Fortuna reports production of 1.8 million ounces of silver and 10,101 ounces of gold for the first quarter of 2020

Production Results

Fortuna reports production of 1.8 million ounces of silver and 10,101 ounces of gold

for the first quarter of 2020

Vancouver, April 14, 2020-- Fortuna Silver Mines Inc. (NYSE: FSM) (TSX: FVI) is pleased to report

production results for the first quarter of 2020 from its two operating mines in Latin America, the San Jose

Mine in Mexico and the Caylloma Mine in Peru. The C ompany produced 1.8 million ounces of silver and

10,101 ounces of gold , plus base metal by -products. Government-mandated constraints on business to

curb the spread of COVID -19 in the countries that host our operations, ha ve resulted in reduced

production at the Caylloma Mine during the first quarter of 2020, and subsequent to the end of the

quarter, have resulted in the suspension of operations at the San Jose Mine. Due to the uncertainties

related to the impact of these constraints on the Company’s business and operations, the Company has

withdrawn its production and cost guidance for 2020 u ntil further notice (refer to Fortuna news release

dated April 2, 2020).

First Quarter Production Highlights

▪ Silver production of 1,819,312 ounces; 19 percent decrease over Q1 2019

▪ Gold production of 10,101 ounces; 24 percent decrease over Q1 2019

▪ Lead production of 7,722,793 pounds; 8 percent increase over Q1 2019

▪ Zinc production of 11,821,186 pounds; 5 percent increase over Q1 2019

▪ Cash cost1 for San Jose is US$71.1/t, in line with Q1 2020 budget

▪ Cash cost1 for Caylloma is US$80.8/t, in line with Q1 2020 budget

Consolidated Operating Highlights

First Quarter 2020 First Quarter 2019

Caylloma,

Peru

San Jose,

Mexico

Consolidated

Caylloma,

Peru

San Jose,

Mexico

Consolidated

Processed Ore

Tonnes milled 132,741 246,826 130,150 256,643

Average tpd milled 1,491 2,837 1,479 2,984

Silver2

Grade (g/t) 70 216 66 267

Recovery (%) 83.53 91.66 84.06 90.76

Production (oz) 249,111 1,570,201 1,819,312 233,836 1,999,495 2,233,331

Gold

Grade (g/t) 0.24 1.33 0.28 1.71

Recovery (%) 46.39 91.34 48.74 90.14

Production (oz) 471 9,630 10,101 573 12,741 13,314

-2-

First Quarter 2020 First Quarter 2019

Caylloma,

Peru

San Jose,

Mexico

Consolidated

Caylloma,

Peru

San Jose,

Mexico

Consolidated

Lead

Grade (%) 2.96 N/A 2.74 N/A

Recovery (%) 89.28 N/A 91.34 N/A

Production (lbs) 7,722,793 N/A 7,722,793 7,172,202 N/A 7,172,202

Zinc

Grade (%) 4.58 N/A 4.37 N/A

Recovery (%) 88.22 N/A 90.07 N/A

Production (lbs) 11,821,186 N/A 11,821,186 11,295,244 N/A 11,295,244

Notes:

1. Preliminary estimates of cash operating costs per tonne, subject to modification on final cost consolidation

2. Metallurgical recovery for silver at the Caylloma Mine is calculated based on silver content in lead concentrate

3. Totals may not add due to rounding

San Jose Mine, Mexico

The San Jose Mine produced 1,570,201 ounces of silver and 9,630 ounces of gold in the first quarter of

2020, 11 percent and 16 percent below budget respectively. Average head grades for silver and gold were

216 g/t and 1.33 g/t, 6 percent and 12 percent below budget respectively.

Lower silver and gold production in the first quarter was attributed to a decrease in processed tonnes and

to a variation in head grades . The decrease in processed tonnes is due to a stoppage in mining and

processing operations caused by illegal road blockades in the vicinity of the mine, including access to the

mine (refer to Fortuna news releases dated March 24, 2020 and March 25, 2020). The variation in head

grades is related to a planned modification in the mining sequence to allow preparation work to be

conducted for pillar recovery. This restricted access to high -grade material and resulted in mining more

variable peripheral stopes during the quarter. The decrease in metal production due to the modification

of the mining sequence is planned to be recovered throughout the remainder of the year, once

government-imposed restrictions on the mining industry are lifted and production at the mine

recommences.

