Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

FPX.V ·

FPX Nickel Delivers PFS for Baptiste Nickel Project with After-Tax NPV of US$2.01 Billion and 18.6% IRR

Economic Studies

Suite 320 – 1155 West Pender Street

Vancouver, BC Canada V6E 2P4

Tel: 604.681.8600

e-mail: [email protected]

FPX Nickel Delivers PFS for Baptiste Nickel Project with After-Tax

NPV of US$2.01 Billion and 18.6% IRR

Vancouver, September 6, 2023 – FPX Nickel Corp. (TSX-V: FPX, OTCQB: FPOCF ) (“FPX” or the

“Company”) is pleased to announce results from the preliminary feasibility study (“ PFS”) for its 100%-

owned Baptiste Nickel Project (“Baptiste” or the “Project”) in central British Columbia, with an after-tax

NPV8% of $2.01 Billion and IRR of 18.6% at $8.75 /lb Ni. The PFS has been prepared in accordance with

National Instrument 43-101 (“NI 43-101”) and demonstrates the potential to develop a high-margin, long-

life, large-scale, and low-carbon mine with unparalleled flexibility to produce either a high-grade

concentrate (60% nickel) for direct feed into the stainless steel industry (the “Base Case”) or further refining

into battery -grade nickel sulphate, cobalt precipitate, and copper concentrate products for the battery

material supply chain (the “Refinery Option”). All amounts are in US Dollars unless otherwise indicated.

Highlights

• After-tax NPV8% of $2.01 Billion and IRR of 18.6% at $8.75 /lb Ni

• 29-year mine life producing an average 59,100 tonnes per year of nickel

• Phased development approach, with expansion following the 3.7-year after-tax payback period

• Life-of-mine (“LOM”) average C1 operating cost of $3.70/lb Ni ($8,150/t), assuming no byproduct

credits

• LOM average annual pre-tax free cash flow of $578 million during operating years

• Strategic product flexibility, with a Base Case high-grade nickel concentrate (60% nickel) for direct

feed to the stainless steel industry, plus a Refinery Option to produce battery-grade nickel sulphate

“The PFS firmly establishes Baptiste as a key strategic asset in the development of Canada’s critical

minerals supply chain ,” commented Martin Turenne , FP X’s President and Chief Executive Officer .

“Despite the inflationary pressures observed in the mining industry in recent years, the study has yielded

after-tax NPV and IRR superior to those observed in the 2020 preliminary economic assessment, reflecting

greater engineering maturity and incorporating the several optimizations identified by our class -leading

project team in regards to resource modelling, mine planning, process recovery , and site design. The

Baptiste project represents a significant opportunity for First Nations, the governments of British Columbia

and Canada, and FPX to work together to develop a project that creates substantial and sustainable benefits

while protecting the environment for future generations. We look forward to continued collaboration with

local Indigenous groups, and the provincial and federal governments to support the development of

Canada’s critical minerals ecosystem and to leverage health, economic and social benefits for local

communities.”

Webinar and Presentation

The Company’s management will host a live webinar on Wednesday, September 6 at 10:00 a.m. Eastern

(7:00 a.m. Pacific) to provide an overview of the P FS results and to answer questions from

participants. Participants can access the live webinar at the following link:

https://www.renmarkfinancial.com/events/renmark-virtual-non-deal-roadshow-tsx-v-fpx-otcqb-fpocf-

2023-09-06-100000

The results of the PFS are summarized in a corporate presentation available on the homepage of the

Company’s website at www.fpxnickel.com.

PFS Overview

The Base Case outlines an open -pit mining project in central British Columbia which will produce an

average of 59,100 tonnes of nickel per year in concentrate over a 29 -year mine life. The project will b e

developed in a phased approach, with an initial mill throughput rate of 108,000 tonnes per day (Phase 1),

followed by an expansion to 162,000 tonnes per day (Phase 2) funded from free cash flow after the initial

after-tax payback period of 3.7 years. The mining strip ratio averages 0.41 in the Phase 1, and 0.56 overall

for life-of-mine (excluding capitalized pre-stripping).

The Project will utilize a conventional processing flowsheet with SAG -mill based grinding followed by

magnetic separation, froth flotation, and a flotation tailings leach circuit , as previously described in the

Company’s June 27, 2023 news release. Overall Davis Tube Recoverable (“DTR”) nickel recovery is

estimated to average 88.7% for the life-of-mine, with 93% of the nickel produced contained in a high-grade

flotation concentrate (60% nickel) and the balance (7% of nickel produced) contained in a mixed hydroxide

precipitate (“MHP”) produced from a tailings leach circuit.

