Asanko Gold Confirms Robust Economics for Phase 1

Technical Reports (NI 43-101) Shareholder Meetings

Vancouver,  British  Columbia,  November  13,  2014  –  Asanko  Gold  Inc.  (“Asanko”  or  the  “Company”)  (TSX,   NYSE  MKT:  AKG)  is  pleased  to  announce  an  optimized  mine  plan  and  associated  operating  costs  for  Phase  1 of  the  Asanko  Gold  Mine  (“AGM”  or  the  “Project”)  in  Ghana,  which  confirms  the  robustness  of  the  Project’s economics.     These,   together   with   the   updated   capital   cost   estimate   and   an   updated   Mineral   Resource Estimate  (“MRE”)  released  earlier  in  the  year,  collectively  form  the  “Definitive  Project  Plan”  (“DPP”)  for Phase  1  of  the  Project.

Definitive  Project  Plan  Highlights:

  • Life  of  Mine  (“LoM”)  gold  production  of  2.33  million  ounces  over  a  12  year  life  of  mine.
  • Capital  cost  of  U$295  million,  including  all  associated  infrastructure  and  allowances  for  contingencies.
  • Lowest  quartile  All-­‐In-­‐Sustaining-­‐Costs1  of  US$781/oz;  competitive  operating  cash  costs  of  US$645/oz.
  • Project  fully  funded  with  US$130  million  undrawn  debt  facility  and  US$228  million  cash  on  hand2.
  • First  gold  targeted  during  Q1  2016  and  steady-­‐state  production  in  Q2  2016.
  • Robust  project  economics  with  strong  cash  flow  generation  even  in  a  weak  gold  price  environment:
Gold PriceNPV (5%) US$ (millions)After Tax IRR (%)2017 After-­‐Tax FCF (US$ millions)
Spot -­‐ US$1,150/oz25320103
Study Basis -­‐ US$1,300/oz41226120
Upside Case -­‐ US$1,500/oz62435143

*Real  ungeared  post  tax  project  NPV  &  IRR  over  Life  of  Mine

As  a  result  of  the  positive  economic  outcomes  of  the  DPP,  a  portion  of  the  Company’s  Mineral  Resources for  Phase  1  have  been  upgraded  to  Mineral  Reserves  as  follows:

ClassificationTonnage (Mt)Grade (g/t)Ounces (millions)
Proven15.62.271.12
Probable21.12.071.39
Total Proven & Probable36.72.152.51

Commenting  on  the  DPP,  Asanko’s  President  &  CEO  Peter  Breese  said:  “The  Definitive  Project  Plan  confirms   the  attractive  project  economics  and  highly  competitive  AISC  costs  of  Phase  1  of  the  Asanko  Gold  Mine,   which  we  identified  when  we  acquired  the  Project  earlier  this  year  from  PMI  Gold.  With  significant  cash  flow   generation,   even   at   current   spot   gold   prices,   this   Project   forms   the   cornerstone   of   our   strategy   to   be   a   growth   oriented,   low-­‐cost   producer.   Construction,   which   started   in   August   2014,   is   on   schedule   and   on   budget  and  we  are  anticipating  first  gold  to  be  poured  in  Q1  2016.      

“The   final   step   in   showcasing   the   value   of   our   flagship   Asanko   Gold   Mine   will   be   the  completion   of   the   Phase  2  study  in  Q1  2015.    Phase  2  will  result  in  the  development  of  the  large-­‐scale  Esaase  deposit,  located   30  km  to  the  north  of  the  plant  site.    The  study  is  expected  to  substantially  improve  the  economics  that  were   detailed  in  a  stand-­‐alone  Pre-­‐Feasibility  Study  for  Esaase  in  May  2013  by  capturing  operating  and  capital   synergies  based  on  expanding  and  sharing  the  Phase  1  processing  facilities.”  

The   DPP   will   be   published   as   a   NI   43-­‐101   compliant   Technical   Report   and   will   be   filed   on   SEDAR   at www.sedar.com  on  or  before  December  19,  2014.  This  will  replace  the  2012  Definitive  Feasibility  Study completed  by  PMI  Gold.

