Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

FVI.TO ·

Fortuna announces positive construction decision for its Lindero gold Project in Salta, Argentina

Mine Development & Operations Mergers & Acquisitions

Fortuna announces positive construction decision for its Lindero gold Project in

Salta, Argentina

(All dollar amounts are expressed in US dollars unless otherwise indicated)

Vancouver, September 21, 2 017-- Fortuna Silver Mines Inc. (NYSE: FSM) (TSX: FVI) is pleased to

announce today that the Board of Directors of the Company has made a positive construction decision

for the 100% owned Lindero gold Project located in the Province of Salta, Argentina. In July 2016,

Fortuna completed the acquisition of Goldrock Mines Corp. whose principal asset was the Lindero

Project (see Fortuna news release dated July 28, 2016 ). Lindero has an approved environmental impact

study and has been granted all major permits for the construction of an 18,750 tpd open pit, heap leach

gold mine.

Jorge Ganoza, President, CEO and Director, commented, “With a base case IRR 1 of 18% and a 3. 6 year

payback, we have delivered a strong project greatly derisked technically and financially that will

contribute low cost gold production over its 15 years of operation. Initial capital of $239 million is going

to be comfortably funded from our approximately $190 million cash position, available lines of credit

and projected cash flows. We do not envision accessing equity capital markets or having to tak e hedge

positions for this project.” Mr. Ganoza continued, “The optimization work conducted over the past year

has captured opportunities for improved metallurgical recovery and reduced leach time. At the same

time, technical risks have been mitigated on th e process side by bringing in a SART 2 plant, ore

agglomeration and a conveyor stacking system to year one.” Mr. Ganoza added, “Under our

construction plan, detailed engineering and site activities are expected to commence next month with

commissioning expected in the second quarter of 2019.” Mr. Ganoza concluded, “In the first year of full

production, Lindero will take Fortuna's annual production to approximately 9 million ounces of silver

and 190,000 ounces of gold or 340,000 gold equivalent2 ounces.”

Figures reported in this news release supersede those stated in the Goldrock 2016 Feasibility Study. An

updated feasibility study technical report will be filed on SEDAR at www.sedar.com and posted on our

website at https://www.fortunasilver.com/mines-and-projects/technical-reports/ within forty-five days

from the date of this news release.

Notes:

1. IRR: Internal Rate of Return

2. SART: Sulphidization-Acidification-Recycle-Thickening

3. Gold equivalent ounces calculated using a gold to silver ratio of 1 to 60

2

Life of Mine Highlights

Mine life 1 (years) 15

Annual ore placed in leach pad (Mt) 6.75

Strip ratio (waste to ore) 1.2

Head grade (g/t) 0.62

Recovery (%) 75

Gold recovered to doré (Moz) 1.3

Average annual gold recovered to doré 2 (koz) 96

Peak annual gold recovered to doré (koz) 138

AISC3 ($/oz Au) 802

Initial capital ($ M) 239

Sustaining capital ($ M) 105

Gold price ($) 1,250

Exchange rate (ARS4:USD) 17.80

After-tax NPV 5 @ 5% ($ M) 130

After-tax IRR6 (%) 18

Payback period7 (years) 3.6

Production

Base Case Economics

Notes:

1. Includes 20 months of heap rinsing of gold inventory

2. Average over years 1 – 13. Does not include gold from heap rinsing.

3. All-In Sustaining Cash Cost

4. Argentine Peso

5. Net Present Value; considers initial capital in one single annual period; excludes High -Pressure-Grinding-Roller

(HPGR) acquired upon the acquisition of Goldrock Mines Corp.

6. Considers initial capital in one single annual period; excludes High-Pressure-Grinding-Roller (HPGR) acquired

upon the acquisition of Goldrock Mines Corp.

7. Payback based on undiscounted cash flow

The Lindero porphyry gold system remains open at depth below the current pit shell of reserves and

resources with high grade drill intercepts bottoming on mineralization . The nearby Arizaro p orphyry

system, located within the Lindero concession, is a ne ar term exploration target discussed, along with

Lindero and other exploration prospects, in the Brownfields Exploration Opportunities section in this

news release.