The Project will be supplied with low-carbon power from the BC Hydro provincial electricity transmission

grid, resulting in a n estimated Scope 1 and 2 carbon intensity of 2.4 t CO 2/t nickel produced, placing

Baptiste within the lowest decile of global nickel production. The Project will be accessed by a road system

consisting of upgrades and expansions to an existing forest service road (“FSR”) network. All mine tailings

and waste rock are proposed to be managed within a single integrated facility that will utilize open pit pre-

stripping material and waste rock for embankment construction.

Base Case economics are presented in Table 1, based on a $8.75/lb nickel price.

Table 1 – Base Case Economics

Criteria Units Base Case

Initial Capital Cost USD, millions 2,182

Operating Cost $/t milled 8.15

C1 Operating Cost1 USD /lb Ni 3.70

All-in Sustaining Cost (“AISC”)2 USD /lb Ni 4.17

After-

Tax

NPV8% USD, millions 2,010

IRR % 18.6

Payback Period years 3.7

Mine Life-to-Payback ratio 7.8

NPV-to-Initial Capex ratio 0.92

Annual Free Cash Flow, Pre-Tax3 USD, millions 578

Notes:

1. Exclusive of any byproduct credits.

2. Inclusive of operating cost, sustaining capital, expansion capital, closure capital, and royalties.

3. For production years.

The Refinery Option outlines an off-site refinery to upgrade a portion of nickel-in-concentrate to produce

40,000 tpa of battery-grade nickel sulphate for the electric vehicle battery supply chain, with the balance of

concentrate continuing to be directly supplied to the stainless steel industry. Along with battery-grade

nickel sulphate, this option also supports the valorization of cobalt and copper as refinery byproducts. The

Refinery Option presents incremental capital expenditure of $448 million with an incremental operating

cost of $1.02 per pound of nickel (C1 cost of $0.79/lb Ni, including credits for cobalt and copper

byproducts), resulting in total NPV8% of $2,127 million. Further discussion of the Refinery Option is

contained within the “Refinery Option” section near the end of this news release.

Mining & Mineral Reserves

The Baptiste deposit will be mined as a conventional large -scale truck and shovel operation with up to

60 Mt of material mined per year during Phase 1 and up to 120 Mt of material mined per year during

Phase 2. The mining operation will feature 250 mm blast-hole electric drills, 42 m3 electric excavators, and

300 t haul trucks working on nominal 10 m high benches. A flexible combination of dozers, graders, wheel

loaders, and excavators will form the core of the support equipment fleet.

The mineral resource estimate (effective November 14, 2022, see FPX news release) for the Project is based

on updated drilling from the 2021 season, informing the Baptiste deposit geological model. Taking

advantage of the resource shape and local topography, mining will commence at the south of the deposit

before moving north west and northeast, respectively. This approach provides two distinct advantages

during the initial operating years, including a higher average mill feed grade and a lower mining strip ratio.

This approach allows capital advantages through the deferment of mining equipment to sustaining costs, as

well as a lower mining operating cost during Phase 1.

A summary of the PFS mine plan is presented in Table 2, followed by a chart of tonnage moved and average

mill feed grade throughput for the envisioned mine life (Figure 1).

Table 2 – PFS Mine Plan Summary

Phase 1 Phase 2 Total

Operating Years 1 to 9 10 to 29 29 years

Head Grade, Average (% DTR Ni) 0.135 0.128 0.130

Mill Throughput (tpd) 108,000 162,000 -

Tonnes Milled, Total (Mt) 345 1,143 1,488

Tonnes Waste, Total (Mt)1 141 697 838

Strip Ratio (waste:ore)1 0.41 0.61 0.56

Notes:

1. Excludes capitalized pre-stripping.

Figure 1 – Material Moved and Mill Feed Grade by Year

The Probable Mineral Reserves for the project are estimated at 1,488 Mt at an average grade of 0.13%

DTR nickel (0.21% total nickel), resulting in 1,933 kt of contained DTR nickel metal (3,125 kt of total

nickel metal) over the 29-year mine life. Included in waste material for the PFS are 44 Mt of inferred

material at an average grade of 0.113% DTR nickel.

Table 3 – Baptiste Nickel Project Reserve Estimate

Category Tonnes

(Mt)

DTR

Nickel

(%)

Total

Nickel

(%)

Contained Metal

(kt DTR nickel)

Contained Metal

(kt total nickel)

Proven - - - - -

Probable 1,488 0.13 0.21 1,933 3,125

Proven &

Probable

1,488 0.13 0.21 1,933 3,125

Notes:

1. Mineral Reserves are reported effective September 6, 2023.

2. The Qualified Person for the estimate is Mr. Cristian Hernan Garcia Jimenez, P.Eng, an

independent consultant.

3. Mineral Reserves were developed in accordance with CIM Definition Standards (2014).

4. Mineral Reserves are reported using a fixed 0.06% DTR Ni cut-off grade, which represent

approximately US$9/t NSR value, which is above the economic cut-off grade of US$5.5/t.

