  Phase  1  of  the  Asanko  Gold  Mine  (“AGM” or  the  “Project”)  in  Ghana  which  is  nearing  completion.    Phase  1  will  be  a  low  cost,  long  life  mine  producing 190,000  ounces  of  gold  per  annum  at  steady  state,  with  the  first  gold  pour  on  track  for  early  Q1  2016.    The latest  videos  and  photographs  are  available  at  http://www.asanko.com/projects/photo-­‐gallery.

The  Project  continues  to  advance  with  three  quarters  of  the  overall  project  complete  and  around  2,400 employees   and   contractors   on   site,   as   at   the   end   of   August   2015.     Concrete   civils,   steel   erection, mechanical  and  platework  are  nearing  completion  whilst  piping  and  Electrical  and  Instrumentation  (“E&I”) are  well  underway.

Peter  Breese,  President  and  CEO,  commented  on  the  status  of  the  construction  of  Phase  1:  “The  current   level   of   activity   and   energy   at   the   Project   site   is   tremendous   and   we   have   achieved   some   significant   milestones  since  our  last  update,  including  the  installation  of  the  primary  crusher  and  the  mill  shells.    

The   completion   and   handover   of   88   new   houses   as   part   of   the   partial   village   relocation   is   a   major   achievement  and  one  that  was  done  in  close  collaboration  with,  and  support  from,  the  local  community.  

Overall,  the  project  is  currently  on  budget  and  tracking  a  few  weeks  ahead  of  the  original  schedule.    As  such,   the  focus  is  now  shifting  to  the  commissioning  plan  to  ensure  the  successful  start-­‐up  and  ramp-­‐up  of  Phase   1  operations.”      

Mining  Update  

Pre-­‐stripping  of  the  Nkran  Pit,  the  main  mineral  resource  for  Phase  1,  continues  to  advance  according  to schedule.     Hard   rock   was   reached   in   August,   when   drill   and   blast   operations   commenced.   Mining operations  are  running  at  planned  production  levels  of  80,000  to  90,000  tonnes  per  day  which  are  in  line with  the  long-­‐term,  steady  state  life  of  mine  plan.    The  on-­‐site  explosive  magazine  was  commissioned  in early  September  and  is  now  fully  operational.    Blasting  has  been  limited  to  the  Western  and  Southern  sides of  the  pit  pending  the  completion  of  the  partial  relocation  of  the  Nkran  village  which  is  now  complete.

The  contractor  has  mined  12  million  tonnes  from  the  pit  as  at  the  end  of  August,  representing  over  60%  of the  planned  pre-­‐strip.    Approximately  53,000  tonnes  of  ore  at  a  grade  of  1.62  g/t  have  been  mined  during the  pre-­‐strip  and  placed  on  the  run-­‐of-­‐mine  pad.  This  ore  mined  was  previously  categorized  as  inferred resources   that   were   not   included   in   the   Mineral   Reserve   Estimate.   Grade   control   drilling,   assaying   and reconciliation  procedures  are  operational  and  functioning  well.    Prior  to  milling  operations  commencing,  it is  planned  to  have  over  400,000  tonnes  of  ore  at  reserve  grade  on  the  stockpiles,  which  is  in  excess  of  one month’s  production  requirements.

Pit  dewatering  has  continued  to  advance  ahead  of  the  mining  operations  with  4.6  million  cubic  metres  of the  expected  6  million  cubic  metres  of  water  now  pumped  from  the  Nkran  pit  (approximately  77%).  The  pit is  expected  to  be  empty  in  November.    Pit  dewatering  boreholes  are  currently  being  drilled  and  will  be operational  as  required  during  Q4  2015.

Construction  

Installation  of  the  primary  crusher  has  been  completed,  with  work  focusing  on  the  completion  of  structural, mechanical  and  platework.  The  concrete  work  for  the  run-­‐of-­‐mine  tip  wall  and  erection  of  the  primary  tip bin  at  the  primary  crusher  has  also  been  completed.      Installation  of  the  apron  feeder  and  other  mechanical equipment  is  underway.  The  stockpile  feed  conveyor  is  due  to  be  finished  by  the  end  of  September.    The stockpile  tunnel  is  complete  and  the  mill  feed  conveyor  is  being  assembled.    It  is  expected  that  the  crusher and  stockpile  will  be  ready  for  commissioning  on  low-­‐grade  ore  in  Q4  2015.

In  the  milling  section,  the  shells  for  both  the  SAG  and  ball  mills  have  been  installed  and  the  associated steelwork  is  nearing  completion.    The  SAG  mill  discharge  sump  is  in  place  as  well  as  the  vibrating  screens. Mechanical   installation   of   the   gravity   circuit   and   hydro-­‐cyclones   will   begin   in   September.     All   milling equipment  is  now  on  site  and  ready  for  installation.