Lindero After-Tax Economics Sensitivity Analysis

Gold Price NPV @ 5% IRR Payback Period

($/oz) ($ M) (%) (Years)

1,150 68 12 4.7

1,250 130 18 3.6

1,350 192 23 3.1

1,450 253 28 2.4

3

Mineral Reserves and Resources

Mineral Reserves and Resources are reported as of September 9, 2017 based on 132 diamond drill holes

totaling 37,897 meters and the addition of 12 new holes drilled by Fortuna in 2016 totaling 4,462

meters. The estimates incorporate a revised geological interpretation and updated metallu rgical

recoveries, metal prices and estimated operating costs.

Mineral Resource estimation involved the usage of drill hole samples in conjunction with surface

mapping to construct three -dimensional wireframes defining lithologic, alteration, and grade dom ains.

Samples were selected inside these wireframes, coded, composited and top cut. Boundaries were

treated as hard, firm or soft based on statistical and geostatistical analysis. Gold and copper grades were

estimated by ordinary kriging into a geological block model consisting of 10 m x 10 m x 4 m selective

mining units representing each domain. Estimated grades were validated globally, locally, and visually

prior to classification and are reported above a 0.20 g/t Au cut-off grade within a conceptual pit shell.

Mineral Reserve estimates have considered only Measured and Indicated Mineral Resources as only

these categories have sufficient geological confidence to be considered Mineral Reserves. Subject to the

application of certain economic and mining-related qualifying factors, Measured Resources may become

Proven Reserves and Indicated Resources may become Probable Reserves.

Contained Metal

Tonnes Au Cu Au

(000) (g/t) (%) (koz)

Prove n 26,009 0.74 0.11 618

Probable 62,263 0.57 0.11 1,131

Proven + Probable 88,272 0.62 0.11 1,749

Mineral Resources Contained Metal

Tonnes Au Cu Au

(000) (g/t) (%) (koz)

M easured 610 0.24 0.06 5

Indicated 11,897 0.24 0.07 92

Measured + Indicated 12,507 0.24 0.07 97

Inferred 5,700 0.36 0.10 65

Mineral Reserves - Proven and Probable

Lindero, Argentina

ClassificationProperty

Lindero, Argentina

ClassificationProperty

Notes:

1. Mineral Reserves and Resources are as defined by CIM Definition Standards on Mineral Resources and Mineral Reserves

2. Mineral Resources are exclusive of Mineral Reserves

3. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability

4. There are no known legal, political, environmental, or other risks that could materially affect potential development of the

Mineral Resources or Mineral Reserves at Lindero

5. Mineral Resources and Mineral Reserves for Lindero are reported as of September 9, 2017

6. Mineral Reserves for Lindero are reported based on open pit mining within designed pit shells based on variable gold cut -off

grades and gold recoveries by metallurgic al type. Met type 1 cut- off 0.27 g/t Au, recovery 75.4%; Met type 2 cut -off 0.26 g/t

Au, recovery 78.2%; Met type 3 cut- off 0.26 g/t Au, recovery 78.5%; and Met type 4 cut -off 0.30 g/t Au, recovery 61.7%. The

cut-off grades and pit designs are considered appropriate for long term gold prices of $1,250/oz

7. Lindero Mineral Resources are reported within a conceptual pit shell above a 0.2 g/t Au cut -off grade using a long- term gold

price of $1,250/oz, mining costs at $1.67 per tonne of material, with total proc essing and process G&A costs of $7.84 per

tonne of ore and an average process recovery of 75%. The refinery costs net of pay factor were estimated to be $6.90 per

ounce of gold. Slope angles are based on 3 sectors (39°, 42°, and 47°) consistent with geotec hnical consultant

recommendations

8. Eric Chapman, P.Geo. (APEGBC #36328) is the Qualified Person for resources and Edwin Gutierrez (SME Registered Member

#4119110RM) is the Qualified Person for reserves, both being employees of Fortuna Silver Mines Inc.

9. Totals may not add due to rounding procedures

4

Lindero Initial Capital Costs

The fully scoped initial capital cost is estimated at $239 million including $19 million for owner operated

mining fleet and $24 million for contingencies. Estimated capital costs are based on the cost

environment in Argentina for the first semester of 2017. Sustaining capital for the project is estimated at

$105 million.

