Fox tungsten project updated to 486,000 tonnes of 0. 81 7 % W O 3 ( Indicated ) and 361,000 tonnes of 1.568% W O 3 (Inferred) January 2 6 th , 201

Corporate Updates

Happy Creek

’s

Fox tungsten

project

updated to

486,000

tonnes of 0.

81

7

% W

O

3

(

Indicated

)

and 361,000 tonnes of 1.568% W

O

3

(Inferred)

January 2

6

th

,

201

7

–

Vancouver, British Columbia. Happy Creek Minerals Ltd. (TSXV: HPY) (the

“Company

”

)

,

is pleased to

announce

an update

to its

mineral resource estimate completed in

accordance to NI 43

-

101

for

the

Ridley Creek

zone and a first

-

time resource for the

BN

zone

o

n

its 100% owned

Fox tungsten property

.

The Fox property is

located

75

km northeast of 100 Mile

House

in the

south

-

central

Cariboo, British Columbia

, Canada

.

The Fox property consists of a

recently discovered

, large scale, 10

km by 3 km

tungsten skarn

mineral system containing seven mineralized zones

at surface

.

All zones are open in extent.

The

current r

esource is for the Ridley Creek and BN

z

o

ne

s

.

The price used for the current estimate is

US$166.5/ MTU, or US$16.65/Kg WO

3

in concentrate.

The total Indicated

R

esources for the Ridley Creek

z

one amount to 486,000 tonnes grading

0.817% W

O

3

.

The

total Inferred

R

esource

is now

361,000 tonnes grading 1.568% WO

3

for the

Ridley Creek and BN

z

one

s

combined.

These grades are thought to be

comparable to the

Cantung

property

in the Northwest Territories, regarded as

among the

highest grade

mine

s

in the

western world

.

The selected cut

-

off for the material

amenable to open pit extraction is 0.2% W

O

3

.

For material ame

n

able to underground extraction

,

a

cut

-

off

of

0.55% W

O

3

was applied.

Table

1

:

Resource Estimate at

0.

2% and 0.55

% WO

3

Cut

-

off

ZONE

CLASSIFICATION

Cut

-

off

WO

3

(%)

Tonnes

(t)

WO

3

(%)

WO

3

MTU

WO

3

(kg)

Contained

Ridley Creek

Indicated in

-

pit

>0.2

329,000

0.729

250,000

2,500,000

Ridley Creek

Indicated

-

underground

>0.55

157,000

0.940

147,000

1,470,000

Ridley Creek zone

Indicated

total

486,000

0.817

397,000

3,970,000

Ridley Creek

Inferred in

-

pit

>0.2

14,000

0.630

9,000

90,000

Ridley Creek

Inferred

-

underground

>0.55

93,000

0.825

77,000

770,000

BN

Inferred

-

underground

>0.55

254,00

0

1.892

480,000

4,800,000

Ridley Creek and

BN zone

Inferred total

361,000

1.568

566,000

5,660,000

Note:

Cut

-

off determined by using a WO

3

price of

US$166.5

/MTU WO

3

in concentrate.

David

Blann, P.Eng., President

and

CEO, comments

: “

O

ne of o

ur stated goa

l

s

for 2016 was

to

expand the resource base

for the project

and we have increased

the total contained kg of WO

3

by two and a half times

while

significantly increas

ing

the overall resource grade.

The additional

drill

holes in Ridley Creek

provided

better geological contro

l. A tighter envelope on the high

-

grade

mineralization

with

a

re

-

co

nfigured

resource

pit

shell

ha

ve

captured

the

higher

grade

with a

low

strip ratio

of 3.3:1

.

Mineralization below the pit shell contains grade that is thought to be readily

accessible underground from the bottom of the pit.

We

also drilled

seven

more

succes

sful

holes

at the BN zone

that together with drill holes from 2012, has

returned

an

inferred resource grade

of 1.892% WO

3

.