PHASE  1  DEFINITIVE  PROJECT  PLAN  –  EXECUTIVE  SUMMARY  

Introduction  

The  Asanko  Gold  Mine  (“AGM”  or  the  “Project”)  is  located  in  Ghana,  West  Africa  (Figure  1).  It  is  wholly-­‐ owned  by  Asanko  Gold,  with  a  10%  free  carried  interest  held  by  the  Government  of  Ghana  which  becomes effective   when   production   commences.     Ghana   is   Africa’s   second   largest   gold   producer   and   has   been producing  gold  on  a  large  scale  for  many  years.  Ghana  has  many  internationally  recognised  gold  mining companies  operating  in  the  country  including  AngloGold  Ashanti,  Newmont  and  Goldfields.

Figure  1.  Project  Location  

The  AGM  consists  of  six  known  open  pit  deposits  over  a  30km  trend  and  is  being  developed  in  two  phases. Phase  1  will  mine  the  Nkran  pit,  which  accounts  for  85%  of  the  Phase  1  ore  reserves,  and  four  satellite deposits,  Abore,  Asuadai,  Dynamite  Hill  and  Adubiaso.

Phase  1  is  fully  permitted  and  funded,  with  US$130  million  of  undrawn  debt  facilities  (refer  news  release dated  July  14,  2014)  and  US$228  million  cash  on  hand.    Construction  commenced  in  Q3  2014  and  first  gold is  targeting  for  Q1  2016,  with  steady-­‐state  production  in  Q2  2016.

The  Company  engaged  DRA  Mineral  Projects  (“DRA”)  to  manage  the  DPP  for  Phase  1  of  the  Asanko  Gold Mine  based  on  the  September  2014  Mineral  Resource  Estimate  (“MRE”),  prepared  for  Asanko  by  Charles Muller,  CJM  Consulting.

Mineral  Resource  Estimation  –  Phase  1  

In  September  2014  Asanko  completed  a  comprehensive  review  of  the  original  May  2012  Mineral  Resource Estimate  (“MRE”)  for  the  four  deposits  which  comprise  Phase  1  -­‐  Nkran,  Adubiaso,  Abore  and  Asuadai  -­‐  that were   acquired   from   PMI   Gold   Corporation   ("PMI   Gold")   in   February   2014.   The   original   MRE   was   not deemed  to  be  a  suitable  input  for  the  detailed  mine  planning  required  to  commence  the  mining  operations of  Phase  1.  In  addition,  the  Company  announced  a  maiden  resource  for  the  recently  discovered  Dynamite Hill,  following  completion  of  a  drilling  programme  earlier  in  the  year.

The  results  of  the  new  MRE  for  Phase  1,  shown  in  the  table  below,  are  not  materially  different  to  the  2012 MRE  and  therefore  confirm  the  validity  of  the  previous  estimate.  Importantly,  however,  the  new  MRE  more precisely  represents  grade  distribution  and  continuity  within  the  deposits,  and,  as  a  result,  the  model  now supports  the  ability  to  plan  the  mine  with  the  selectivity  required  to  manage  grade  control  and  volumes.

The  total  Measured  and  Indicated  Mineral  Resources  increased  by  about  0.43  million  ounces  of  gold  and the  Inferred  Mineral  Resources  have  decreased  by  about  0.41  million  ounces  of  gold  compared  to  the  May 2012  MRE.

Table  1:  2014  Updated  Mineral  Resource  Estimate  for  Phase  1  only    

DepositMeasured Tonnes Grade Ounces (millions) (g/t) (millions)Indicated Tonnes Grade Ounces (millions) (g/t) (millions)Total (M&I)Inferred Tonnes Grade Ounces (millions) (g/t) (millions)
TonnesGradeOunces
(millions)(g/t)(millions)
Nkran13.242.551.0925.802.231.8539.042.342.947.062.340.53
Abore1.611.700.093.371.630.184.981.650.276.591.650.35
Adubiaso0.732.600.061.402.040.092.132.230.150.202.270.02
Dynamite Hill0.000.000.001.841.860.111.841.860.110.521.510.03
Asuadai0.000.000.001.641.340.071.641.340.071.251.610.06
Total15.582.471.2434.052.102.3049.632.223.5415.621.960.99

Notes:   Cut-­‐off  grade  of  0.8  grams  per  tonne  of  gold.    Due  to  rounding  differences,  some  totals  may  not  add  exactly   Combined  resource  statements  for  Phase  1  and  Phase  2  are  on  page  11  of  this  release.  