Initial Capital Costs

Description ($ M)

Road infrastructure 2

Mine equipment and development 22

Crushing 26

Agglomeration 9

Leach pad 27

Stacking and solution handling 18

ADR1, electrowinning and refinery 13

SART plant 22

Laboratories 3

Power distribution 3

Camp and ancillary facilities 15

Water supply and distribution 10

Total Direct Costs 169

Commissioning 2

Construction indirect costs (catering, temporary camps, energy, etc.) 8

Spare parts 2

Owner´s cost 19

EPCM2 16

Contingency 24

Total Indirect Costs 70

Total Construction CAPEX3 239

Pre-production operating expenses 10

Capital credit net of taxes (14)

Working capital 4

Total Initial Capital 239

Notes:

1. ADR: Adsorption, Desorption and Recovery

2. EPCM: Engineering, Procurement, Construction and Management

3. CAPEX: Capital Expenditure; excludes High-Pressure-Grinding-Roller (HPGR) acquired upon the acquisition of Goldrock

Mines Corp.

4. Totals may not add due to rounding

5

Life of Mine Capital

Description ($ M)

Mine equipment 42

Leach pad second phase 29

Closure 35

Sustaining CAPEX 105

ADR expansion 8

Sustaining + Expansion CAPEX 113

Note: Totals may not add due to rounding

Lindero Operating Costs

Lindero cost estimates consider an owner operated mining fleet and on -site diesel power generation

provided by a contractor. Estimated electricity cost is $0.21 per kilowatt hour with a diesel cost of $2.20

per gallon.

Life of Mine Operating Costs

Cash Cost per tonne of Processed Ore Cash Cost per ounce

($/t) ($/oz)

Mine 2.5 166

Plant 5.5 371

General services 1.2 80

Administrative services mine 0.9 64

Distribution and gold refining costs 0.2 12

Cash Cost 10.3 692

Copper credits - (34)

Cash Cost net of by-product credits - 658

General and administrative - 35

Royalties and other taxes - 29

Sustaining capital - 81

AISC - 802

Description

Note: Totals may not add due to rounding

6

Metallurgical Testing and Mineral Processing

Metallurgical Testing

The Lindero project has an extensive body of metallurgical investigation comprised of several phases of

test work as indicated in the Goldrock 2016 Technical Report (see 2016 Goldrock Technical Report ).

Since September 2016, Fortuna has carried out complementary metallurgical test work in the areas o f

comminution, heap permeability and cement agglomeration, gold extraction in column tests, and

copper removal with SART technology with the purpose of confirming and optimizing process design

criteria.

The table below shows key gold extraction results for 10 -meter columns from laboratory test work,

carried out in the first semester of 2017, on material cured in a cyanide solution and agglomerated. A

4% deduction has been accounted for design purposes when going from laboratory results to the field.

Key Gold Extraction Results for 10-meter Columns

Met Type in Reserve Estimation Laboratory Field

(%) (%) (%)

1 Fresh intrusive 63 79.4 75.4

2 Oxide porphyry 20 83.0 79.0

3 Fresh porphyry 9 82.7 78.7

4 Sediments 8 72.8 68.8

Weighted average: 79.9 75.9

Met Type

Gold Extraction

Met Type Description

Optimization of the process design has confirmed the be nefit of the use of a High -Pressure-Grinding-

Roller (HPGR), the inclusion of cyanide cure of ore, and copper removal/ cyanide recovery with a SART

plant. Results indicate that these components allow for improved gold leaching kinetics and effective

extraction of copper from the pregnant solution.

Mineral Processing

Ore will be crushed at a nominal rate of 18,750 tpd using a three -stage crushing system including a

HPGR in the tertiar y stage. A final crush size of P 80 6.0 millimeter is projected. The crushed product will

be agglomerated and cured with a cyanide solution and then conveyed to the leach pad. A mobile

conveying and stacking system will be used to stack ore in 10 meter high lifts. Life of mine (LOM) leach

pad area is projected at 105 hectares with a maximum height of 100 meters. Leaching will be carried in

two stages with a first stage of 30 days and a second stage of 60 days.

The gold pregnant solution will be pumped at a rate of 400 cubic meters per hour to a SART plant, where

copper content in solution will be precipitated in order to maintain copper levels below 400 parts per

million in the solution. The project contemplates an expansion of the pregnant solution flow rate from

400 cubic meters per hour to 600 cubic meters per hour in year four with the objective of reducing

inventory of gold ounces in the heap at the end of mining.

