Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

FM.TO ·

FIRST QUANTUM MINERALS REPORTS FIRST QUARTER 2023 RESULTS (In United States dollars, except where noted otherwise)

Financials

NEWS RELEASE

23-16

April 25, 2023

www.first-quantum.com

FIRST QUANTUM MINERALS REPORTS FIRST QUARTER 2023 RESULTS

(In United States dollars, except where noted otherwise)

Toronto, Ontario ( April 25, 2023 ) - First Quantum Minerals Ltd. (“First Quantum” or “the Company”) (TSX: FM)

today reports results for the three months ended March 31, 2023 (“Q1 2023” or the "first quarter") of net earnings

attributable to shareholders of the Company of $75 million ($0.11 earnings per share) and adjusted earnings1 of

$76 million ($0.11 adjusted earnings per share2).

“The first quarter was difficult with production impacted at our three largest operations. At Cobre Panamá,

production was interrupted by a temporary suspension of exports but returned to full production rates once the

suspension was lifted. Our Zambian operations experienced a seasonal impact, however, the rainy season is

nearing an end. We are focused on improving operational performance and expect production to recover over the

course of the year and, as such, we remain committed to our guidance for 2023,” commented Tristan Pascall,

Chief Executive Officer. “The first quarter also had important milestones, including a refreshed contract with the

Government of Panamá and a new partnership with Rio Tinto to progress the La Granja project in northern Peru.

The Company also successfully executed on two of our brownfield projects. Commissioning of the CP100

Expansion was completed ahead of schedule and remains on track to achieve 100 million tonnes of throughput per

annum by the end of this year and we introduced first ore through the Enterprise nickel plant. Both of these

projects will increase our copper and nickel production, two metals that are critical to the global transition to cleaner

energy.”

Q1 2023 SUMMARY

In Q1 2023, First Quantum reported gross profit of $280 million, EBITDA1 of $518 million, net earnings attributable

to shareholders of $0.11 per share, and adjusted earnings of $0.11 per share2. Relative to the fourth quarter of last

year (“ Q4 2022 ”), first quarter financial results were impacted by lower sales volumes as a result of lower

production that was partially mitigated by lower input costs and stronger realized copper and gold prices.

Total copper production for the first quarter was 138,753 tonnes, a 33% decrease from Q4 2022. The quarter-over-

quarter decrease in production was attributable to a 15-day temporary suspension of production at Cobre Panamá

and the rainy season in Zambia, with Sentinel receiving its highest rainfall in 25 years. Kansanshi continued to

experience lower feed grades across all three circuits.

Copper C1 cash cost 2 of $2.24 per lb for Q1 2023 was $0.38 per lb higher than Q4 2022. While market rates for

fuel and freight were, on average, lower in the first quarter of 2023, these benefits were more than offset by lower

production levels.

2023 guidance on production, C1 cash costs 2, all-in sustaining cost (“AISC”) 2 and capital expenditures that was

previously disclosed on January 16, 2023 remains unchanged. For 2023, copper production is forecast to be

770,000 to 840,000 tonnes. Production is expected to recover for each of the next three quarters, particularly in the

second half of the year. Copper C1 cash costs 1 are guided to be $1.65 to $1.85 per lb. Capital cost guidance for

2023 is $1,600 million.

1 EBITDA and adjusted earnings are non-GAAP financial measures. These measures do not have a standardized meaning prescribed by IFRS and might not be comparable to

similar financial measures disclosed by other issuers. See “Regulatory Disclosures”.

2 Adjusted earnings per share, copper C1 cash cost (copper C1), and all-in sustaining costs (AISC) are non-GAAP ratios which do not have a standardized meaning prescribed

by IFRS and might not be comparable to similar financial measures disclosed by other issuers. See “Regulatory Disclosures”.

Q1 2023 OPERATIONAL HIGHLIGHTS

Total copper production for Q1 2023 was 138,753 tonnes, down from the 206,007 tonnes reported in Q4 2022 as

each of the Company's three largest operations had negative production impacts during the period. Copper sales

volumes in Q1 2023 totalled 150,287 tonnes, 11,534 tonnes higher than production.

• Cobre Panamá produced 65,427 tonnes of copper in Q1 2023, a decrease of 24,225 tonnes from the

previous quarter as production was interrupted on February 23, 2023 for 15 days as a result of export

restrictions imposed by the Maritime Port Authority ("AMP"). Following a resolution issued by the AMP,

concentrate loading recommenced on March 9, 2023 with a record number of vessels loaded in March.

Throughput returned to full capacity on March 10, 2023, two days after the restart of operations. Copper

C1 cash cost1 of $1.65 per lb was $0.02 per lb higher than the previous quarter mainly attributable to lower

production levels. The commissioning of the CP100 Expansion was completed in the first quarter and the

annualized throughput rate of 100 million tonnes per annum ("Mtpa") remains on schedule for the end of

the year. 2023 Production guidance for Cobre Panamá remains unchanged at 350,000 to 380,000 tonnes

of copper and 140,000 to 160,000 ounces of gold. For the full year 2023, grades and recoveries are

expected to be broadly consistent with 2022 regardless of the increased processing throughput, with some

fluctuation from quarter to quarter. Construction of the molybdenum plant is progressing well, with

completion of construction and commencement of commissioning expected by the end of 2023 with first

production expected in Q1 2024.