Mineral  Reserve  Statement  –  Phase  1

The   DPP   reports   a   Mineral   Reserve   for   Phase   1   based   on   the   associated   MRE   and   a   gold   price   of US$1,300/oz.    Specifically,  DRA  derived  optimized  pit  shells  for  Phase  1  based  on  the  material  reported  as Measured   and   Indicated   Mineral   Resources.     The   operating   costs   assumed   for   the   optimization   were supplied  by  an  in-­‐country  contractor,  reviewed  and  agreed  by  DRA.    Metallurgical  recoveries  have  been provided  by  DRA  based  on  analysis  of  previous  test  work,  operational  results  and  more  recent  test  work. Five  separately  designed  pits  were  developed  from  the  optimized  pit  shells;  Nkran,  Adubiaso,  Dynamite  Hill, Abore  and  Asuadai.

Table  2:  2014  Updated  Mineral  Reserve  Statement  for  Phase  1  only  

DepositClassificationTonnage (Mt)Grade (g/t)Ounces (millions)
NkranProven13.52.321.00
Probable17.72.121.20
AdubiasoProven0.92.230.06
Probable0.91.900.05
AboreProven1.21.690.06
Probable0.91.870.05
AsuadaiProven0.00.000.00
Probable0.51.260.02
Dynamite HillProven0.00.000.00
Probable1.11.880.07
DepositClassificationTonnage (Mt)Grade (g/t)Ounces (millions)
TotalProven15.62.271.12
Probable21.12.071.39

Notes:   Cut-­‐off  grade  of  0.8  grams  per  tonne  of  gold.    Due  to  rounding  differences,  some  totals  may  not  add  exactly   The  grades  and  tonnes  reported  have  been  modified  by  mining  recovery  and  dilution  based  on  ore  body   geometry  and  mining  methodology.  Globally  this  generates  a  mining  dilution  5%  and  ore  loss  of   approximately  5%.  Combined  reserve  statements  for  Phase  1  and  Phase  2  on  page  12  of  this  release.  

A   'Mineral   Reserve'   is   the   economically   mineable   part   of   a   Measured   or   Indicated   Mineral   Resource, demonstrated  by  at  least  a  Preliminary  Feasibility  Study.  It  includes  diluting  materials  and  allowances  for losses  that  may  occur  when  the  material  is  mined.  DRA  is  of  the  opinion  that  the  classification  of  Mineral Reserves  as  reported  herein  meets  the  definitions  of  Proven  and  Probable  Mineral  Reserves  as  stated  by the   CIM   Definition   Standards   (2005).   Measured   and   Indicated   Mineral   Resources   that   are   not   Mineral Reserves  have  not  demonstrated  economic  viability.    Inferred  Mineral  Resources  are  excluded  from  the Mineral   Reserve   Estimate.   All   figures   are   rounded   to   reflect   appropriate   levels   of   confidence.   Apparent differences  may  occur  due  to  rounding.

Mining  Operations  

A  Life  of  Mine  (“LoM”)  schedule  has  been  developed  to  supply  a  three  million  tonnes  per  annum  (“Mtpa”) mill  feed  rate  from  the  Nkran  pit  and  the  four  satellite  deposits.    A  mining  contractor  will  be  used  for  all  ore and  waste  mining  activities.

The  five  deposits  will  all  be  mined  utilizing  a  conventional  truck  and  shovel  method.  Grade  control  drilling together  with  onsite  laboratory  facilities  will  be  used  to  delineate  the  ore  from  the  waste.    Ore  and  waste will   be   drilled   and   blasted,   then   loaded   and   hauled   to   either   the   ROM   pad,   direct   tip   into   the   crushing facility,  placed  on  pit  rim  stockpiles  (for  the  remote  deposits)  or  placed  on  waste  rock  storage  facility  with haul  trucks.    A  single  fleet  of  mining  equipment  will  be  shared  between  all  the  deposits.    For  the  satellite deposits  -­‐  Adubiaso,  Dynamite  Hill,  Abore  and  Asuadai  -­‐  a  fleet  of  contracted  road  trucks  will  be  utilized  to haul   ore   from   the   respective   pit   rim   stockpiles   to   the   ROM   stockpile   situated   at   the   central   processing facility,  which  is  located  close  to  the  Nkran  pit.