The  carbon-­‐in-­‐leach  circuit  is  continuing  to  progress  with  all  seven  tanks  fully  erected  and  interconnecting steel   and   platework   also   in   place.   The   mechanical   installation   of   the   agitators   and   inter-­‐stage   carbon screens  will  begin  this  month.  Welding  and  platework  on  the  pre-­‐leach  thickener  has  been  completed  and the  thickener  has  now  been  internally  sandblasted  and  painted.    Mechanical  installation  of  the  pre-­‐leach thickener  mechanism  is  expected  to  be  completed  in  September,  with  piping  well  underway.

The  reagents  preparation  area  is  nearing  completion,  with  installation  of  piping,  cable  racks,  cabling  and electrical  installation  planned  to  finish  this  month.

The  Tailings  Storage  Facility  (“TSF”)  is  over  95%  complete  and  will  be  inspected  by  an  independent  third party  in  October.    The  final  inspection  report  will  allow  the  Company  to  meet  its  last  permit  condition  and the  TSF  will  be  ready  to  accept  tailings.    The  tailings  pipeline  construction  is  60%  complete  and  on  schedule for  completion  in  October.    It  is  expected  that  the  TSF  will  be  utilized  for  storing  water  for  use  in  the  start-­‐ up  and  commissioning.

E&I  is  underway  in  all  areas  and  progressing  well.  The  mill  control  room  is  in  position,  along  with  the  main Motor  Control  Centers  for  the  milling  operations.    Wiring  and  cables  are  being  run  to  the  main  electrical drives  including  the  mill  motors.    Construction  of  the  medium  voltage  substation  is  complete  and  is  being connected  to  the  low  voltage  side  of  the  161kV  substation.

All  other  ancillary  services,  such  as  change  house,  workshop,  raw  water  dam  and  pollution  control  dam, continue  to  advance  according  to  schedule.

Power  

In  June  2015  Asanko  signed  a  life  of  mine,  fixed-­‐priced  power  purchase  agreement  with  the  independent power  producer  Genser  Energy  Ghana  Limited  (“Genser”)  for  the  supply  of  17  megawatts  (“MW”)  to  Phase

1.  Earthworks  for  Genser’s  liquid  fuel  power  plant,  adjacent  to  the  AGM  site,  have  commenced  and  are expected  to  be  completed  in  September,  after  which  the  main  construction  of  the  power  plant  will  begin.

Commissioning  of  the  power  plant  is  targeted  for  April  2016.

Until  the  main  power  plant  is  operational,  Genser  will  provide  temporary  power  to  Phase  1  via  five  5MW semi-­‐mobile  liquid  natural  gas  fired  generator  units.    The  five  generators  are  expected  to  arrive  on  site  in October  and  will  take  approximately  2  weeks  to  install  and  commission.    All  necessary  permits  have  been obtained  for  the  temporary  power  generators  and  power  is  expected  to  be  available  in  November,  ahead  of commissioning  and  start-­‐up  activity.

In  addition  to  the  dedicated  power  plant,  the  Company  has  also  constructed  a  161kV  power  line  which connects  to  the  main  power  grid.    The  line  will  be  used  to  deliver  excess  power  from  the  dedicated  power plant  into  the  grid,  or  to  provide  a  back-­‐up  source  of  power  for  the  operations.    All  the  power  line  towers over   the   30   km   line   length   have   been   erected   and   stringing   of   the   power   line   is   80%   complete. Commissioning  of  the  power  line  is  expected  in  early  October.

Health  and  Safety    

The  main  EPCM  contractor,  DRA  Global,  continued  their  excellent  safety  record  with  a  recent  achievement of  2.4  million  lost  time  injury  free  man  hours.    Health  and  safety  continue  to  be  a  main  focus  across  all aspects  of  the  Company’s  operations.

Partial  Relocation  of  Nkran  Village  

The  partial  relocation  of  the  Nkran  village  (88  building  structures)  has  been  completed.    A  formal  handover ceremony  was  held  on  15  September  and  the  villagers  will  be  moved  into  their  new  houses  over  the  coming week.    The  new  resettlement  project  offers  a  substantial  improvement  in  quality  of  life  with  all  the  houses fitted   with   kitchen   and   bathroom   facilities,   electricity   and   potable   water.   There   is   also   street   lighting,   a water   storage   facility   and   an   integrated   waste   management   system.     A   community   centre,   school   and football  field  are  also  being  built.  All  the  relocated  properties  were  built  by  local  Ghanaians  from  the  region, adding  considerable  value  to  the  communities  impacted  by  the  mine.

