FPX Nickel Commences Preliminary Feasibility Study on the

Baptiste Nickel Project

Vancouver, January 17, 2023 – FPX Nickel Corp. (TSX-V: FPX, OTCQB: FPOCF) (“FPX” or the

“Company”) is pleased to announce the commencement of a preliminary feasibility study (“PFS”) for the

Baptiste Nickel Project (“Baptiste” or “the Project”) in central British Columbia. The PFS will mark the

culmination of the extensive de -risking and optimization program that has been underta ken since the

issuance of the 2020 preliminary economic assessment (“ 2020 PEA”). The PFS is expected to be

completed in September 2023.

Highlights

• The PFS will present a mature project basis, integrating FPX’s extensive de -risking and

optimization program undertaken since the 2020 PEA

• The PFS will present two strategic options, including:

o Base Case – production of a high-grade awaruite concentrate (50-65% Ni) for direct feed

to the stainless steel market , utilizing a simple and robust c oncentrator flowsheet that is

only possible due to Baptiste’s awaruite mineralization

o Option – further upgrading of the high-grade awaruite concentrate to produce battery-grade

nickel sulphate and cobalt -rich products for the electric vehicle battery suppl y chain ,

utilizing moderate leaching conditions and standard hydrometallurgical unit operations

• The PFS will be prepared by a team of industry-leading consultants, all of whom have meaningfully

contributed to the Project’s de-risking and optimization program since the 2020 PEA , thus

maintaining strong continuity in the ongoing development of Baptiste

“The PFS will mark the culmination of several years of robust project de-risking and optimization activities,

including resource definition drilling, engineering trade -off studies , baseline studies and pilot -scale

metallurgical test programs ,” commented Martin Turenne, the Company’s President and CEO. “Since

completion of the 2020 PEA, w e have consistently applied a major company -style mindset to project

development, and believe the PFS will confirm Baptiste as a peer-leading development-stage nickel project,

highlighting its potential for large -scale, low -cost and low -carbon nickel production spanning multiple

decades.”

The PFS will mark the culmination of an extensive de -risking and optimization program that has been

undertaken since the issuance of the 2020 PEA. With data collection and fundamental optionality largely

addressed during the post-PEA work program, FPX is confident that the PFS can be executed in an efficient

manner, and the team will be able to focus on maximizing the project’s technical and commercial maturity.

Key work elements since the 2020 PEA and their respective impact on the PFS base case are presented in

Table 1.

The PFS will present a base case of a mine and concentrator facility to produce a high -grade awaruite

concentrate (50-65% Ni) which can be directly fed to the stainless steel industry without intermediate

processing. As a strategic alternative, the PFS will present an option to further refine the high -grade

awaruite concentrate within a standalone, off-site refinery to produce both battery -grade nickel sulphate

and cobalt-rich products for the electric vehicle battery supply chain. This highly flexible approach is due

to Baptiste’s unique mineralogy and the resultant simple flowsheets for the produc tion of high -value

concentrate and sulphate products.

Table 1 – Baptiste Nickel Project: Summary of De-Risking & Optimization Program Since 2020

PEA

Work

Elements

Description Results

Geology &

Resource

Estimate

Completion of an in-fill drilling

program, targeting conversion of near-

surface, high-grade inferred resources to

the indicated category.

Drill results converted inferred resources

to indicated resources, as per Company

objective.

See FPX News Release dated March 14,

2022

Completion of an updated resource

estimate incorporating 2021’s in-fill

drilling, combined with a new geological

modelling approach and improved dike

model.

2022 mineral resource estimate achieved a

6% Davis Tube Recoverable (“DTR”) Ni

grade increase for indicated resources as

compared to 2020 mineral resource

estimate.

2022 mineral resource estimated included

first-time reporting of Total Ni, DTR Co,

and DTR Fe, providing the opportunity

for potential inclusion of secondary

products within the PFS economic basis.

See FPX News Release dated November

14, 2022

Metallurgy Phase 1 – Grindability and initial pilot-

scale testwork on both mine phase and

master composites

A mature dataset supporting PFS-level

design criteria.

See FPX News Release dated December

8, 2021

Phase 2 – Mineralogy on both mine

phase and master composites; and

flotation testwork on master composite

A mature dataset to support PFS-level

design criteria.

See FPX News Release dated July 27,

2022

Work

Elements

Description Results

Phase 3a – Larger-scale pilot testwork to

validate the PFS flowsheet

Results both validate the PFS flowsheet as

well as confirm tangible process benefits

in plant-scale processing.

See FPX News Release dated July 27,

2022 for initial results. Full results will

be released in late January 2023.

Phase 3b – Variabilty testwork on the

concentrator flowsheet and optimization

testwork on the hydrometallurgical

refinery flowsheet for production of

nickel sulphate

Testwork in progress to further support

design criteria.

Results forecast for release in April 2023.

Geotechnical Completion of phased geotechnical and

hydrogeological site investigation

programs in 2021 and 2022. Historic

open-pit geotechnical data analyzed to

provide more mature open-pit design

criteria.

Suitable site characterization information

now available for PFS design and

estimating purposes.

Engineering

Studies

Focusing on project elements having the

strongest influence on overall project

value, a series of de-risking and

optimization trade-off studies were

conducted.