The

Ridley Creek and BN

zones

remain open to further expansion along with

several others

that

have

only received limited exploration

work

to date

.

As a

new discovery in the

w

estern world, we are pleased with the results of the 2016 program

and we

plan to

continue

advancing the 100% owned Fox as a leading new tungsten project

.

”

A

summary

and geological interpretation

of exploration work

completed in 2016

along with

plans

for 201

7 are pending.

Table 2

a, b and c

shows the sensitivity of the model to changes in cut

-

off with the selected cut

-

off highlighted.

Table

2

a

:

Sensitivity to cut

-

off

grade

for the Ridley Creek zone within the resource constraining

pit

shell

Zone

Classification

WO

3

Cut

-

off

Tonnage

WO

3

WO

3

(%)

(T)

(%)

(MTU)

contained

Ridley Creek within the

resource constraining shell

Indicated

> 0.7

196,000

0.919

180,000

> 0.55

262,000

0.846

222,000

> 0.4

304,000

0.797

242,000

> 0.3

318,000

0.778

247,000

> 0.2

329,000

0.759

250,000

> 0.1

355,000

0.715

254,000

Inferred

> 0.7

7,000

0.764

5,000

>0.55

9,000

0.727

7,000

> 0.4

13,000

0.661

9,000

> 0.3

14,000

0.641

9,000

> 0.2

14,000

0.630

9,000

> 0.1

15,000

0.611

9,000

Table

2

b

:

Sensitivity to cut

-

off

grade

for the Ridley Creek zone below the resource constraining

shell

(Underground amenable)

Zone

Classification

WO

3

Cut

-

off

Tonnage

WO

3

WO

3

(%)

(T)

(%)

(MTU)

contained

Ridley Creek

b

elow the

resource constraining shell

(Underground)

Indicated

> 1.0

60,000

1.273

76,000

> 0.8

92,000

1.139

105,000

> 0.7

111,000

1.073

120,000

> 0.6

137,000

0.994

136,000

> 0.55

157,000

0.940

147,000

> 0.4

208,000

0.827

172,000

> 0.3

231,000

0.780

180,000

Inferred

> 1.0

15,000

1.189

18,000

> 0.8

43,000

0.988

43,000

> 0.7

65,000

0.910

59,000

> 0.6

85,000

0.849

72,000

> 0.55

93,000

0.825

77,000

> 0.4

131,000

0.725

95,000

> 0.3

148,000

0.681

101,000

Table

2

c

:

Sensitivity to cut

-

off

grade

for the BN Zone

Inferred resource amenable to underground

extraction.

Zone

Classification

WO

3

Cut

-

off

Tonnage

WO

3

WO

3

(%)

(T)

(%)

(MTU)

BN Zone

Inferred

> 1.0

191,000

2.252

431,000

> 0.8

222,000

2.067

458,000

> 0.7

237,000

1.985

469,000

> 0.6

248,000

1.924

477,000

> 0.55

254,000

1.892

480,000

> 0.4

272,000

1.798

489,000

> 0.3

291,000

1.702

495,000

The quantity and grade of reported Inferred resources in this estimation are conceptua

l in nature,

and there has been insufficient exploration to define these Inferred Resources as an Indicated or

Measured Resource. It is uncertain if further exploration will result in upgrading them to an

Indicated or Measured Resource category.

Mineral R

esources that are not Mineral Reserves do not have demonstrated economic viability.

Tungsten a

ssays are reported in percent WO

3

(tungsten trioxide), the compound for which

tungsten market prices are published. Quantities of WO

3

are traditionally reported in M

etric Ton

Units

,

which are equal to 10

kg of WO

3

.

For example, a

grade of 0.

8

% W

O

3

contains

8

kg of

W

O

3

/tonne.

A NI

43

-

101 t

echnical

r

eport for the

Fox

Tungsten Project mineral resource estimate will be filed

on S

EDAR

within 45 days.