Caylloma Mine, Peru

The Caylloma Mine produced 249,111 ounces of silver in the first quarter of 20 20, 17 percent above

budget. Average head grade for silver was 70 g/t, 17 percent above budget.

Lead and zinc production for the first quarter of 20 20 was 7,722,793 pounds and 11,821,186 pounds,

17 percent and 3 percent above budget respectively. Average head grades for lead and zinc were 2.96 %

and 4.58 %, 19 percent and 6 percent above budget respectively.

On Sunday, March 15, 2020, the Government of Peru introduced a series of measures to contain the rapid

spread of COVID-19. The Company, in compliance with the regulatory framework issued by the Ministerio

de Energía y Minas (MINEM) and the Ministerio del I nterior (MININTER), proceeded to demobilize non -

critical personnel and continued to operate, using essential personnel at Caylloma, by drawing ore from

its coarse ore stockpiles (refer to Fortuna news release dated March 17, 2020 ). In the first quarter,

-3-

86 percent of treated ore was sourced from the Animas vein grading 70 g/t Ag, 2.95% Pb and 4.57 % Zn

and 14 percent was sourced from coarse ore stockpiles grading 71 g/t Ag, 2.91% Pb and 4.65 % Zn.

Lindero Project, Argentina

Mining activity ramped up in the first quarter of 2020 with a total of 718,000 tonnes of mineralized

material and 1,766,000 tonnes of waste mined until March 19, 2020, when operations were suspended

due to a government declared period of mandatory national social isolation in relation to COVID-19 (refer

to Fortuna news release dated April 2, 2020 ). Prior to the shut-down, t he operation had successfully

achieved a mining rate of 40,000 tonnes per day which is required to support full production.

The table below details material movements from the pit as estimated from the grade control model

versus the Mineral Reserve block model for comparable volumes.

Grade Control Model1, 3 Mineral Reserve Model2, 3 Difference

Stockpile Tonnes 718,000 675,000 6.4 %

Au (g/t) 0.51 0.56 -8.9 %

Au (oz) 11,700 12,200 -4.1 %

Waste Dump Tonnes 1,766,000 1,801,000 -1.9 %

Notes:

1. Grade control model numbers are based on estimates from blast holes

2. Mineral Reserve model numbers are based on the updated Mineral Reserve estimates as of March 31, 2019 (refer to

Fortuna news release dated April 4, 2019). See also the Technical Report entitled “Fortuna Silver Mines Inc.: Lindero

Property, Salta Province, Argentina” with an effective date of October 31, 2017 prepared by Eric Chapman, Edwin

Gutierrez, Geoff Allard and Denys Parra Murrugarra. The updated Mineral Reserve estimate does not materially

change the information presented in the Technical Report.

3. Based on a cut-off grade of 0.26 g/t Au

Since the start of pre -production in September 2019, mining has focused on extracting medium to low -

grade material for stockpiling and preparing the mine through additional waste stripping, while actively

avoiding high-grade zones so that this material will be available as direct feed upon plant commissioning.

The main reason for the differences between the two models is related to the focus on extracting low

grade mineralized material and waste in the first quarter, as demonstrated by a high strip ratio of 2.46.

Mining predominantly in waste areas results in higher levels of dilution than would on average be

experienced. This level of dilution is not expected to be observed when mining switches to higher grade

areas.

Quality Assurance & Quality Control

Grade control estimates are based on blast hole chip samples submitted to Lindero´s on -site laboratory

for preparation and assaying for gold, using fire assay with an atomic absorption finish. The QA -QC

program includes the blind insertion of certified ref erence standards and assay blanks at a frequency of

approximately 1 per 20 normal samples as well as the submission of duplicate samples for verification of

sampling and assay precision levels by an ISO 9001:2000 certified umpire laboratory. ALS Global

Laboratory in Mendoza, Argentina prepared the samples for assaying and then forwarded the samples to

ALS Global Laboratory in Lima, Peru for assay by standard fire assay methods.