5. The Mineral Reserves are supported by a mine plan, based on a pit design, guided by a Lerchs

Grossmann (LG) pit shell. Inputs include $8.75/lb Ni, $1.98/t mining opex, $3.72/t process opex,

$1.10 /t G&A opex, pit slopes varying from 42-44 degrees, and 85% process recovery

6. Life-of-mine strip ratio is 0.56 (W:O), excluding capitalized pre-stripping.

7. Ore and contained nickel tonnes are reported in metric units and grades are reported as

percentages.

8. All figures are rounded to reflect the relative accuracy of the estimate. Totals may not sum due to

rounding as required by reporting guidelines.

Metallurgy & Process Facilities

The PFS metallurgical testwork program involved multiple bench- and pilot-scale campaigns (see FPX’s

June 27, 2023 news release ). The overall processing strategy takes advantage of awaruite’s unique

characteristics in a simple flowsheet utilizing well -proven unit operations, as p resented in Figure 2. The

estimated life-of-mine DTR nickel recovery for the PFS is 88.7%, as presented in Table 4. Based on

average grade of 0.21% total nickel, this equates to a 55% total nickel recovery.

Figure 2 – Baptiste PFS Concentrator Flowsheet

Table 4 – Life of Mine DTR Nickel Recovery

Recovery DTR Nickel

Recovery (%)

By

Processing

Stage

Roughing Magnetic Separation 95.0

Cleaning Magnetic Separation 99.3

Recleaning Magnetic Separation 99.7

Flotation 87.4

Flotation Tailings Treatment 54.8

Overall To Awaruite Concentrate 82.2

To Mixed Hydroxide Precipitate 6.5

Combined To Both Nickel Products 88.7

The process plant will be developed in two phases, with the Phase 1 plant capable of processing 108,000

tpd of ore, and the Phase 2 expansion bringing total processing capacity to 162,000 tpd. Processing facilities

utilize conventional unit operations and configurations in comminution, magnetic separation, flotation, and

tailings leach.

Awaruite

Concentrate

60% Ni

Cleaning

Magnetic Separation

Roughing

Magnetic Separation

Primary Grinding

1st Regrind

Combined

Tailings

2nd Regrind

Recleaning

Magnetic Separation

Flotation

Mixed

Hydroxide

Precipitate

(MHP)

Flotation Tailings Leach &

Dissolved Nickel Recovery

In consider ation of ore grindability, low abrasivity, and low power cost, comminution will consist of

primary gyratory crushing, followed by semi-autogenous (“SAG”) mill and ball mill grinding. Based on

awaruite’s intense magnetic response, a coarse primary grind of 250 m allows approximately 84% of the

fresh plant feed to be diverted directly to final tailings in the primary magnetic separation stage. Followed

by two stages of regrind and cleaner magnetic separation, a further 12% of fresh plant feed is diverted to

final tailings, resulting in a “magnetics only” concentrate consisting of awaruite and magnetite. This results

in a flotation circuit which only needs to treat less than 5% of fresh plant feed.

Flotation utilizes well-defined conditions in conventional mechanical flotation cells. Roughing flotation

followed by four stages of cleaning flotation produces a high-grade nickel concentrate (60% nickel) which

is then dewatered, briquetted, and bagged for sale to market. Flotation tailings are subjected to mild

atmospheric tank leaching conditions to recover nickel not recovered in flotation (approximately 6.5% of

DTR nickel) . Leach solution is purified and nickel is subsequently precipitated to a MHP product

(containing 45% nickel) which is then dewatered and bagged for sale to market.

Other Facilities

The proposed tailings facility design considers management of tailings and mine waste in a single integrated

facility, utilizing open pit pre-stripping material and waste rock for dam construction. Deposition of waste

rock and tailings is considered within the open pit in the final years of operations. The tailings facility will

incorporate cross-valley dams and is situated in close proximity to the open pit, with gravity-flow of tailings

for the first 6 years of operations, followed by the installation of a tailings pumping system in Year 7.

The conceptual site water management plan includes management of site contact water in the tailings

facility with collection of runoff water downstream of all other Project infrastructure/disturbance s. PFS

water balance modelling indicates the site to be in an annual water deficit, requiring a modest allowance

for freshwater makeup during operations, including for potable water requirements.

The Project considers a full suite of on -site infrastructure and ancillaries. Both the construction and

operation phases will be supported by an on-site camp facility.

The Project will connect with BC Hydro’s low-carbon grid, with multiple options having been validated

through a formal BC Hydro study. The PFS considers a 230 kV connection to the Glenannan substation

located to the south of the Project, with a line length of approximately 155 km. The current FSR network

will suitably support the early stages of site construction. The current road network will be upgraded,

including minor expansions, at the end of the first year of construction resulting in reduced travel times to

site. No other off-site facilities are envisioned to be required for the Project.

