Vancouver, September 6, 2018 -- Fortuna Silver Mines Inc. (NYSE: FSM) (TSX: FVI) is pleased to provide
results for its infill drilling program at the Lindero Project in Argentina. The Lindero P roject is under
construction, and commercial operations are planned to start late in the third quarter of 2019, with an
estimated gold production of 1 37,000 ounces of gold in the first full year of operatio n (Please refer to
the Lindero Project Technical report dated October 31, 2017).
Eric Chapman, Vice President of Technical Services, commented: "Infill drilling has been carried out with
the express intention of improving the confidence in the estimated tonnes and grade of material
planned for mining in year one at Lindero . The mineralized intercepts encountered have met or
exceeded our expectations in 44 of the 61 holes drilled when compared to estimated block model gold
grades as of September 9, 2017." Mr. Chapman continued, "Of particular interest are the results for drill
holes LDH-138, LDH-139, and LDH-164 associated with the mingled diorite porphyry unit in the center of
the deposit, in an area which was previously thought to be non -mineralized. The new drilling results are
presently being incorporated into an updated internal estimate of Mineral Resources and Re serves with
the intention of optimizing the mine plan to capture the benefits of these new results. Such updated
technical information will not materially change the existing Mineral Resources estimates."
The infill d rilling program, consisting of 61 diamond drill holes totaling 1,952 meters, focused on the
areas planned for mining at Lindero in year one with holes ranging from 12 m eters to 68 m eters in
length. The program was designed with three objectives: to improve the estimation of grades in
mineralized areas with lower density of drilling ; to better define the contact between mineralized and
non-mineralized material at the periphery of the deposit and at the boundaries between lithologic units;
and to source fresh samples for complementary metallurgical column tests on Mineral R eserves
scheduled for year one. A map showing 2018 infill d rilling collar location and a longitudinal section
showing updated drilling and 2017 block model can be found at the fol lowing links, respectively:
https://fortunasilver.com/site/assets/files/4406/lindero-infill-drilling-2018-collar-location-
map_5sept18.pdf and https://fortunasilver.com/site/assets/files/4407/lindero-section-a-a-25m-width-
updated-drilling-and_2.pdf.
-2-
Infill drill program highlights include:
LDH-138
• 1.84 g/t Au over 42 meters from surface
LDH-146
• 2.15 g/t Au over 20 meters from surface
LDH-164
• 1.20 g/t Au over 66 meters from surface
LDH-186
• 2.24 g/t Au over 28 meters from surface
LDH-187
• 2.33 g/t Au over 24 meters from surface
The following table sets out the assay results for the infill drill program:
Drill hole Easting Northing Elevation From
(m)
To
(m)
Interval²
(m)
Au
(g/t)
Cu
(%) Lithology Codes
Holes to investigate grade continuity in mineralized areas
LDH-131 7226099.99 2623223.46 3922.92 0.8 53 52.2 0.46 0.11 PBFD/CPD1
LDH-132 7226051.85 2623225.41 3914.05 1 40 39 0.87 0.09 CPD1
LDH-136 7226206.97 2622983.99 3940.49 24 52 28 0.29 0.13 DDP
LDH-138 7226165.65 2622984.51 3931.91 2 44 42 1.84 0.25 DDP
LDH-139 7226124.55 2623023.58 3938.25 0.3 52 51.7 0.84 0.17 DDP