-4-

Qualified Person

Amri Sinuhaji, Technical Services Director – Mine Planning, for the Company is a Qualified Person as

defined by National Instrument 43 -101- Standards of Disclosure for Mineral Projects. Mr. Sinuhaji is a

Professional Engineer registered with the Association of Professional Engineers and Geoscientists of the

Province of British Columbia (# 48305) and has reviewed and approved the scientific and technical

information contained in this news release.

About Fortuna Silver Mines Inc.

Fortuna is a growth oriented, precious metals producer focused on mining opportunities in Latin America.

Our primary assets are the Caylloma silver Mine in southern Peru, the San Jose silver-gold Mine in Mexico

and the Lindero gold Project , currently unde r construction, in Argentina. The company is selectively

pursuing acquisition opportunities throughout the Americas and in select other areas. For more

information, please visit our website at www.fortunasilver.com.

Jorge A. Ganoza

President, CEO and Director

Fortuna Silver Mines Inc.

Trading symbols: NYSE: FSM | TSX: FVI

Investor Relations:

Carlos Baca

T (Peru): +51.1.616.6060, ext. 0

Forward-looking Statements

This news release contains forward -looking statements which constitute “forward -looking information” within the

meaning of applicable Canadian securities legislation and “forward -looking statements” within the meaning of the

“safe harbor” provisions of the Private Securities Litigation Reform Act of 1995 (collectively, “Forward -looking

Statements”). All statements included herein, other than statements of historical fact, are Forward -looking

Statements and are subject to a variet y of known and unknown risks and uncertainties which could cause actual

events or results to differ materially from those reflected in the Forward -looking Statements. The Forward-looking

Statements in this news release may include, without limitation, statements about the Company’s plans for its mines

and mineral properties; the duration and impacts of COVID-19 on the Company’s production, workforce, business,

operations and financ ial condition; the duration of the suspension of operations at the Company’s mines and the

Lindero Project; the Company’s business strategy, plans and outlook; the merit of the Company’s mines and mineral

properties; mineral resource and reserve estimates; production costs; timelines; the future financial or operating

performance of the Company; expenditures; approvals and other matters. Often, but not always, these Forward -

looking Statements can be identified by the use of words such as “estimated”, “pote ntial”, “open”, “future”,

“assumed”, “projected”, “used”, “detailed”, “has been”, “gain”, “planned”, “reflecting”, “will”, “containing”,

“remaining”, “to be”, or statements that events, “could” or “should” occur or be achieved and similar expressions,

including negative variations.

-5-

Forward-looking Statements involve known and unknown risks, uncertainties and other factors which may cause the

actual results, performance or achievements of the Company to be materially different from any results, performance

or achievements expressed or implied by the Forward -looking Statements. Such uncertainties and factors include,

among others, changes in general economic conditions and financial markets; the duration and impacts of COVID-19

on the Company’s production, workforce, business, operations and financial condition, and the risks relating to a

global pandemic, which unless contained could cause a slowdown in global economic growth; the duration of the

suspension of operations at the Company’s mines and the Lindero Project, the impact of the suspension of operations

on production and the Company’ business operations and financial condition; changes in prices for silver and other

metals; technological and operational hazards in Fortuna’s mining and mine development activities; risks inherent in

mineral exploration; uncertainties inherent in the estimation of mineral reserves, mineral resources, and metal

recoveries; changes to current estimates of mineral reserves and resources; changes to production and cost

estimates; governmental and other approvals; changes in government, political unrest or instability in countries

where Fortuna is active; labor relations issues; as well as those factors discussed under “Risk Factors” in the

Company's Annual Information Form. Although the Company has attempted to identify important factors that could

cause actual actions, events or results to differ materially from those described in Forward-looking Statements, there

may be other factors that cause actions, events or results to differ from those anticipated, estimated or intended.