• Kansanshi’s copper production of 28,683 tonnes in Q1 2023 was 6,119 tonnes lower than the previous

quarter due to the seasonal impact of the rainy season and lower feed grades across all three circuits,

particularly from the M11 area at lower elevations in the main pit. Variability of grades in ore stockpiles and

lower grades from narrow-veined regions were the main drivers behind the lower grades. Copper C1 cash

cost1 of $2.88 per lb was $0.07 higher than Q4 2022 mainly due to lower production volumes despite an

improvement in input costs. Production in 2023 is expected to be 130,000 to 150,000 tonnes of copper and

95,000 to 105,000 ounces of gold. Mining fleet deployment changes over the past six months have

enabled the operation to open up mining areas, placing less reliance on variable grade ore stockpiles, as

well as mining cutbacks M15 and M17 at upper elevations in the main pit with historically higher grades,

which will benefit production through the rest of 2023. An extensive drilling campaign is ongoing in areas

associated with vein mineralization prior to mining.

• Sentinel reported copper production of 36,232 tonnes in Q1 2023, 37,177 tonnes lower than the previous

quarter due to the intense rainy season, resulting in the accumulation of water in the Stage 1 pit. Saturated

ground conditions significantly impacted mining rates due to poor road conditions and water in the pit

prevented access to working faces, particularly in the lower benches of Stage 1. Copper C1 cash cost 1 of

$2.70 per lb was $1.15 per lb higher than the preceding quarter reflecting the lower production volumes.

Despite the challenges encountered during the first quarter, copper production for 2023 remains

unchanged at 260,000 to 280,000 tonnes as higher feed grades are expected in the second half of the

year, with grades showing improvement already in April. The current focus on deploying additional

dewatering capacity in Stage 1 to regain access to the high-grade ore is already yielding results early in

the second quarter. The mine plan has been rescheduled, even if total volumes remain substantively the

same and higher grade zones will be dispatched across the remaining three quarters of the year. This is to

be complemented by a change in location of the in-pit ramps to liberate high-grade ore by mining the

saddle zones between Stage 1 and Stage 2. There will also be a redistribution of loading equipment to

better suit working areas and truck fleet capacity is planned to increase in the second quarter with the

commissioning of an additional Liebherr T284, followed by two more in the second half of the year.

• Ravensthorpe payable nickel production of 4,344 tonnes was 106 tonnes lower than the fourth quarter. A

major two week High Pressure Acid Leach train shutdown was performed during February. The shutdown

ran according to schedule with all works being completed on time. Nickel C1 cash cost 1 was $9.34 per lb

relatively unchanged from the preceding quarter. Production guidance for 2023 remains at 23,000 to

28,000 contained tonnes of nickel.

First Quantum Minerals Ltd. 23-16

Page 2 of 12

1 C1 cash costs (C1) is a non-GAAP ratio which does not have a standardized meaning prescribed by IFRS and might not be comparable to similar financial measures disclosed

by other issuers. See “Regulatory Disclosures”.

COBRE PANAMÁ UPDATE

During the quarter, the Company continued to engage in good faith discussions with the Government of Panamá

("GOP") and, on March 8, 2023, the Company and the GOP issued a press release announcing that an agreement

was reached on the terms and conditions of the draft of a concession contract (the “Refreshed Concession

Contract”). The Refreshed Contract will have an initial 20-year term with a 20-year extension option and additional

extensions for life of mine. The Refreshed Concession Contract is expected to be presented before the National

Assembly of Panamá in the legislative term that commences on July 1, 2023, after having gone through a public

consultation process and receipt of all required prior governmental approvals.

Once the agreement is signed and passed into law, payments to cover taxes and royalties up to the year-end 2022

of approximately $395 million are expected to be made within 30 days of the Refreshed Concession Contract being

enacted into law. In addition, past due amounts payable for 2023 corporate tax instalments, withholding taxes and

quarterly royalty payments will also be due 30 days after being enacted, without penalty or interest. It is intended

that the charge relating to taxes and royalties up to the year-end 2022 be excluded from 2023 adjusted earnings.

The expected taxes and royalties to the GOP relating to 2023 is $375 million. Any non-profit based top-up tax to

meet the proposed minimum contribution is expected to be recognized within operating profit and impact AISC 1.

The AISC1 guidance range is unchanged and is able to accommodate the expected impact of between $0.00 per lb

to $0.05 per lb. At current consensus pricing, the adjusted effective tax rate for the Group for the full year 2023 is

expected to be between 35% and 40%.