LDH-141 7226047.11 2622985.12 3908.88 0.4 28 27.6 0.82 0.14 FPD
LDH-142 7226165.33 2622866.27 3900.94 0 24 24 0.48 0.14 CPD1
LDH-143 7226082.61 2622908.28 3899.15 0 16 16 0.65 0.15 CPD1
LDH-146 7225965.14 2623224.75 3884.60 0 20 20 2.15 0.19 S1/FPD
LDH-147 7226004.47 2623301.49 3879.90 0 20 20 0.46 0.11 S1
LDH-148 7226123.29 2623333.85 3886.19 0 24 24 0.90 0.09 CPD1
LDH-149 7226205.15 2623345.56 3887.53 0 24 24 1.62 0.12 FPD/CPD1
LDH-150 7226326.21 2623338.44 3914.58 0 32 32 0.45 0.10 CPD1
LDH-151 7226402.07 2623265.21 3910.70 0 20 20 0.36 0.15 CPD1
LDH-163 7226275.73 2623372.92 3898.69 1 24 23 1.01 0.14 PBFD
LDH-164 7226163.52 2623061.14 3953.17 0 66 66 1.20 0.19 DDP
LDH-170 7226326.20 2623297.81 3927.06 0.7 32 31.3 0.35 0.08 CPD1
LDH-171 7226207.03 2623019.15 3953.44 28 64 64 0.88 0.21 DDP/CPD2
LDH-173 7226164.59 2622907.84 3916.12 11.2 24 12.8 1.36 0.26 DDP
LDH-174 7226204.85 2622864.55 3902.69 4 12 8 0.18 0.07 FPD
LDH-175 7226086.05 2622944.01 3908.68 0 24 24 0.21 0.04 FPD
LDH-176 7226006.21 2622991.53 3901.43 0.5 16 15.5 0.41 0.10 FPD
LDH-177 7225966.95 2623068.30 3892.02 0 24 24 0.42 0.14 FPD
LDH-180 7226005.98 2623226.39 3900.41 0 32 32 1.20 0.08 FPD
LDH-181 7225977.42 2623183.11 3900.19 0 20 20 1.72 0.18 FPD/S1
LDH-182 7225969.81 2623137.46 3899.92 0 24 24 1.39 0.28 FPD
LDH-183 7226009.20 2623185.12 3911.37 0 40 40 1.14 0.16 FPD
LDH-184 7226164.99 2623280.62 3911.07 0 38 38 0.33 0.04 FPD
LDH-185 7226205.91 2623387.06 3879.19 0 12 12 1.76 0.11 CPD1
LDH-186 7226169.57 2623336.10 3888.51 0 28 28 2.24 0.13 CPD1
LDH-187 7225968.08 2623266.00 3876.14 0 24 24 2.33 0.20 FPD/S1
including 6 18 12 3.65 0.27 FPD
LDH-188 7226058.84 2623325.32 3882.33 0 20 20 1.64 0.20 FPD
-3-
Drill hole Easting Northing Elevation From
(m)
To
(m)
Interval²
(m)
Au
(g/t)
Cu
(%) Lithology Codes
Holes to investigate mineralized contacts
LDH-129 7226084.78 2623142.84 3932.60 0 56 56 0.61 0.08 PBFD
LDH-130 7226125.40 2623185.44 3926.50 No intervals of significance PMI
LDH-133 7226162.53 2623102.03 3934.68 1.1 52 50.9 0.17 0.06 CPD2/DDP
LDH-134 7226204.08 2623104.63 3934.82 No intervals of significance CPD2
LDH-135 7226203.64 2623182.71 3919.25 No intervals of significance CPD2
LDH-137 7226206.02 2622947.00 3935.77 No intervals of significance DDP
LDH-140 7226085.50 2623025.55 3924.89 No intervals of significance CPD2
LDH-144 7226007.07 2622943.37 3891.29 0 16 16 0.22 0.08 S1
including 6 12 6 0.38 0.09 S1
LDH-145 7225967.00 2623104.67 3895.54 8 20 12 0.42 0.09 CPD2/FPD
LDH-152 7226404.54 2623145.93 3903.55 0 12 12 0.28 0.07 CPD1
LDH-153 7226403.40 2623183.62 3906.08 No intervals of significance CPD1
LDH-154 7226403.29 2623224.50 3909.31 No intervals of significance CPD1
LDH-155 7226444.71 2623263.79 3898.17 No intervals of significance FPD
LDH-156 7226445.12 2623222.02 3900.21 0 32 32 0.25 0.13 CPD1/FPD
including 27 32 5 0.61 0.26 FPD
LDH-157 7226445.29 2623182.85 3902.52 No intervals of significance CPD1
LDH-158 7226445.66 2623144.89 3899.28 26 38 12 0.40 0.13 CPD1
LDH-159 7226402.69 2623104.65 3899.57 36 48 12 0.67 0.15 CPD1
LDH-160 7226401.25 2623392.24 3897.96 No intervals of significance CPD1
LDH-161 7226401.20 2623303.54 3907.77 No intervals of significance CPD1
LDH-162 7226403.97 2623343.96 3900.63 No intervals of significance FPD
LDH-165 7226205.29 2623064.11 3947.10 28 60 32 0.44 0.14 DDP/CPD2
LDH-166 7226244.43 2623065.41 3940.71 No intervals of significance PMI
