Focus Graphite Highlighted in Prime Minister Carney's Historic Clean Energy and Critical Minerals Announcement; Completes Lac Knife Electrical Desktop Study Preferred Hydro-Quebec connection strategy advances federally supported infrastructure planning and could reduce
Focus Graphite Highlighted in Prime Minister
Carney's Historic Clean Energy and Critical
Minerals Announcement; Completes Lac Knife
Electrical Desktop Study
Preferred Hydro-Quebec connection strategy advances
federally supported infrastructure planning and could reduce
future Lac Knife capex requirements
Ottawa, Ontario--(Newsfile Corp. - August 21, 2026) -
Focus Graphite Inc. (TSXV: FMS) (OTCQB:
FCSMF) (FSE: FKC0)
("
Focus
" or the "
Company
"), a Canadian developer of high-grade flake
graphite deposits and advanced graphite materials for battery, defence and industrial applications, is
pleased to highlight the Government of Canada's recognition of infrastructure supporting the Company's
100%-owned Lac Knife Graphite Project ("
Lac Knife
" or the "
Project
") in Prime Minister Mark Carney's
August 17, 2026 announcement advancing clean-energy and critical-minerals infrastructure across the
Labrador Trough
1
.
The Government of Canada identified Focus Graphite's Lac Knife infrastructure initiative among four
strategic pre-development projects supported and funded through Natural Resources Canada's
("
NRCan
") First and Last Mile Fund ("
FLMF
"), describing the planned road and electrical connection as
supporting the development of battery and energy-storage technologies required by Canada and its
allies.
The recognition follows Focus's June 3, 2026 announcement that it secured C$1,378,700 in non-
repayable federal funding to advance engineering, environmental, permitting, Indigenous engagement
and feasibility activities for Lac Knife's road and electrical infrastructure
2
. The funding represents
approximately 50% of eligible project costs.
Focus has now completed an independent electrical infrastructure desktop study (the "
Study
") prepared
by Norda Stelo Inc. ("
Norda Stelo
"), identifying a preferred pathway for connecting Lac Knife to
Quebec's hydroelectric grid.
"Lac Knife's recognition within the Prime Minister's announcement reinforces the strategic importance of
bringing Canadian critical mineral projects and their enabling infrastructure forward," said Dean Hanisch,
Chief Executive Officer of Focus Graphite. "We are already turning that support into tangible progress.
With both our access-road and electrical desktop studies now complete, we are identifying meaningful
infrastructure efficiencies relative to the 2023 Feasibility Study. The preferred electrical strategy provides
a pathway to significantly reduce power-related capital requirements while connecting Lac Knife to
Quebec's clean hydroelectric grid. We are grateful for Canada's continued support."
"Infrastructure and access to power remain key constraints for mine development, with direct
implications for capital, execution and timelines," said Jason Latkowcer, Vice President, Corporate
Development of Focus Graphite. "Canada's investment in energy and critical-mineral infrastructure is
helping define a clearer development pathway for Lac Knife. Advancing that work reduces development
uncertainty and provides a stronger basis for future capital allocation and evaluation by potential
strategic, financing and other investment partners."
"Critical minerals are essential to Canada's economic prosperity, security, and sustainability, and we are
proud to advance Canadian mineral supply chains as a part of the historic Churchill Falls and Labrador
Trough announcement," said the Honourable Tim Hodgson, Minister of Energy and Natural Resources.
"As a part of this nation-building initiative, through our First and Last Mile Fund, Canada is advancing the
infrastructure we need to unlock projects like Lac Knife and strengthen Canada's critical minerals value
chain. This is how your federal government is working with industry to build a stronger, more competitive
critical minerals sector; create opportunities for Indigenous and local communities; and deliver minerals
Canada and our allies need for clean technologies, advanced manufacturing and defence applications."