Production  will  commence  at  the  Nkran  pit  as  it  comprises  85%  of  the  ore  reserves  for  Phase  1.    This  will assist   in   keeping   the   pre-­‐stripping   volumes   low   and   delivering   higher   mill   feed   grades   early   in   Phase   1. Approximately  one  year  of  waste  stripping  will  be  required  to  expose  sufficient  ore  to  maintain  a  constant ore  feed  rate  of  3Mtpa  once  the  mill  has  been  commissioned.    During  Year  1,  ore  that  is  mined  will  be stockpiled   and   will   form   the   basis   of   the   initial   plant   feed   for   commissioning   and   early   production.   The mining  of  all  five  deposits  runs  for  a  period  of  approximately  12.4  years  based  on  the  current  production schedule.

The  production  schedule  has  been  designed  to  maintain  a  consistent  stripping  ratio  through  the  life  of  the operation.  The  LoM  average  operating  strip  ratio  is  4.7:13  .  The  peak  production  requirements  are  26Mtpa of  total  material  movement.

The  average  mining  cost  over  the  life  of  Phase  1  is  estimated  at  US$3.88  per  tonne  mined  (ore  and  waste), which  equates  to  a  total  mining  cost  of  US$348  per  ounce  of  gold  produced.  Waste  mining  and  haulage costs   are   US$3.28   per   tonne   whilst   ore   mining   and   haulage   costs   are   US$6.70   per   tonne.   The   main differences  between  the  two  mining  cost  rates  is  the  additional  costs  of  grade  control  and  longer  hauls  to the  run-­‐of-­‐mine  crusher  on  ore  tonnes.

Mining  capital  requirements   include  initial  contractor  mobilization,  establishment  of  the  contractor,  site clearing,  pit  de-­‐watering  and  pre-­‐stripping  of  the  Nkran  pit.  This  is  estimated  to  be  US$70.6million.

Table  3:  DPP  Mine  Plan Years  2015  –  2021  

2015201620172018201920202021
Ore mined (‘000t)2303,7043,1233,3193,0002,9512,850
Grade mined (g/t)2.442.152.222.152.302.282.23
Waste (‘000t)19,76121,25421,92821,15220,99323,17922,754
Strip ratio (w:o)86.055.747.026.377.007.867.98
Plant feed (‘000t)-­‐2,5383,0003,0003,0003,0003,000
Feed grade (g/t)-­‐2.582.272.152.302.272.20
Recovery (%)-­‐88.8992.6692.3492.6392.6292.60
Gold produced (oz)-­‐187,429202,624191,131205,500202,711196,273

Years  2022  -­‐  2028  

2022202320242025202620272028
Ore mined (‘000t)3,0013,0013,0013,0003,0012,325-­‐
Grade mined (g/t)2.202.151.931.942.082.12-­‐
Waste (‘000t)18,1478,4849,7614,6191,863889-­‐
Strip ratio (w:o)6.052.833.251.540.620.38-­‐
Plant feed (‘000t)3,0003,0003,0003,0003,0003,000968
Feed grade (g/t)2.202.151.931.942.081.991.53
Recovery (%)92.6092.2792.3692.4592.5692.50112.13
Gold produced (oz)196,226191,712172,160173,326185,728177,60753,462

Note:  Recovery  in  first  and  last  year  adjusted  for  inventory  lockup  of  approx.  7,300  ounces  

Processing  

The  plant  design  is  based  on  a  typical  single  stage  crushing,  SAG,  ball  milling  circuit  (SABC)  and  carbon  in leach  (“CIL”)  flow  sheet.    It  includes  single  stage  jaw  crushing  with  reclaim  from  a  live  stockpile  and  open circuit  SAG  mill,  feeding  cyclones  that  in  turn  operate  in  a  closed  circuit  with  a  ball  mill.    A  pebble  crusher will   receive   scats   from   the   SAG   mill,   crush   them   and   return   them   to   the   SAG   for   further   grinding.     The hydrocyclones  will  achieve  the  final  product  size  of  P80  106  μm.    A  gravity  circuit  will  be  utilised  to  treat  a portion  of  the  cyclone  underflow  stream  to  recover  coarse  free  gold,  around  40%,  from  the  recirculating load.    The  milled  product  will  gravitate  to  a  trash  screen  before  entering  a  pre-­‐leach  thickener  followed  by  a conditioning  tank.

