Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

FPX.V ·

FPX Nickel Reports Value Engineering Studies Outlining Improvements in Mineral Processing Facilities and Validating PFS Project Schedule

Economic Studies

Suite 320 – 1155 West Pender Street

Vancouver, BC Canada V6E 2P4

Tel: 604.681.8600

e-mail: [email protected]

FPX Nickel Reports Value Engineering Studies Outlining

Improvements in Mineral Processing Facilities and Validating PFS

Project Schedule

Vancouver, July 10, 2024 – FPX Nickel Corp. (TSX-V: FPX, OTCQB: FPOCF) (“FPX” or the

“Company”) is pleased to provide an update on value engineering (“Value Engineering”) studies focused

on the mineral processing and infrastructure facilities for the Baptiste Nickel Project (“ Baptiste” or “the

Project”) in central British Columbia. The mineral processing and infrastructure Value Engineering studies

have achieved significant value creation through facility optimization, flowsheet refinement, enhanced

operability, and improvements to the project build strategy and execution basis.

Highlights

• Primary crushing: Changing from a gyratory-type primary crusher to mineral sizers has reduced

earthwork and structural quantities, improved Phase 1 operability, and eliminated the need for a

second primary crushing circuit in Phase 2

• Concentrator expansion: A new integrated approach to the Phase 2 expansion has reduced overall

quantities, improved Phase 2 operability, and reduced the footprint of process and infrastructure

facilities

• Project phasing: The phased approach and throughput rates in the preliminary feasibility study

(“PFS”) have been validated, while acceleration of the Phase 2 expansion improves Baptiste’s

metal production profile

• Execution schedule has been confirmed, further validating the PFS’s estimated three-year

construction duration

“Results from our mineral process and infrastructure Value Engineering studies have added significant

value to the Baptiste Nickel Project,” commented Andrew Osterloh, the Company’s Senior Vice President,

Projects & Operations. “By reducing quantities, improving operating efficiency, and advancing the project

execution plan, we have enhanced Baptiste’s potential as a long life, large-scale, low-cost, and low-carbon

producer of made-in-Canada nickel units. We look forward to advancing additional engineering studies on

the mining and refinery aspects of the Project in advance of commencing a feasibility study.”

Background

The Baptiste 2023 preliminary feasibility study (“ PFS”) demonstrates the potential to develop a high -

margin and low-carbon nickel mine producing an average of 59,100 tonnes per year of nickel over a 29 -

year mine life (see the Company’s September 6, 2023 news release). Due to awaruite’s properties, Baptiste

has the unparalleled flexibility to produce either a high-grade concentrate (60% nickel) for direct feed into

the stainless steel industry (the “ Base Case”) or for further refining into battery -grade nickel, cobalt, and

copper products for the electric vehicle battery supply chain (the “Refinery Option”).

While the PFS presents robust economics, including a Base Case after-tax NPV8% of US$2.01 Billion and

after-tax IRR of 18.6% at US$8.75 /lb Ni, FPX strives to add further value to Baptiste, focusing on a holistic

blend of economics, constructability, operability, risk and ESG considerations.

The key Value Engineering studies pursued by FPX in 2024 are:

• Mineral processing and infrastructure (described herein)

• Mine planning and engineering (to be completed in the third quarter of 2024)

• Refinery planning (to be completed in the third quarter of 2024)

Mineral Processing & Infrastructure Value Engineering Studies

FPX engaged Fluor Canada Ltd. (“Fluor”) and Wood Canada Ltd. (“Wood”) to perform detailed reviews

of the 2023 PFS and to conduct mineral process and infrastructure Value Engineering studies . The

consultants identified three primary opportunities to add further value, which are described in greater detail

hereunder:

• Primary crushing: application of mineral sizers

• Phase 2 concentrator expansion

• Project phasing

As described below , each of the mineral process and infrastructure Value Engineering studies validated

several key tenets from the PFS and added significant project value through reduced quantities, improved

operability, reduced process operating costs, and reduced process and infrastructure footprint.

Primary Crushing

The PFS considered a gyratory -type primary crusher. In re-evaluating the Project’s geotechnical and

communication datasets , the Company has identified an opportunity to use mineral sizers for primary

crushing. Taking advantage of the modest compressi ve strength and fractured nature of the Baptiste ore,

mineral sizers have added significant value through reduced earthwork and structural quantities, increased

operating availability, and the complete elimination of the second primary crushing line for the pl anned

mine expansion from an initial Phase 1 processing throughput of 108,000 tonnes per day (“tpd”) to 162,000

tpd in Year 10 (“Phase 2”).