NOTES ON THE

MINERAL RESOURCE ESTIMATE PARAMETERS AND METHOD

Mineral resources are estimated in conformance with the CIM Mineral Resource

definitions referred to in NI 43

-

101 Standards of Disclosure for Mineral Projects

.

This

mineral resource estimate is an update of the

March 15th

, 201

6

estimate conducted

by

Geoquest Consulting

Ltd.

and

AGP Mining Consultant

s Inc. covering the Ridley

Creek Zone (RC Zone). The estimate is also a first

-

time resource estimate for the B

N

z

one

.

The estimate was completed based on the concept of a small scale, open pit

and

underground room and pillar

operation

for the RC Zone and a small scale underground

room and pillar mining operation for the BN Zone

. No other zones on the Fox Tungsten

Proj

ect were evaluated.

All samples

prior to the 2016 drill campaign

were sent to the Agat Laboratory facility

in Vancouver, B.C., using a chain of custody, where they were prepared and analyzed

first with an aqua regia digest and ICP

-

ICP/MS finish to provide

a multi

-

element

analyses. For samples within and adjacent

to the

tungsten

-

mineralized domain, a

peroxide fusion digestion and ICP/OES finish was performed in triplicate and

averaged, providing results in percent W (tungsten). A portion of these that retur

ned

greater than 0.6% tungsten, were again repeated using XRF analyses.

For the 2016 drill campaign, the samples were sent to SGS Laboratory facility located

in Vancouver. Samples were crushed to 90% passing 2mm. A 250g split was

pulverized to 85% passing

75 microns. The samples were first analysed

with an aqua

regia digest and ICP

-

ICP/MS finish to provide a multi

-

element analyses

. For tungsten,

all samples were analysed using a

peroxide fusion digestion and ICP/

AES

finish

. Over

limits tungsten samples wer

e re

-

analysed with pyrosulphate fusion XRF.

All a

ssays received for tungsten (W) are converted to WO

3

by multiplying W by 1.261.

The quality control and quality assurance program remain the same as previous years.

For

every 10 samples submitted

, Happy Cree

k Mineral

inserted either a blank, a

certified reference standard, or a ¼ core duplicate sample in the sequence. In addition,

Agat

and SGS

Laboratory conducts its own quality assurance/quality control (QA/QC)

and reports these with every work order.

The

R

C Zone

model was interpolated with

60

core holes and 10 trenches completed

by Happy Creek from 2010 through to 201

6

, totalling

6,100

metres and containing

2

,

005

assays.

The BN Zone model is supported by 14 drill holes completed by Happy

Creek in

2012 and

2

016 totalling 1,916 meters of drilling and containing 447 assays.

The 3D wireframes developed to control the grade interpolation of the resource model

were based primarily on lithology, and included the construction of a mineralized

wireframe within the ca

lc

-

silicate/skarn lithology to control the extent of the

mineralization to reasonable distance from the drill data.

At the RC Zone the model

was enhance

d

by the addition of the high grade probabilistic model in order to reduce

the dilution of the higher

-

gr

ade material with the adjoining lower

-

grade material. This

methodology assumes a certain degree of selectivity which can be achieved via the

selection of small equipment, mining on 2.5

-

meter flitches and the use of

a

UV lamp.

Happy Creek preferentially s

amples the drill core in either 1 m or 2 m intervals. The

nominal composite length was 2.5

m. The composite intervals were created moving

downward from the collar of the holes toward the hole bottoms. Composites lengths

are automatically adjusted by the

software to leave no remnants at the lithological

boundaries.

For the treatment of outliers

on the RC Zone

, raw assays were capped at

7.0

% and

0.

45

% WO

3

in the CSSK (

calc

-

silicate

) and GRA (granite) domains

respectively,

in

combination with a search restriction applied on composite values greater than 2.

5

%

WO

3

. The procedure used allows the deposit to retain the high

-

grade assays while

limiting their influence during the interpolation to a maximum of 40

m x 30

m x 10

m

(l

ength x width x height).

