FORTUNE MINERALS REPORTS FEDERAL GOVERNMENT FUNDING FOR TLICHO ALL-SEASON ROAD TO THE COMMUNITY OF WHATI Public road will enable NICO Mine operations as Fortune seeks financing for construction
January 12, 2017 Issued Capital: 270,899,007
NEWS RELEASE
FORTUNE MINERALS REPORTS FEDERAL GOVERNMENT FUNDING FOR
TLICHO ALL-SEASON ROAD TO THE COMMUNITY OF WHATI
Public road will enable NICO Mine operations as Fortune seeks financing for
construction
LONDON, ONTARIO, Fortune Minerals Limited (TSX: FT) (OTCQX: FTMDF) (“Fortune” or the
“Company”) (www.fortuneminerals.com) is pleased to report that the Government of Canada, the
Government of the Northwest Territories (“ GNWT”) and the Tlicho Government have jointly
announced federal funding for the construction of the Tlicho All-Season Road (“ TASR”) to the
community of Whati (See January 11, 2017 news release link). The federal government will provide
up to 25 per cent of the construction costs for this road through the P3 Canada Fund. Procurement of
the TASR - through a GNWT Public-Private-Partnership, will start with the release of the Request for
Qualifications in February 2017, and will be followed by a Request for Proposal and bids from private
industry to provide combined finance and construction.
Like our news? Click-to-Tweet.
Whati is located 50 km south of Fortune’s proposed NICO Cobalt-Gold-Bismuth-Copper Mine, which
has already received its environmental assess ment approval and the major mine permits for
construction, including a 50 km spur road to Whati. The TASR is a critical enabler for mine operations
and will allow the Company to truck metal concentrates south to the rail head at Hay River for railway
delivery to its proposed refinery in Saskatchewan for downstream processing to value added
products. With development of the NICO Project, Fortune would become an important supplier of
cobalt chemicals needed to manufacture lithium-ion batteries used in portable electronic devices,
electric vehicles and stationary storage cells. The NICO mineral reserves also contain more than 1.11
million ounces of gold and 12% of global bismuth reserves.
David Massola, Fortune’s Vice President of Finance and CFO, commented, “With cobalt and gold
prices firming, and greater certainty of an all-season road, Fortune is well-positioned to secure the
financing needed to begin construction of the NICO mine.”
David Ramsay, a Fortune director and former GNWT Cabinet Minister, said, “This investment in public
infrastructure addresses concerns over the reliability, safety and high annual costs of maintaining
winter ice roads for Tlicho community re-supply and socio-economic connectivity. This all-season
connection of Whati to the Northwest Territories public highway system will reduce the cost of living
and improve the delivery of services in the outlying Tlicho communities. It will also help diversify the
economy by providing commutable employment to the NICO Mine and nearby Snare Hydro Complex,
while reducing the cost of future hydro expansions, and promote mineral exploration and development
and tourism.”
About the Tlicho All-Season Road:
The TASR will consist of approximately 97 km of a new 2-lane road from Highway 3 to the community
of Whati, and includes four new bridges and one large arched culvert. The GNWT Department of
Transportation has been working closely with the Tlicho Government since 2012 on the TASR
initiative to provide reliable year-round all-weather public road access to the community of Whati and
FORTUNE MINERALS LIMITED
148 Fullarton Street, Suite 1600, London, Ontario, Canada N6A 5P3
Tel. 519-858-8188 ~ Fax. 519-858-8155
improved winter road access to the communities of Gameti and Wekweti. The routing for the TASR
follows an existing brownfield land-based winter road route to minimize environmental disturbance
and lower construction costs. The project is currently in the late stages of environmental assessment
led by the Mackenzie Valley Environmental Impact Review Board and is expected to be completed
this summer. Confirmation that funding is now available will inform the environmental assessment
process in terms of timing for construction.