A   seven   stage   CIL   circuit   will   be   used   to   leach   and   adsorb   gold   from   the   milled   ore   onto   activated carbon.    An  AARL  elution  circuit  will  be  used  to  recover  gold  from  loaded  carbon.    Cyanide  in  the  CIL  tailings will   be   detoxified   using   the   SO2   /   Air.     The   detoxified   tailings   are   then   pumped   to   the   Tailings   Storage Facility  (“TSF”).

This  process  flow  sheet  is  well  known  in  industry,  and  is  relatively  low  risk  as  it  has  historically  been  proven a  successful  processing  route  for  the  Nkran  ores  during  Resolute  Mining  Ltd  operations,  1998  to  2002.

Figure  2:  Process  Flow  Sheet  

Table  4:  LoM  Process  Plant  Recoveries  

CompositeGravity – CIL (P80 = 106μm ) _
Oxide90.0%
Transitional91.7%
Fresh92.7%
LOM Recovery92.5%

Table  5:  LoM  Process  Plant  Operating  Costs    

LoM US$/t
Crusher Liners0.26
Mill Liners0.36
Grinding Media0.76
Reagents (CIL)1.90
Reagents (Detox)0.70
Reagents (Other)0.57
Tailings0.40
Power6.16
Labour0.72
Maintenance0.78
Laboratory0.24
Other0.55
Total13.40

Capital  Costs    

The  initial  capital  cost  of  the  mine,  process  plant  and  associated  infrastructure  for  Phase  1  is  estimated  at US$295  million.  The  cost  is  inclusive  of  all  infrastructure  and  indirect  costs  required  for  the  Project  including allowances   for   contingencies   and   estimating   inaccuracies   of   8.3%   in   aggregate   (amounting   to   US$22.75 million).  The  engineering  has  been  developed  to  support  a  capital  and  operating  cost  estimate  to  a  nominal accuracy  of  -­‐/+5%  (Table  6).

Table  6:  Capital  Costs  

Asanko Gold Mine – Phase 1Capital Estimate
(US$ million)
Process plant85.48
Mining (pre-­‐production costs)70.59
Power infrastructure18.18
Buildings, offices and accommodation12.31
TSF, WRD, ROM, water supply, civil works23.08
CSR, owners team, G&A47.37
EPCM15.51
Sub total272.52
Contingency & estimating inaccuracies22.75
Total295.27

A  summary  of  the  process  plant  capital  costs  are  shown  in  the  Table  7  below  (-­‐5%  to  +5%  nominal accuracy).

Table  7:  Plant  Capital  Costs  

DescriptionCost (US$ million)
Civils8.32
Structural steel and platework17.45
Mechanicals25.88
Piping and valves9.95
Electrical and instrumentation15.42
Transportation4.27
Total *81.28
  • Excluding  contingency  and  attributable  EPCM  

Operating  costs  

The   average   cash   operating   cost   for   Phase   1   is   estimated   at   US$645   per   ounce   (Table   8),   which   is competitive  on  a  global  comparison.  All-­‐In-­‐Sustaining  Costs  (“ASIC”)  are  US$781  per  ounce,  which  places Phase  1  in  the  lowest  quartile  of  industry  costs.  These  costs  are  based  on  the  treatment  of  3Mtpa  of  ore producing  an  average  190,000  ounces  of  gold  per  annum.