Project Execution

The Gantt chart presented in Figure 3 summarizes the conceptual project development timeline. The critical

path runs through the environmental assessment (“ EA”) and permitting process, with an anticipated EA

decision in the first quarter of 2027. Approxi mately 9-12 months off the critical path are engineering

studies, with key events includ ing the feasibility study and front -end engineering and design (“ FEED”)

ahead of the final investment decision (“FID”). Following a positive EA decision and permitting the project

through 2027, the FID will approve the project to proceed with construction early works commencing in

early 2028, followed by full construction and subsequent production of first nickel in the fourth quarter of

2030.

Figure 3 – Project Development Schedule

Capital Cost Estimate

Initial capital costs have been estimated in alignment with AACE (Association for the Advancement of

Cost Engineering) Class 4 standards and have a stated accuracy of +/ - 25%. The PFS contributors

completed engineering, design, and costing inputs for their respective scope, with the overall esti mate

consolidated by Ausenco Engineering Canada Inc. Sustaining and expansion capital costs have been

estimated in alignment with AACE Class 5 standards, and closure capital costs have been estimated on an

order-of-magnitude basis.

The total initial capital cost for the Project is estimated to be $2,182 million and is expended in Years -3, -

2, and -1 ahead of start-up at the commencement of Year 1. Expansion capital cost is estimated to be $763

million and is expended ahead of expansion start-up at the commencement of Year 10. Sustaining capital

cost is estimated to be $1,281 million. Total closure capital cost is estimated to be $284 million. No salvage

value is considered due to the 29-year mine life.

Table 5 – Total Estimated Capital Costs

Capital

Cost Type

Category Total

(USD, millions)

Initial

Capital

Costs

Mining 325

Process Plant 730

Tailings Facility 115

On-Site Infrastructure 106

Off-Site Infrastructure 127

Indirect Costs 401

Owner’s Costs 106

Contingency 272

Total Initial Capital 2,182

Capital

Cost Type

Category Total

(USD, millions)

Sustaining

Capital

Costs

Mine Equipment 643

Tailings Facility 421

Indirect & Owner’s Costs 20

Contingency 97

Total Sustaining Capital 1,181

Total Expansion Capital Costs 763

Total Closure Capital Costs 284

Total Capital Costs (life-of-mine) 4,410

Operating Cost Estimate

Total operating costs are estimated to average $8.15 per tonne milled for life-of-mine, for an equivalent C1

cost of $3.70 /lb nickel produced (exclusive of any byproduct credits). Phase 1 operating costs of $7.88/t

milled are lower than the life -of-mine average, primarily due to the impact of the lower strip ratio in the

early operating years. Inclusive of royalties, sustaining capital, expansion capital, and closure capital, AISC

is estimated to average $4.17 /lb nickel produced for life-of-mine.

Mine operating costs are estimated to average $3.14 per tonne milled for life -of-mine, with lower costs

during Phase 1 ($2.59 per tonne m illed) due to the lower strip ratio. Processing costs are estimated to

average $3.63 per tonne milled for life-of-mine, with the Phase 2 costs slightly lower due to increased

throughput. G&A averages $1.09 per tonne milled for life-of-mine, benchmarking consistently with nearby

major operating mines. Concentrate transport averages $0.29 per tonne milled for life-of-mine, assuming

shipment of concentrates from Baptiste to east Asia.

The Project is subject to a 1% net smelter return (“ NSR”) which is payable on annual sales less

transportation costs to market.

Table 6 – Life-Of-Mine Operating Cost and AISC

Category Units Phase 1 Phase 2 LOM

Average

Mining $/t milled 2.59 3.31 3.14

Processing $/t milled 3.75 3.59 3.63

G&A $/t milled 1.23 1.05 1.09

Concentrate Transport $/t milled 0.31 0.29 0.29

Total Cash Costs $/t milled 7.88 8.24 8.15

C1 Operating Cost1 $/lb nickel produced 3.48 3.76 3.70

AISC2 $/lb nickel produced 3.97 4.23 4.17

Notes:

1. Exclusive of any byproduct credits.

2. Inclusive of operating cost, expansion capital, sustaining capital, royalties, and closure capital.

Economic Analysis

At an assumed nickel price of $8.75/lb and a CAD :USD exchange rate of 0.76, the Project generate s an

after-tax NPV8% of $2.01 billion, an after-tax IRR of 18.6%, and an after -tax payback of 3.7 years. See

Table 7 for further details regarding PFS economics and Table 8 for NPV 8% sensitivity to nickel price,

recovery, initial capital cost, and operating cost.