About NICO:
Fortune owns a 100% interest in the NICO Cobalt-Gold-Bismuth-Copper project, a planned Canadian
vertically integrated producer of cobalt chemicals for the lithium-ion battery industry, with gold and
bismuth co-products, and copper as a minor by-product. More than $115 million has been spent by
Fortune advancing this project from an in-house disco very in the mid-1990’s to a development asset
with a positive feasibility st udy and environmental assessment approvals for both the mine and
concentrator in the Northwest Territories and refinery in Saskatchewan. NICO has also been test
mined and pilot plant processed to mitigate development risks, Front-End Engineering and Design
(“FEED”) studies have been completed with detailed engineering for procurement, and the Company
has an execution plan for project delivery. Fortune is working to secure off-take agreements and
project financing to commence construction.
NICO has proven and probable mineral reserves totaling more than 33 million tonnes that will support
a 21-year mine life at a planned mill throughput rate of 4,650 metric tonnes of ore per day.
Approximately 180 wet tonnes of bulk concentrate are planned to be produced per day containing the
recoverable metals for shipment south to the refinery in Saskatchewan and downstream processing to
value-added metals and chemicals. Life of mine average annual production is projected to be 41,300
ounces of gold, 1,615 tonnes of cobalt contained in a battery grade cobalt sulphate, 1,750 tonnes of
bismuth contained in metal ingots and oxide powder, and 265 tonnes of copper.
The disclosure of scientific and technical information contained in this press release has been
approved by Robin Goad, M.Sc., P.Geo., President and Chief Executive Officer of Fortune, who is a
“Qualified Person” under National Instrument 43-101. The technical report on the feasibility study
referred to above, entitled “Technical Report on the Feasibility Study for the NICO-Gold-Cobalt-
Bismuth-Copper Project, Northwest Territories, Canada”, dated April 2, 2014 and prepared by Micon
International Limited, from which certain informat ion in this press release has been extracted, has
been filed on SEDAR and is available under the Company’s profile at www.sedar.com.
About Fortune Minerals
Fortune is a Canadian development stage mining company focused on advancing the vertically
integrated NICO gold-cobalt-bismuth-copper project in the Northwest Territories and a related refinery
the Company plans to construct in Saskatchewan. Fortune also owns the Sue-Dianne copper-silver-
gold deposit located 25 km north of NICO and a potential future source of incremental mill feed to
extend the life of the NICO mill. The Company also maintains the right to repurchase the Arctos
anthracite coal deposits in northwest British Columbia that were recently purchased by a provincial
Crown corporation.
Follow Fortune Minerals:
Click here to subscribe to Fortune’s email list.
Click here to follow Fortune on LinkedIn.
For further information please contact:
Fortune Minerals Limited
Troy Nazarewicz
Investor Relations Manager
Tel.: (519) 858-8188
www.fortuneminerals.com
This press release contains forward-looking informat ion and forward-looking statements within the meaning of
applicable securities legislation. This forward-looking information includes statements with respect to, among
other things, the Company’s plans to develop the NICO project and the proposed construction of the TASR.
Forward-looking information is based on the opinions and estimates of management as well as certain
assumptions at the date the information is given (incl uding, in respect of the forward-looking information
contained in this press release, assumptions regarding the Company’s ability to arrange the necessary financing
to continue operations and develop the NICO project and the construction of the TASR). However, such
forward-looking information is subject to a variety of ri sks and uncertainties and other factors that could cause
actual events or results to differ materially from those projected in the forward-looking information. These factors
include the risks that the Company may not be able to finance and develop NICO on favourable terms or at all,
the TASR may not be constructed within the antici pated time frame and other operational and development
risks, market risks and regulatory risks. Readers ar e cautioned to not place undue reliance on forward-looking
information because it is possible that predictions, fore casts, projections and other forms of forward-looking
information will not be achieved by the Company. The fo rward-looking information contained herein is made as
of the date hereof and the Company assumes no responsibilit y to update or revise it to reflect new events or
circumstances, except as required by law.