Phase 2 Concentrator Expansion

The PFS considered the construction of a standalone processing facility for the Phase 2 expansion from

108,000 tpd to 162,000 tpd. A new approach to expansion is based on an integrated concentrator approach

which entails an expansion of the Phase 1 processing facility rather than the construction of a new

standalone facility for Phase 2 . This integrated approach results in a reduced process and infrastructure

footprint, improved Phase 2 operability, and reduced Phase 2 work force requirements.

Project Phasing

A Value Engineering study re-evaluated the phased approach to processing throughput and compared it

with a series of single-build scenarios ranging from 80,000 to 163,000 tpd. Following this evaluation, the

PFS’s phased approach has been validated; however, the Phase 2 expansion has been accelerated to Year 6

from Year 10. This acceleration in metal production is expected to generate improved economics versus

the PFS, with the Phase 2 expansion funded from operating free cash flow following the 3.7 year after-tax

payback demonstrated in the PFS.

Project Execution

Both Fluor and Wood were assigned further scope to review the PFS’ s execution basis, including the

permanent facility layout, construction sequence, contracting approach, and overall execution schedule.

Note that Fluor and Wood jointly executed the detailed engineering and construction management of the

nearby Mt. Milligan Mine, which was commissioned in 2013 and is located 80 km east of Baptiste . Mt.

Milligan is of comparable size and complexity to Baptiste , which uniquely positions Fluor and Wood to

provide relevant context to the Baptiste project execution plan.

Through this additional execution planning effort , numerous scheduling improvements to the PFS were

identified, thereby improving the constructability, operability, and maintainability of Baptiste. In addition,

increased focus on allowances for temporary construction facilities has improved execution scope assurance

ahead of the environmental assessment and permitting processes. Fundamentally, these robust execution

planning efforts further de-risk the Baptiste execution schedule, including the PFS assumption of a three-

year construction period.

Andrew Osterloh, P.Eng., FPX Nickel’s Qualified Person under NI 43-101, has reviewed and approved

the technical content of this news release.

About the Decar Nickel District

The Company’s Baptiste Nickel Project represents a large -scale greenfield discovery of nickel

mineralization in the form of a sulphur -free, nickel -iron mineral called awaruite (Ni 3Fe) hosted in an

ultramafic/ophiolite complex. The Baptiste mineral claims cover an area of 408 km2 west of Middle River

and north of Trembleur Lake, in central British Columbia. In addition to the Baptiste Deposit itself,

awaruite mineralization has been confirmed through drilling at several target areas within the same claims

package, most notably at the Van Target which is located 6 km to the north of the Baptiste Deposit. Since

2010, approximately US $30 million has been spent on the exploration and development of Baptiste.

The Baptiste Deposit is located within the Baptiste Creek watershed, on the traditional territories of the

Tl’azt’en Nation and the Binche Whut’en, and within several Tl’azt’enne and Binche Whut’enne keyohs.

FPX has conducted mineral exploration activities to date subject to the conditions of agreements with First

Nations and keyoh holders.

About FPX Nickel Corp.

FPX Nickel Corp. is focused on the exploration and development of the Decar Nickel District, located in

central British Columbia, and other occurrences of the same distinctive style of awaruite nickel -iron

mineralization. For more information, please vie w the Company’s website at https://fpxnickel.com/ or

contact Martin Turenne, President and CEO, at (604) 681-8600 or [email protected].

On behalf of FPX Nickel Corp.

"Martin Turenne"

Martin Turenne, President, CEO and Director

Email: [email protected]

Phone: 604-681-8600

Forward-Looking Statements

Certain of the statements made and information contained herein is considered “forward -looking

information” within the meaning of applicable Canadian securities laws. These statements address future

events and conditions and so involve inherent risks and u ncertainties, as disclosed in the Company's

periodic filings with Canadian securities regulators. Actual results could differ from those currently

projected. The Company does not assume the obligation to update any forward-looking statement.

Neither the TSX Venture Exchange nor its Regulation Services Provider accepts responsibility for the

adequacy or accuracy of this release.