Operating  costs  were  developed  in  conjunction  with  the  project  design  criteria,  process  flow  sheet,  mass and  water  balance,  mechanical  and  electrical  equipment  lists,  and  in-­‐country  labour  cost  data.  The  cash operating   costs   are   defined   as   the   direct   operating   costs   including   contract   mining,   processing,   tailings storage,  water  treatment,  general  and  administrative  and  refining  costs

Table  8:  Cash  Operating  Costs

DescriptionUS$/oz
Waste mining243
Ore mining105
Processing210
General and administrative83
Refining4
Cash Costs645
Royalties65
Sustaining and deferred capex19
Corporate Overhead35
Interest on Project Debt17
All-­‐in sustaining cash costs781

Note:  The  costs  detailed  above  are  calculated  for  the  purpose  of  this  report  in  real  terms  with  no  material  change  in   the  key  profitability  projected  for  the  LoM  period.  

Key  Sensitivities  

A   range   of   Project   sensitivities   have   been   evaluated   to   assess   their   impact   on   the   base   case   numbers included  in  the  financial  model.  The  significant  financial  sensitivities  identified  were  discount  rate  and  gold price  (Table  9).

Table  9:  Key  Sensitivities  

Discount Rate
Price US$ Gold/oz3%5%6%7%8%IRR
1,100 1,200 1,300 1,400 1,500 1,600261,394200,576173,980149,587127,17716.0%
380,964306,894274,467244,704217,34121.1%
500,079412,695374,410339,250306,91025.9%
619,172518,476474,332433,777396,45930.4%
738,254624,246574,243528,292485,99834.7%
857,327730,008674,146622,801575,53038.9%

Numbers  quoted  as  net  present  value  (“NPV”)  discounted  at  various  discount  rates  and  expressed  in  thousands  of  US   dollars  

Other  significant  sensitivities,  identified  as  installation  capital,  operating  costs,  feed  grade,  taxation  and process  recovery  were  evaluated  and  presented  as  a  tornado  plot  (Table  10).

Table  10:  Tornado  Plot  of  Various  Parameters  

FlexPositive CaseNegative Case
Process recovery1%13,718(13,717)
Taxation2.5%16,316(16,316)
Discount1%41,759(38,286)
Feed grade1%13,717(13,718)
Selling priceUS$100105,781(105,801)
Operating cost3%21,915(21,917)
Installation capex10%16,412(16,415)

NPV  Tornado  Sensitivity  Plot

Instal capex Opexex
pex
Selling price
Disco ProcGrade (feed) unt (approx.) Taxation ess recoveryd)
(approx.)
on
ry

NPV  Impact  $'m

(150)  (100)  (50)  -­‐  50  100  150 Negative Positive

Civil  and  Infrastructure    

US$23  million  has  been  provided  for  the  TSF,  waste  rock  dumps,  run  of  mine,  water  supply  and  related  civil works  as  part  of  the  infrastructure  capital  costs.    In  addition,  a  further  US$35.6  million  has  been  included  in deferred  capital  for  the  TSF  expansion,  buffer  dams  and  dewatering  dams.  The  operating  costs  for  tailings management  through  the  current  life  of  mine  have  been  included  in  the  plant  operating  costs.

The  layout  of  the  process  plant  and  mine  facilities  have  been  designed  to  be  close  to  the  main  resource,  the Nkran  pit  and  to  be  compact  in  order  to  minimise  impact  on  the  environment.  The  new  plant  layout  has also  made  allowance  to  accommodate  the  footprint  for  the  inclusion  of  the  future  Phase  2  project.

The  total  power  requirements  for  the  Project  are  estimated  at  18  MW  of  consumed  power.  Power  will  be sourced  from  the  Ghanaian  grid.    Power  quality  meters  installed  in  April  2014  have  been  monitoring  the grid  over  the  past  seven  months  and  confirmed  a  high  reliability  and  availability  of  over  99%.

The  TSF  will  consist  of  a  multi-­‐zoned  downstream  perimeter  embankment,  comprising  a  total  footprint  area (including  the  basin  area)  of  approximately  67  ha  for  the  Phase  1  TSF,  increasing  to  209  ha  for  the  total Project  TSF.  The  TSF  is  designed  to  store  a  total  of  33Mt  of  waste.  The  TSF  will  be  lined  with  a  1.5mm  HDPE geomembrane   with   an   additional   underdrainage   system   discharging   to   collection   sumps   located   at   the lowest  point  in  the  TSF.