Project value improved through:

• Change to SAG (semi-autogenous

grinding) mill comminution

• A phased development approach

with a smaller scale of initial

development as compared to the

2020 PEA approach

• A detailed alternatives assessment

of all available mine waste

management strategies identified

several viable alternatives, with

the lowest overall risk option to

be carried forward to the PFS

• Improved understanding of linear

facility options (road and power

corridors) and economics

• Evaluation of multiple mine

planning scenarios, improving the

metal production profile,

optimizing hauling distances and

overall footprint

See FPX News Release dated June 9,

2022

Work

Elements

Description Results

Environmental

& Cultural

Baseline

Studies

Execution of 2021 baseline readiness

reconnaisance program, following by

resumption of full environmental and

cultural baseline studies in 2022,

utilizing an Indigenous-led process

which involves signifcant contributions

from local stakeholders.

Collaborative approach with local

stakeholders has produced high quality

results on schedule.

Indigenous

Engagement

A comphrehensive Memorandum of

Agreement was signed with the Binche

Whut’en First Nation, which provides

support to FPX’s project development

activities.

See FPX News Release dated June 21,

2022

The PFS will fully incorporate de-risking and optimization results as summarized in Table 1. The PFS

will be conducted with the assistance of industry-leading service providers, and the collective team will

produce a fully integrated National Instrument 43-101 compliant technical report. Key service providers

have all meaningfully contributed to previous Project works, which reduces both technical, commercial,

and schedule risks. Key service providers contributing to the PFS are presented in Table 2.

Table 2 – Key Service Providers Contributing to the PFS

Participant Scope of Responsibility First Engaged on the Project

Ausenco Engineering

Canada Ltd.

Process, infrastructure, and overall PFS

integration

Q4-2021

Knight Piésold Ltd. Tailings, water management, and

geotechnical

Q2-2021

Onsite Engineering Ltd. Site access road Q4-2021

Carisbrooke Ltd. Off-site power system Q4-2021

Next Mine Consulting Geological modelling and resource

estimation

Q4-2021

Jeff Austin Metallurgical consultant and Qualified

Person

2018

Shas-Ti (an Ecofor

Consulting and Binche

Whut’en joint venture)

Environmental and cultural baseline

studies

Q1-2022

ERM Hydrology and meteorology Q1-2021

Lorax Geochemistry Q4-2021

Sasuchan Environmental Hydrogeology Q4-2022

In addition to the technical work conducted since the PEA, the Company has also focused efforts on

understanding the current project execution environment, including both cost escalation and schedule

considerations. FPX and its consultants have reviewed recently constructed major concentrator projects

as well as regional mining projects, and learnings from both efforts will bolster PFS execution planning

and cost estimating efforts. With the resultantly mature technical and commercial basis presented in the

PFS, the Company is confident that Baptiste’s large scale, long life, favourable jurisdiction, and low-

carbon intensity will support the continued development of the Project as a preferred feed source to either

or both of the stainless steel and electric vehicle battery supply chains.

Andrew Osterloh, P.Eng., FPX Nickel’s Qualified Person under NI 43-101, has reviewed and approved

the technical content of this news release.

About the Decar Nickel District

The Company’s Decar Nickel District claims cover 245 km 2 of the Mount Sidney Williams

ultramafic/ophiolite complex, 90 km northwest of Fort St. James in central British Columbia. The district

is a two-hour drive from Fort St. James on a high-speed logging road.

Decar hosts a greenfield discovery of nickel mineralization in the form of a naturally occurring nickel-iron

alloy called awaruite (Ni3Fe), which is amenable to bulk-tonnage, open-pit mining. Awaruite mineralization

has been identified in four target areas within this ophiolite complex, being the Baptiste Deposit, and the

B, Sid and Van targets, as confirmed by drilling , petrographic examination, electron probe analyses and

outcrop sampling on all four targets. Since 2010, approximately US $28 million has been spent o n the

exploration and development of Decar.

Of the four targets in the Decar Nickel District, the Baptiste Deposit, which was initially the most accessible

and had the largest known surface footprint, has been the focus of diamond drilling since 2010, with a total

of 99 holes and 33,700 m of drilling completed. The Sid target was tested with two holes in 2010 and the

B target had a single hole drilled in 2011; all three holes intersected nickel-iron alloy mineralization over

wide intervals with DTR nickel grades comparable to the Baptiste Deposit. In 2021, the Company executed

an inaugural drilling program at Van which returned results comparable with the strongest results at

Baptiste. In 2022, the Company executed a step-out drilling program at Van which demonstrated a sizeable

expansion of the mineralized zone identified in the 2021 program.

About FPX Nickel Corp.

FPX Nickel Corp. is focused on the exploration and developme nt of the Decar Nickel District, located in

central British Columbia, and other occurrences of the same unique style of naturally occurring nickel-iron

alloy mineralization known as awaruite. For more information, please view the Company’s website at

www.fpxnickel.com or contact Martin Turenne, President and CEO, at (604) 681 -8600 or

[email protected].

On behalf of FPX Nickel Corp.

"Martin Turenne"

Martin Turenne, President, CEO and Director

Forward-Looking Statements

Certain of the statements made and information contained herein is considered “forward -looking

information” within the meaning of applicable Canadian securities laws. These statements address future

events and conditions and so involve inherent risks and uncertainties, as disclosed in the Company's

periodic filings with Canadian securities regulators. Actual results could differ from those currently

projected. The Company does not assume the obligation to update any forward-looking statement.

Neither the TSX Venture Exchange nor its Regulation Services Provider accepts responsibility for the

adequacy or accuracy of this release.