At

a

0.1% WO

3

cutoff, the capping strategy removed 4.4%

of the metal in the Indicated and Inferred categories.

The BN Zone assays were

capped at 6% WO

3

. A high

-

grade search restriction was not necessary since the

coefficient of va

riation was less than 2.0 indicating the data does not show a high

variability.

Densities were determined from

613

representative rock samples

from the RC Zone

using industry standard methods. For the material within the mineralized zone, a

density of 2.8

5

5 g/cm

3

was applied to the calc

-

silicate lithology, and 2.

707

g/cm

3

applied to the granite lithology.

There was no density measurement for BN Zone

samples. The material was assigned the RC

-

Zone calc

-

silicate lithology density.

A (3D) geological and block m

odel was generated using Geovia Gems software. The

block mo

del matrix size of 5

m x 5

m x 2.5

m (width x length x height) was selected

with consultation with the engineering team from AGP, and was based on the size

deemed suitable for an open pit mining s

cenario

drilling in 5

-

meter bench and mining

in 2.5

-

meter flitches on the RC Zone. The model matrix is also suitable for a room and

pillar operation at the RC and BN Zone.

A

good

variogram was obtained using the 3D data within the

RC Zone

mineralized

enve

lope

. The direction and plunge represented by the variogram coincide with the

known interpreted plunge of the mineralization at the RC Zone. The nugget effect is

moderate, at

55

% of the sill value. At

96

% of the sill, the maximum range is a little

less

than 100

m. The definition of the variogram near the origin was

reasonable

. The

grade model was interpolated using ordinary kriging, and validated using inverse

distance squared and nearest neighbour models.

The BN zone had too few data points

to generat

e a reliable variogram therefore the grade model was interpolated using an

inverse distance squared and

a

nearest neighbour

check

models

.

The interpolation was carried out in multiple passes with increasing search ellipsoid

dimensions.

For both zones, the

c

lassification was based primarily on the pass

number, followed by an adjustment to the class model, based on diamond drilling

density (core area), the distance to the closest sample

. The

krige efficiency

was use

d

as a modifier on the RC Zone

.

No mining

plans have yet been completed for the deposit; however, from the geometry

of the deposit, it seems likely that open pit mining, followed by an underground

operation, may be considered for future extraction

of the RC Zone. The BN Zone will

likely be mined v

i

a

a room and pillar operation with ramp access.

Preliminary metallurgical test work to date is based on several surface bulk samples,

and indicates the scheelite (tungsten mineral) can be recovered using primarily gravity

methods and/or flotation to prod

uce potentially acceptable commercial

grades and

containing no deleterious elements that would

a

ffect its ability to be sold

. Potential by

-

products of zinc indium, bismuth, gold and silver have not been included in the

resource estimate at this stage, but

may be included in a future PEA, after more

detailed metallurgy is performed.

Under CIM definitions, Mineral Resources should have a reasonable prospect of

economic extraction. A tungsten price of US$166.52/MTU of WO

3

in concentrate was

used for the cut

-

o

ff estimation. In order to assess the Mineral Resources an in situ

resource cut

-

off grade of 0.20% WO

3

has been applied for potential open pit resources

and 0.55% WO

3

for potential underground material

To further assess reasonable prospects of economic e

xtraction, a Lerchs

-

Grossman

(LG)

optimized shell was generated to constrain the potential open pit material.

Parameters used to generate this shell included:

50° slopes for the pit shell

CDN$8/t mining, CDN$26/t milling, CDN$10/t G&A operating costs

75.8

% WO

3

recovery to a 68% WO

3

concentrate

US

$

166.52

/MTU WO

3

in concentrate

price

, based on a recently negotiated long term

price by a

n established

t

ungsten producer.

A

s a check, a

calculation using the three

year trailing average APT price arrived at a

similar price.

0.80 US$/CDN$ forex rate

economics applied to Indicated and Inferred materials.