Tailings  will  be  pumped  from  the  process  plant  to  the  TSF  via  a  HDPE  pipe  contained  within  a  HDPE  lined trench  and  discharged  into  the  TSF  by  sub-­‐aerial  deposition  methods,  using  a  combination  of  spigots  at regularly  spaced  intervals  from  the  embankment.    Supernatant  water  will  be  removed  from  the  TSF  via submersible  pumps  located  on  a  floating  barge  located  within  the  supernatant  pond  throughout  operation.

The  decant  barge  will  be  tethered  to  the  TSF  perimeter  so  as  not  to  cause  damage  to  the  TSF  basin  HDPE geomembrane  liner.

Employment  

Phase  1  of  the  Project  will  employ  approximately  660  people,  including  contractors,  to  operate  the  mine. Permanent  employees  will  be  predominantly  sourced  from  the  local  communities  and  elsewhere  within Ghana,  which  has  a  highly  trained  mining  workforce  due  to  a  mature  gold  mining  industry.

The  Company  is  closely  engaged  with  all  local  stakeholders  and  has  implemented  a  number  of  vocational training   schemes   in   the   local   communities   aimed   at   developing   the   capabilities   of   the   local   youth   in employable  skills  to  support  the  construction  and  operation  stages  of  Phase  1.  To  date  56  students  have graduated   and   joined   the   local   employment   pool.   95   local   community   members   have   already   been employed  by  contractors  during  the  early  works  phase.

Partial  Resettlement  of  Manso-­‐Nkran  Village  

The  legal  and  institutional  context  of  resettlement  in  Ghana  is  completed  under  the  Ghana  Minerals  and Mining  Act,  2006  (Act  703)  and  its  associated  Legislative  Instrument  (LI),   the  Mining  and  Environmental Guidelines  of  1994  and  the  Environmental  Protection  Agency  (EPA)  regulations  among  others.

Phase  1  will  mainly  source  ore  from  the  Nkran  pit.    There  are  approximately  88  dwellings  in  the  Manso-­‐ Nkran   community   that   lie   within   500   meters   of   the   final   pit   design.     Under   the   above   mentioned regulations,   these   dwellings   must   be   relocated   prior   to   mining   activity.     To   achieve   a   successful   partial resettlement,  and  in  accordance  with  Section  7  of  the  LI  2175,  Asanko  Gold  has:

(a) Engaged  in  prior  consultations  with  the  District  Assembly,  Chiefs  and  the  inhabitants  to  be  resettled  on the  impending  resettlement  activities;

(b) Collected,  analysed  and  documented  information  on  the  socio-­‐economic  and  environmental  conditions of  the  inhabitants  to  be  settled;

(c) Prepared   a   plan   for   the   overall   development   of   the   resettlement   area   which   include   the   measures, policies  and  strategies  to  guide  the  future  development  of  the  area;

(d) Prepared   a   strategic   action   plan   (Resettlement   Action   Plan)   which   outlines   specific   projects   and programmes  with  action  plans,  guidelines  and  institutional  arrangements  for  execution;  and  has

(e)  Established   a   Resettlement   Negotiations   Committee   (RNC)   with   affected   households.     The   RNC   is working  assiduously  with  relevant  government  agencies  and  the  management  of  Asanko  to  ensure  a successful  implementation  process.

In  resettling  a  portion  of  Manso-­‐Nkran  community  that  will  be  affected  by  mining  activity  during  Phase  1, Asanko  has  committed  to  adhering  to  the  provisions  in  the  Ghana  Minerals  and  Mining  Act,  2006  (Act  703) and   other   regulations,   as   well   as   following   international   best   practise   regarding   compensation   and resettlement  of  a  community.