7

Following the SART plant, the pregnant sol ution will go to an ADR plant and then to electrowinning and

refining where gold will be poured in doré bars. Life of mine recovery is estimated at 75%.

Mining

Lindero will be an owner operated conventional open pit mining operation with a nominal rate of

18,750 tpd of ore and a life of pit operations of 13 years using existing reserves. The ratio of waste to

ore over LOM is 1.2 to 1. The key mining fleet equipment will be initially composed of six 100 ton trucks

and two 17 cubic yard wheel loaders.

In the initial two years, the operation will benefit from mining the higher grade outcropping portion of

the deposit, with an average head grade of 0.9 0 g/t Au, and a low s trip ratio of 0.77 to 1. For the initial

four years, the average head grade is projected at 0.77 g/t Au and a strip ratio of 1 to 1.

Mining costs benefit from short haul distances from the pit to the primary crusher and waste dumps.

Maximum distances are in the range of 2 kilometers. LOM direct mine cost is estimated at $1.1 per

tonne moved.

Refer to the appendix for LOM annual production plan.

Environmental Studies and Permitting

All necessary permits have been granted by the Salta provincial government for the development of

Lindero as an open pit, heap leach gold mine.

In November 2010, Mansfield Minera (subsidiary of Fortuna) submitted an E nvironmental Impact

Assessment (EIA) for the Lindero Project, and in November 2011 received approval thr ough the issue of

the Declaració n de Impacto Ambiental. Approval of the EIA represents formal approval for mine

construction, allowing excavation to proceed. Environmental law requires that the EIA be updated

biannually with the current report submitted in December 2015 and an updated report planned for

submission in March 2018.

In addition, a formal public declaration of support for the Lindero development has been issued by the

provincial government, recognizing Lindero as the priority development project for the Salta province.

Key Infrastructure

Access Roads and Site Access

Lindero is located 260 kilometers due west of the city of Salta, the main service center for the project

and the region. Drive time from Salta to the project is approximately 7.5 hours over a road distance of

420 kilometers with good year round access.

The project site infrastructure has a compact layout footprint of approximately 60 hectares.

8

Power Supply

Power will be generated on-site by a contractor through an 8 MW capacity diesel oil plant.

Water Supply

Process water requirements are 105 cubic meters per hour and will be sourced from two existing wells

located 13 kilometers south east from the project site. An additional well is required and will be drilled

as part of construction activities.

Camp Facilities

A permanent accommodation c amp for 320 beds will be built for the LOM operation. For the

construction period, temporary accommodations will be implemented to accommodate the peak of

construction manpower estimated at 600 people.

Brownfields Exploration Opportunities

Arizaro Gold-Copper Porphyry System

The Arizaro Project is located within the Lindero mining concession, 3.2 kilometers southeast of the

Lindero Project. Historic work has included regional and local mapping, trenching with surface rock -chip

sampling (27 trenches, 6,568 total meters, 495 samples) and drilling (8,854 meters, 29 core holes)

completed over four campaigns (2002 and 2010-2013). Drill results include hole ARD-24 intersecting 160

meters averaging 0.64 g/t Au, including 104 meters averaging 0.82 g/t Au.

Drill Hole Highlights

Azimuth Dip From To Interval Au Cu

(°) (°) (m) (m) (m) (g/t) (%)

ARD-13 12 180 168 0.61 0.22

including 100 130 30 1.81 0.40

ARD-21 20 359 339 0.43 0.17

including 28 122 94 0.66 0.18

ARD-24 90 250 160 0.64 0.24

including 120 224 104 0.82 0.26270 -78

Drill Hole

235 -86

-70348

Since August 2016, Fortuna has completed the following work at the Arizaro project aimed at geologic

re-interpretation of the porphyry system and identifying near surface gold resources that could

materially add economic benefit to the Lindero Project:

• Relogging of 8,817 meters (29 drill holes) of historic core - similar geology, alteration and

mineralization are found at both Lindero and Arizaro

• Remapping (1:2,000 scale) of the entire surface area from immediately southeast of Lindero to

and including the historic drilling at Arizaro