The

LG

shell was

constrained from extending up a steep bank to the west into a high

strip area that would be more readily exploited by underground methods. A CDN$50/t

underground mining cost was applied assuming room

and pillar mining with good

ground conditions and dilu

tion control.

The quantity and grade of reported Inferred resources in this estimation are conceptual

in nature, and there has been insufficient exploration to define these Inferred

R

esources as an Indicated or Measured

R

esource. It is uncertain if furthe

r exploration

will result in upgrading them to an Indicated or Measured

R

esource category.

Mineral Resources that are not Mineral Reserves do not have demonstrated economic

viability.

Rounding of tonnes as required by reporting guidelines may result in a

pparent

differences between tonnes, grade and contained metal content.

Qualified Persons

David Blann, P.Eng., Director

of the Company

, is a Qualified Person as defined by National

Instrument 43

-

101 and is responsible for the overall preparation and approval of the technical

information disclosed in the news release.

Pierre Desautels, P.Geo. Principal Resource Geologist of AGP Mining C

onsultants Inc. Qualified

Person under NI 43

-

101 who is independent of the Company, has prepared and authorized the

release of the mineral resource estimates presented herein. Jay Melnyk, Eng., Principal Mining

Engineer of AGP Mining Consultants Inc. and Q

ualified Person under NI 43

-

101 guidelines has

reviewed the technical content of the News Release in relation to cut

-

off determination and the

resource constraining shell.

On behalf of the Board of Directors,

“David E Blann”

____________________

_______

David E Blann, P.Eng.

President, CEO

FOR FURTHER

INFORMATION,

PLEASE CONTACT:

David Blann, President, CEO

Corporate Office:

Phone: 604.662.8310

Email:

[email protected]

Website:

www.happycreekminerals.com

Corporate Communications:

Ron Birch: Phone: 250.

545

.

0383

Toll Free: 1

.

800

.

910

.

7711

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the

policies of the

TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

David Blann, P.Eng.

, Director,

is a Qualified Person as defined by National Instrument 43

-

101 and is responsible for

the preparation and approval of

the technical information disclosed in the news release.

This press release contains "forward

-

looking information" within the meaning of applicable securities laws, including

statements that address capital costs, recovery, grade, and timing of work or pl

ans at the Company’s mineral projects.

Forward

-

looking information may be, but not always, identified by the use of words such as "seek", "anticipate", "plan",

"planned", "continue", "expect", “thought to”, "project", "predict", "potential", "targeting", "

intends", "believe",

“opportunity”, “further” and others, or which describes a goal or action, event or result such as "may", "should", "could",

"would", "might" or "will" be undertaken, occur or achieved. Statements also include those that address future

mineral

production, reserve potential, potential size or scale of a mineralized zone, potential expansion of mineralization,

potential type(s) of mining, potential grades as well as to Happy creek’s ability to fund ongoing expenditure, or

assumptions about

future metal or mineral prices, currency exchange rates, metallurgical recoveries and grades,

favourable

operating conditions, access, political stability, obtaining or renewal of existing or required mineral titles,

licenses and permits, labour stability

, market conditions, availability of equipment, accuracy of any mineral resources,

anticipated costs and expenditures. Assumptions may be based on factors and events that are not within the control of

Happy creek and there is no assurance they will prove t

o be correct. Such forward

-

looking information involves known

and unknown risks, which may cause the actual results to materially differ, and/or any future results expressed or

implied by such forward

-

looking information. Additional information on risks an

d uncertainties can be found within

Financial Statements, Prospectus and other materials found on the Company’s SEDAR profile at

www.sedar.com

.

Although Happy creek has attempted to identify important factors that could

cause actual actions, events or results to

differ materially from those described in forward

-

looking information, there can be no assurance that such information

will prove to be accurate as actual results and future events could differ materially from th

ose anticipated in such

statements. Happy creek withholds any obligation to update or revise any forward

-

looking information, whether as a

result of new information, future events or otherwise, unless required by law.