LDH-167 7226242.66 2623022.38 3941.63 No intervals of significance DDP/CPD2
LDH-168 7226243.74 2622984.73 3940.40 No intervals of significance DDP
LDH-169 7226367.30 2623225.69 3922.33 No intervals of significance PMI
LDH-172 7226203.58 2622905.93 3921.17 No intervals of significance PMI
LDH-178 7225966.14 2623026.94 3889.20 0 12 12 0.31 0.09 S1
LDH-179 7226005.87 2623104.15 3910.91 8 26 18 0.30 0.04 PMI/CPD2
LDH-189 7226013.72 2623344.14 3868.03 7 11 4 0.43 0.06 FPD
Units associated with mineralization:
FPD = Fine diorite porphyry
CPD1 = Crowded diorite porphyry 1
PBFD = Bimodal feldspar diorite porphyry
DDP = Mingled diorite porphyry
Units associated with non-mineralization:
CPD2 = Crowded diorite porphyry 2
PMI = Post mineralized intrusive
S1 = Tertiary sedimentary rocks
Notes:
1. All holes drilled vertically
2. The Lindero Deposit is a gold-rich porphyry with mineralization permeating throughout the deposit, making the calculation of true
thickness impossible as no definitive across strike direction exists.
Quality Assurance & Quality Control
Following detailed geological and geotechnical logging, drill core samples are split on -site by diamond
sawing. One half of the core is submitted to the ALS Global Laboratory in Mendoza, Argentina for
preparation. The remaining half core is retained on -site for verification and reference purposes.
Following preparation, the samples are assayed in the ALS Global Laboratory in Lima, Peru for gold by
standard fire assay methods; for silver and base metals by ICP and atomic emission spectroscopy
methods utilizing four acid digestion; and for cyanide soluble copper by atomic absorption methods. The
QA-QC program includes the blind insertion of certified reference standards and assay blanks at a
frequency of approximately 1 per 20 normal samples as well as the in clusion of duplicate samples for
verification of sampling and assay precision levels.
-4-
About the Lindero gold Project
In September 2017, the commencement of construction at Lindero was officially launched (see Fortuna
news releases dated September 21, 2017 and December 21, 2017 ). Lindero has been designed as an
18,750 t onnes per day owner operated open pit mine with a pit life of 13 years based on existing
mineral reserves. The initial capital cost budget estimate for the construction of Lindero is US$239
million, forecast to increase between 10% and 17% (refer to Fortuna news release dated August 7, 2018,
“Fortuna provides construction update and reports initial on -site arrival of mine equipment at its
Lindero gold Project in Argentina”); this amount does not include VAT which is expected to be recovered
in the first 24 months from the start of mining operations. The technical report of the Lindero Project is
available on SEDAR at www.sedar.com and on the Company's website at
https://www.fortunasilver.com/site/assets/files/4098/lindero-project-technical-report-effective-date-
31-oct-2017.pdf.
Qualified Person
Eric N. Chapman, M.Sc., Vice President of Technical Services, is the Qualified Person for Fortuna
Silver Mines Inc. as defined by National Instrument 43 -101. Mr. Chapman is a Professional Geoscientist
of the Association of Professional Engineers and Geoscientists of the Province of British Columbia
(Registration Number 36328) and has reviewed and approved the scientific and technical information
contained in this news release.