Forward-looking Statements contained herein are based on the assumptions, beliefs, expectations and opinions of

management, including but not limited to the duration and impacts of COVID -19 on the Compan y’s production,

workforce, business, operations and financial condition, and the risks relating to a global pandemic, which unless

contained could cause a slowdown in global economic growth; the duration of the suspension of operations at the

Company’s min es and the Lindero Project, the impact of the suspension of operations on production and the

Company’ business operations and financial condition; the expected trends in mineral prices and currency exchange

rates; the accuracy of the Company’s current mineral resource and reserve estimates; that the Company’s activities

will be in accordance with the Company’s public statements and stated goals; that there will be no material adverse

change affecting the Company or its properties; that the reconciliation of mineral reserves at the Lindero Project

remains consistent with the mineral reserve model; that all required approvals will be obtained; that there will be no

significant disruptions affecting operations and such other assumptions as set out herein. Forwa rd-looking

Statements are made as of the date hereof and the Company disclaims any obligation to update any Forward-looking

Statements, whether as a result of new information, future events or results or otherwise, except as required by law.

There can be n o assurance that these Forward -looking Statements will prove to be accurate, as actual results and

future events could differ materially from those anticipated in such statements. Accordingly, investors should not

place undue reliance on Forward-looking Statements.

Cautionary Note to United States Investors Concerning Estimates of Reserves and Resources

Reserve and resource estimates included in this news release have been prepared in accordance with National Instrument 43-101

Standards of Disclosure for Mineral Projects ("NI 43 -101") and the Canadian Institute of Mining, Metallurgy, and Petroleum

Definition Standards on Mineral Resources and Mineral Reserves. NI 43 -101 is a rule developed by the Canadian Securities

Administrators that establishes standards for public disclosure by a Canadian company of scientific and technical information

concerning mineral projects. Equivalent U.S. reporting requirements are currently governed by the United States Securities and

Exchange Commission ("SEC") Industry Guide 7 (“Industry Guide 7”) under the U.S. Securities Act of 1933, as amended. Canadian

standards, including NI 43-101, differ significantly from the requirements of the SEC currently in effect under Industry Guide 7, and

reserve and resource information contained in this news release may not be comparable to similar information disclosed by U.S .

companies. In particular, the term "resource" does not equate to the term "reserves". Under the SEC's disclosure standards

currently in effect under Industry Guide 7, mineralization may not be classified as a "reserve" unless the determination has been

made that the min eralization could be economically and legally produced or extracted at the time the reserve determination is

made. While the SEC recognizes the reporting of mineral deposits which do not meet the Industry Standard Guide 7 definition of

“reserve” as of Febr uary 25, 2019, the effective adoption of the Modernization of Property Disclosures for Mining Registrants,

such rules are not required to be compiled with until the first fiscal year beginning on or after January 1, 2021. As a result, the

SEC's disclosure standards currently in effect normally do not permit the inclusion of information concerning "measured mineral

resources", "indicated mineral resources" or "inferred mineral resources" or other descriptions of the amount of mineralization in

mineral deposits that do not constitute "reserves" by U.S. standards in documents filed with the SEC. You are cautioned not to

assume that resources will ever be converted into reserves. You should also understand that "inferred mineral resources" have a

great amount of uncertainty as to their existence and great uncertainty as to their economic and legal feasibility. You should also

-6-

not assume that all or any part of an "inferred mineral resource" will ever be upgraded to a higher category. Under Canadian

rules, estimated "inferred mineral resources" may not form the basis of feasibility or pre -feasibility studies except in rare cases.

You are cautioned not to assume that all or any part of an "inferred mineral resource" exists or is economically or legally mineable.

Disclosure of "contained ounces" in a resource is permitted disclosure under Canadian regulations; however, the SEC's disclosure

standards currently in effect under Industry Guide 7 normally only permit issuers to report mineralization that does not constitute

"reserves" by such standards as in -place tonnage and grade without reference to unit measures. The requirements of NI 43 -101

for identification of "reserves" are also not the same as those of the SEC's disclosure standards currently in effect under I ndustry

Guide 7, and reserves reported in compliance with NI 43-101 may not qualify as "reserves" under such SEC standards. Accordingly,

information concerning mineral deposits set forth in this news release may not be comparable with information made public b y

companies that report in accordance with U.S. standards.