Preferred Hydro-Quebec Connection Strategy
Norda Stelo evaluated seven potential electrical supply scenarios against technical feasibility,
constructability, cost, environmental considerations and execution requirements. The Study identified a
direct connection to Hydro-Quebec's three-phase, 34.5-kV distribution grid as the preferred solution,
with the connection extending across public lands to the Lac Knife property.
The preferred configuration would require approximately 30.7 kilometres of electrical infrastructure,
consisting of the upgrade of approximately 3.17 kilometres of existing single-phase line to three-phase
service and the construction of approximately 27.5 kilometres of new three-phase distribution line
extending to the Project. The new distribution line would largely follow established corridors, including the
Hydro-Quebec transmission corridor, Highway 389 and the Project's planned access-road corridor.
Under this approach, Hydro-Quebec would construct the principal distribution infrastructure on behalf of
Focus, reducing the Company's direct construction and coordination requirements while also placing
responsibility for associated environmental permitting and long-term maintenance of the distribution line
with Hydro-Quebec.
Potential Capital Savings Relative to 2023 Feasibility Study
The preferred strategy also creates an opportunity to significantly reduce the power-related capital
requirements contemplated in Lac Knife's 2023 Feasibility Study Update ("
FSU
").
The 2023 FSU included C$19.9 million in initial capital for Power and Communications infrastructure,
within total estimated pre-production capital of approximately C$236.9 million. The Norda Stelo Study
identified several factors that could reduce these requirements. These include reducing the anticipated
length of new power-line construction from approximately 50 kilometres to approximately 27.5
kilometres, eliminating the need for additional infrastructure at Hydro-Quebec's Normand substation, and
identifying that certain power-line construction costs contemplated in the FSU may have been
overestimated. The Study also identified the potential for Hydro-Quebec to construct the distribution line
at its standard per-kilometre cost.
Based on the assumptions evaluated in the Norda Stelo Study, the preferred strategy is estimated to
have the potential to reduce Focus's direct power-related capital requirements by more than 50%
relative to the power infrastructure assumptions contained in the 2023 FSU. This estimate is preliminary,
is based on a desktop-level assessment and should not be interpreted as an updated capital cost
estimate for the Project. Any actual reduction will depend on Hydro-Quebec's final connection
requirements and cost responsibilities, detailed engineering and the scope of remaining on-site
electrical infrastructure. There can be no assurance that the estimated reduction will be realized.
Next Steps
Focus intends to continue working with Hydro-Quebec and its engineering consultants to advance the
preferred connection strategy, confirm technical requirements and define future cost responsibilities.
The electrical work is being advanced alongside the Company's access-road planning, environmental
permitting, engineering and Indigenous engagement programs under the federally supported FLMF
initiative.
Natural graphite is designated as a critical mineral in Canada and is used across battery, energy-
storage, defence and advanced-material applications. Focus continues to advance Lac Knife through
engineering, environmental, permitting and Indigenous engagement activities.
Figure 1: Proposed Access Road, Lac Knife (Norda Stelo / IOS Geosciences, 2026)
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1963/310686_0b06cfb494dcf9cf_001full.jpg
Qualified Person
The technical content disclosed in this news release was reviewed and approved by Rejean Girard,
P.Geo (Qc), President of IOS Geosciences Inc., a consultant to the Company, and a qualified person as
defined under National Instrument NI 43-101.
About Focus Graphite Advanced Materials Inc.
Focus Graphite is building an integrated graphite platform to supply the industries shaping the future.
Through the development of world-class graphite resources, advanced processing technologies and
higher-value advanced materials, the Company is positioning itself to support battery, defence,
advanced manufacturing and other strategic industries across North America and allied markets.
The platform is anchored by the Company's two 100%-owned graphite assets in Quebec. Lac Knife is
one of North America's highest-grade feasibility-stage graphite deposits, while Lac Tetepisca is one of
the largest identified graphite resources globally. Together with strategic technology partnerships and
government-supported innovation initiatives, these assets provide the foundation for a secure, scalable
and increasingly integrated graphite supply chain.