Project  Schedule  

The  Company’s  key  Project  timelines  are:

Key MilestonesDateStatus
Commence Bulk EarthworksQ3 2014Completed
Optimized Mine Plan for Phase 1 (Definitive Project Plan)Q4 2014Completed
Mining Pre-­‐Strip Begins at NkranQ1 2015Contractor Selected
All Earthworks CompleteQ1 2015
Concrete CivilsQ1 2015
Mills Arrive on SiteQ2 2015
SAG and Ball Mill Civils CompleteQ3 2015
Piping, Electrical and InstrumentationQ4 2015
CommissioningQ1 2016
First Gold PourQ1 2016
Phase 1 Steady State Production of 190,000oz/paQ2 2016

Table  11:  Asanko  Gold  Mine  Global  Resource  Estimate  

DepositMeasured Tonnes Grade Oz (millions) (g/t) (millions)Indicated Tonnes Grade Oz (millions) (g/t) (millions)Total (M&I)Inferred Tonnes Grade Oz (millions) (g/t) (millions)
TonnesGradeOz
(millions)(g/t)(millions)
Nkran13.242.551.0925.802.231.8539.042.342.947.062.340.53
Abore1.611.700.093.371.630.184.981.650.276.591.650.35
Adubiaso0.732.600.061.402.040.092.132.230.150.202.270.02
Dynamite Hill0.000.000.001.841.860.111.841.860.110.521.510.03
Asuadai0.000.000.001.641.340.071.641.340.071.251.610.06
Phase 1 Total15.582.471.2434.052.102.3049.632.223.5415.621.960.99
Esaase23.381.491.1271.251.443.2894.631.454.4033.591.401.51
Total38.961.882.36105.301.655.58144.261.717.9449.211.582.50

Notes:   The  cut-­‐off  grade  used  for  Phase  1  resources  (Nkran,  Adubiaso,  Abore,  Dynamite  Hill  &  Asuadai)  was  0.8  g/t   and  the  cut-­‐off  grade  used  for  Phase  2  (Esaase)  resource  was  0.6  g/t.    

Due  to  rounding  differences  some  M&I  totals  may  not  add  exactly  with  the  Measured  and  Indicated  figures.    

Table  12:  Asanko  Gold  Mine  Global  Reserve  Estimate  

DepositClassificationTonnage (Mt)Grade (g/t)Ounces (millions)
NkranProven13.52.321.00
Probable17.72.121.20
AdubiasoProven0.92.230.06
Probable0.91.900.05
AboreProven1.21.690.06
Probable0.91.870.05
AsuadaiProven0.00.000.00
Probable0.51.260.02
Dynamite HillProven0.00.000.00
Probable1.11.880.07
Phase 1 TotalProven15.62.271.12
Probable21.12.071.39
EsaaseProven22.851.431.05
Probable29.491.401.32
TotalProven38.451.7692.17
Probable50.591.6782.71

   Notes:   Cut-­‐off  grade  of  0.8  grams  per  tonne  of  gold.    Due  to  rounding  differences,  some  totals  may  not  add  exactly.   The  grades  and  tonnes  reported  have  been  modified  by  mining  recovery  and  dilution  based  on  ore  body   geometry  and  mining  methodology.  Globally  this  generates  a  mining  dilution  5%  and  ore  loss  of   approximately  5%.  

Notes:  

1. Cash  costs  are  mining,  processing,  site  G&A  and  bullion  refining.  AISC  are  as  per  the  World  Gold  Council definition  including  cash  costs  plus  royalties,  sustaining  capital,  corporate  overhead  and  interest  on  debt financing  used  to  build  the  Project.

2. Cash  balance  of  US$228  million  as  at  September  30,  2014

3. Life  of  Mine  strip  ratio  for  Phase  1  including  pre-­‐stripping  21.7Mt  of  waste  at  the  Nkran  pit  is  5.34:1

Management  Conference  Call  and  Webcast  

Asanko  management  will  host  a  webcast  and  conference  call  today  at  9:00am  Eastern  Standard  Time.    An accompanying  presentation  will  be  available  on  the  Company’s  website:  www.asanko.com

To  access  the  conference  call,  please  dial-­‐in  10  minutes  beforehand  and  quote  “Asanko  Gold”:

US  &  Canada  Toll  Free:  800  771  6916 UK  Toll  Free: 0800  528  0641 International:  +1  415  226  5356

A  replay  facility  will  be  available  two  hours  after  the  call  until  December  12,  2014,  please  dial  using  the access  code:  #21741159 US  &  Canada  Toll  Free:  800  558  5253 International:  +1  416  626  4100

Webcast  Details

To  access  the  webcast,  please  click  the  link:  https://cc.callinfo.com/r/1ou0qi8zv6yj7&eom