Funding    

Procurement  is  now  complete  and  the  Project  continues  to  track  within  budget,  with  US$180million  spent and   a   further   US$110   million   committed.   The   Company   is   fully   funded   to   cash   flow   positive   with approximately  US$182  million  in  cash  on-­‐hand  as  at  August  31,  2015  plus  a  US$20  million  cost-­‐overrun facility  for  total  available  funding  of  approximately  US$202  million.  The  remaining  use  of  funds  is  US$162 million  which  includes  US$139  million  for  the  project,  US$18  million  for  working  capital  and  US$5  million for  corporate  costs  until  commercial  production  is  achieved,  which  is  expected  in  Q2  2016.    As  such,  the Company  continues  to  maintain  a  funding  buffer  of  US$40  million.

Enquiries:  

For  further  information  please  visit:  www.asanko.com,  email:  [email protected]  or  contact:

Alex  Buck,  Manager  –  Investor  Relations   Wayne  Drier  -­‐  Executive,  Corporate  Development Toll-­‐Free  (N.America):  1-­‐855-­‐246-­‐7341   Telephone:  +1-­‐778-­‐729-­‐0614 Telephone:  +44-­‐7932-­‐740-­‐452   Email:  [email protected] Email:  [email protected]

About  Asanko  Gold  Inc.  

Asanko’s  vision  is  to  become  a  mid-­‐tier  gold  mining  company  that  maximizes  value  for  all  its  stakeholders. The  Company’s  flagship  project  is  the  multi-­‐million  ounce  Asanko  Gold  Mine  located  in  Ghana,  West  Africa. The  mine  is  being  developed  in  phases.  Phase  1  is  fully  financed,  permitted  and  under  construction.    First gold  is  expected  in  Q1  2016,  with  steady  state  production  of  190,000  ounces  per  annum  in  Q2  2016.

Asanko  is  managed  by  highly  skilled  and  successful  technical,  operational  and  financial  professionals.  The Company   is   strongly   committed   to   the   highest   standards   for   environmental   management,   social responsibility,  and  health  and  safety  for  its  employees  and  neighbouring  communities.

Forward-­‐Looking  and  other  Cautionary  Information

This   release   includes   certain   statements   that   may   be   deemed   "forward-­‐looking   statements".   All   statements   in   this   release,  other  than  statements  of  historical  facts,  that  address  estimated  resource  quantities,  grades  and  contained   metals,  possible  future  mining,  exploration  and  development  activities,  are  forward-­‐looking  statements.  Although  the   Company  believes  the  forward-­‐looking  statements  are  based  on  reasonable  assumptions,  such  statements  should  not   be  in  any  way  construed  as  guarantees  of  future  performance  and  actual  results  or  developments  may  differ  materially   from  those  in  the  forward-­‐looking  statements.  Factors  that  could  cause  actual  results  to  differ  materially  from  those  in   forward-­‐looking   statements   include   market   prices   for   metals,   the   conclusions   of   detailed   feasibility   and   technical   analyses,  the  timely  renewal  of  key  permits,  lower  than  expected  grades  and  quantities  of  resources,  mining  rates  and   recovery  rates  and  the  lack  of  availability  of  necessary  capital,  which  may  not  be  available  to  the  Company  on  terms   acceptable  to  it  or  at  all.  The  Company  is  subject  to  the  specific  risks  inherent  in  the  mining  business  as  well  as  general   economic   and   business   conditions.   For   more   information   on   the   Company,   Investors   should   review   the   Company's   annual  Form  20-­‐F  filing  with  the  United  States  Securities  Commission  and  its  home  jurisdiction  filings  that  are  available   at  www.sedar.com.  

Neither  Toronto  Stock  Exchange  nor  the  Investment  Industry  Regulatory  Organization  of  Canada  accepts  responsibility   for  the  adequacy  or  accuracy  of  this  release.  

Cautionary  Note  to  U.S.  Investors  Regarding  Mineral  Reporting  Standards:  

Asanko  has  prepared  its  disclosure  in  accordance  with  the  requirements  of  securities  laws  in  effect  in  Canada,  which   differ  from  the  requirements  of  US  securities  laws.  Terms  relating  to  mineral  resources  in  this  press  release  are  defined   in  accordance  with  National  Instrument  43-­‐101  -­‐  Standards  of  Disclosure  for  Mineral  Projects  under  the  guidelines  set   out   in   the   Canadian   Institute   of   Mining,   Metallurgy,   and   Petroleum   Standards   on   Mineral   Resources   and   Mineral   Reserves.    The  Securities  and  Exchange  Commission  (the  “SEC”)  permits  mining  companies,  in  their  filings  with  the  SEC,   to  disclose  only  those  mineral  deposits  that  a  company  can  economically  and  legally  extract  or  produce.    Asanko  uses   certain  terms,  such  as,  “measured  mineral  resources”,  “indicated  mineral  resources”,  “inferred  mineral  resources”  and   “probable  mineral  reserves”,  that  the  SEC  does  not  recognize  (these  terms  may  be  used  in  this  press  release  and  are   included   in   the   public   filings   of   Asanko   which   have   been   filed   with   securities   commissions   or   similar   authorities   in   Canada).