For more information on Focus Graphite Inc. please visit
http://www.focusgraphite.com
LinkedIn:
https://www.linkedin.com/company/focus-graphite/
Facebook:
https://www.facebook.com/focusgraphite
X:
https://x.com/focusgraphite
Investors Contact:
Dean Hanisch
CEO, Focus Graphite Inc.
+1 (613) 612-6060
Jason Latkowcer
VP Corporate Development
Cautionary Note Regarding Forward-Looking Statements
Certain statements contained in this press release constitute forward-looking information. These
statements relate to future events or future performance. The use of any of the words "could," "intend,"
"expect," "believe," "will," "projected," "estimated," and similar expressions, as well as statements
relating to matters that are not historical facts, are intended to identify forward-looking information and
are based on the Company's current beliefs or assumptions as to the outcome and timing of such
future events.
In particular, this press release contains forward-looking information regarding, among other things,
the preferred electrical connection strategy identified for the Lac Knife Graphite Project; the potential
connection of Lac Knife to Hydro-Quebec's three-phase, 34.5-kV distribution grid; the anticipated
configuration, routing and length of the proposed electrical infrastructure, including the upgrade of
existing distribution infrastructure and construction of new three-phase distribution line; the potential
construction, permitting, ownership, operation and long-term maintenance of the principal distribution
infrastructure by Hydro-Quebec; the potential reduction in Focus's direct construction, coordination,
permitting and maintenance responsibilities under the preferred strategy; the potential for the
preferred electrical strategy to reduce Focus's direct power-related capital requirements by more than
50% relative to the power infrastructure assumptions contained in the 2023 Feasibility Study Update;
the assumptions underlying that preliminary estimate and the extent to which any anticipated
reduction may ultimately be realized; the nature and extent of Hydro-Quebec's final connection
requirements, cost responsibilities and applicable construction costs; the results of future detailed
engineering and the scope and cost of remaining on-site electrical infrastructure; the potential
elimination of infrastructure previously contemplated at Hydro-Quebec's Normand substation; the
continued advancement of the preferred electrical connection strategy and related discussions and
engineering work with Hydro-Quebec and the Company's engineering consultants; the continued
advancement of road and electrical infrastructure planning, environmental and permitting activities,
engineering and Indigenous engagement under Natural Resources Canada's First and Last Mile
Fund; the continued availability of federal funding and the Company's ability to satisfy applicable
funding conditions and project requirements; the potential benefits of government-supported
infrastructure initiatives to the advancement of Lac Knife; the potential for increasingly defined
infrastructure planning to reduce development uncertainty and support future capital allocation,
financing and evaluation by potential strategic or other investment partners; the continued
advancement and future development of the Lac Knife Graphite Project; and the timing, scope, cost
and results of future engineering, permitting, infrastructure development and other project-
development activities.
Forward-looking statements are subject to known and unknown risks, uncertainties, and other factors
that may cause actual results, performance, or achievements to differ materially from those expressed
or implied by such statements. These risks and uncertainties include, but are not limited to, risks
related to market conditions, regulatory approvals, changes in economic conditions, the ability to
raise sufficient funds on acceptable terms or at all, operational risks associated with mineral
exploration and development, and other risks detailed from time to time in the Company's public
disclosure documents available under its profile on SEDAR+.
The forward-looking information contained in this release is made as of the date hereof, and the
Company is not obligated to update or revise any forward-looking information, whether as a result of
new information, future events, or otherwise, except as required by applicable securities laws. Because
of the risks, uncertainties, and assumptions contained herein, investors should not place undue
reliance on forward-looking information.
Neither TSX Venture Exchange nor its Regulation Services accepts responsibility for the adequacy or
accuracy of this release.
1
https://www.pm.gc.ca/en/news/news-releases/2026/08/17/prime-minister-carney-announces-largest-
clean-energy-investment-north
2
https://focusgraphite.com/focus-graphite-secures-up-to-c1-38-million-under-natural-resource-canadas-