About Fortuna Silver Mines Inc.
Fortuna is a growth oriented, precious metal producer with its primary assets being the Caylloma silver
mine in southern Peru, the San Jose silver -gold mine in Mexico and the Lindero gold Project in
Argentina. The Company is selectively pursuing acquisition opportunities throughout the Americas and
in select other areas. For more information, please visit its website at www.fortunasilver.com.
ON BEHALF OF THE BOARD
Jorge A. Ganoza
President, CEO and Director
Fortuna Silver Mines Inc.
Trading symbols: NYSE: FSM | TSX: FVI
Investor Relations:
Carlos Baca
T (Peru): +51.1.616.6060, ext. 0
-5-
Forward looking Statements
This news release contains forward looking statements which constitute “forward looking information” within the
meaning of applicable Canadian securities legislation and “forward looking statements” within the meaning of the
“safe harbor” provisions of the Private Securities Litigation Reform Act o f 1995 (collectively, “Forward looking
Statements”). All statements included herein, other than statements of historical fact, are Forward looking
Statements and are subject to a variety of known and unknown risks and uncertainties which could cause actual
events or results to differ materially from those reflected in the Forward looking Statements. The Forward looking
Statements in this news release may include, without limitation, statements about the Company’s plans for its
mines and mineral properties , the estimated amount of and grade of mineral resources at Lindero, including the
construction and development of the Lindero gold Project ; the Company’s business strategy, plans and outlook; the
merit of the Company’s mines and mineral properties; mineral resource and reserve estimates; timelines; the future
financial or operating performance of the Company; expenditures; approvals and other matters. Often, but not
always, these Forward looking Statements can be identified by the use of words such as “estimated”, “potential”,
“open”, “future”, “assumed”, “projected”, “used”, “detailed”, “has been”, “gain”, “planned”, “reflecting”, “will”,
“containing”, “remaining”, “to be”, or statements that events, “could” or “should” occur or be achieved and similar
expressions, including negative variations.
Forward looking Statements involve known and unknown risks, uncertainties and other factors which may cause
the actual results, performance or achievements of the Company to be materially different from any results,
performance or achievements expressed or implied by the Forward looking Statements. Such uncertainties and
factors include, among others, whether the Company’s activities at the Lindero gold Project , including the
construction and development of the p roject will proceed as planned; the estimated amount of and grade of
mineral resources at Lindero, changes in general economic conditions and financial markets; changes in prices for
silver and other metals; technological and operational hazards in Fortuna’s mining and mine development
activities; risks inherent in mineral exploration; uncertainties inherent in the estimation of mineral reserves, mineral
resources, and metal recoveries; governmental and other approvals; political unrest or instability in countr ies where
Fortuna is active; labor relations issues; as well as those factors discussed under “Risk Factors” in the Company's
Annual Information Form. Although the Company has attempted to identify important factors that could cause
actual actions, events or results to differ materially from those described in Forward looking Statements, there may
be other factors that cause actions, events or results to differ from those anticipated, estimated or intended.
Forward looking Statements contained herein are based on the assumptions, beliefs, expectations and opinions of
management, including but not limited to : that the Company’s activities at the Lindero gold Project , including the
construction and development of the Project will proceed as planned; expectations regarding construction and
mine production costs; expected trends in mineral prices and currency exchange rates; the accuracy of the
Company’s current mineral resource and reserve estimates; that the Company’s activities will be in accordance with
the Company’s public statements and stated goals; that there will be no material adverse change affecting the
Company or its properties; that all required approvals will be obtained; that there will be no significant disruptions
affecting construction and ope rations of the Lindero gold Project and such other assumptions as set out herein.
Forward looking Statements are made as of the date hereof and the Company disclaims any obligation to update
any Forward looking Statements, whether as a result of new information, future events or results or otherwise,
except as required by law. There can be no assurance that Forward looking Statements will prove to be accurate, as
actual results and future events could differ materially from those anticipated in such statements. Accordingly,
investors should not place undue reliance on Forward looking Statements.