KANSANSHI – CONVERSION OF ZCCM DIVIDEND RIGHTS TO ROYALTY RIGHTS

During the fourth quarter of 2022, an agreement was entered into between KMP and ZCCM-IH to convert ZCCM-

IH's dividend rights in KMP into royalty rights. The transaction was completed on April 4, 2023.

LA GRANJA

On March 30, 2023, the Company entered into an agreement with Rio Tinto to progress the next phase of the La

Granja copper project in northern Peru. La Granja is one of the largest undeveloped copper resources in the world

with a published Inferred mineral resource of 4.32 billion tonnes at 0.51% copper, and has potential for substantial

expansion.

Under the terms of the agreement, the Company will acquire a 55% interest in La Granja for a consideration of

$105 million and will become the operator of the project. The Company will then be responsible for the next $546

million of initial funding. Part of the initial funding will be used to complete a feasibility study, following which the

remaining majority of the initial funding is expected to be spent on construction of the project following a positive

investment decision. The transaction is expected to close before the end of the third quarter.

Work over the initial years is planned to continue to progress community engagement and the feasibility study. The

feasibility study will focus on developing an updated geological resource and reserve model, which will require

additional infill drilling to upgrade Inferred resources to Measured and Indicated categories. Additional metallurgical

studies to establish optimal processing configurations are expected to be carried out in parallel, together with a

high-level project layout and configuration of associated infrastructure requirements and logistical routes.

Further to the agreement on La Granja, First Quantum and Rio Tinto have also entered into a memorandum of

understanding to support co-operation in relation to base metals development opportunities and the sharing of

technology and know-how on certain mining methods, such as the application of trolley-assist and autonomous

mining fleets.

First Quantum Minerals Ltd. 23-16

Page 3 of 12

1 All-in sustaining costs (AISC) is a non-GAAP ratio which does not have a standardized meaning prescribed by IFRS and might not be comparable to similar financial measures

disclosed by other issuers. See “Regulatory Disclosures”.

BROWNFIELD PROJECTS

Construction for the CP100 Expansion project was completed seven weeks ahead of schedule and commissioning

was completed in the first quarter. With these facilities now in daily operation, focus has moved onto ramping up

these facilities over the course of the year to achieve a throughput rate of 100 Mtpa by the end of 2023. Significant

progress has been made on the pre-strip work for the Colina pit and earthworks for the associated overland

conveyor and in-pit crushing facility. The first crusher at Colina is expected to be commissioned in 2024.

At the S3 Expansion, detail design is progressing well. Long-lead mining fleet and long-lead process plant

equipment have been ordered with deliveries commencing in the second half of 2023. Overall project procurement

is approximately 25% committed as at the end of the quarter. The majority of the capital spend on the S3

Expansion is expected in late-2023 and 2024.

First ore through the Enterprise nickel plant was achieved on schedule in February 2023. Plant refurbishment,

completion and commissioning activities were completed on schedule. First production of nickel is expected in the

second quarter of 2023 and ramp up to commercial production will continue over the course of 2023, with ramp up

to full plant throughput in 2024. 2023 production guidance for Enterprise is 5,000 to 10,000 contained tonnes of

nickel.

At the Las Cruces Underground Project, the water concession license was granted in March 2023 and all permits

are in place for project approval. The technical and study work on the polymetallic refinery project are expected to

continue with all permits required to carry out the project now granted. The Las Cruces Underground Project is

awaiting Board approval, which is not expected before the end of 2023 and will take into consideration prevailing

economic conditions and the Company's debt reduction objectives.

FINANCIAL HIGHLIGHTS

• Gross profit of $280 million and EBITDA 1 of $518 million for the first quarter were 22% and 20% lower,

respectively, than the fourth quarter of last year due to lower metal sales volumes.

• Cash flows from operating activities of $299 million ($0.43 per share 2) for the quarter were $62 million

higher than the fourth quarter of last year due mainly to working capital movements related to trade and

other receivables.

• Net debt 1 increased by $88 million during the quarter, taking the net debt 1 balance to $5,780 million as at

March 31, 2023. As at March 31, 2023, total debt was $6,878 million (December 31, 2022, total debt was

$7,380 million). The increase in net debt 1 and total debt1 was attributable to timing of working capital cash

flow and continued investment in the business. The Company continues to target a further $1 billion

reduction in debt in the medium term.

• In the first quarter of 2023, the Company redeemed at par an aggregate principal amount of $850 million of

the senior unsecured notes due 2024. $450 million was redeemed on February 25, 2023 and the

remaining $400 million was redeemed on March 28, 2023. Following the redemptions, there are no

outstanding senior unsecured notes due in 2024.

First Quantum Minerals Ltd. 23-16

Page 4 of 12

1 EBITDA is a non-GAAP financial measures and net debt is a supplementary financial measure. These measures do not have a standardized meaning prescribed by IFRS and

might not be comparable to similar financial measures disclosed by other issuers. See “Regulatory Disclosures”

2 Cash flows from operating activities per share, copper C1 cash cost (copper C1), and copper all-in sustaining cost (copper AISC) are non-GAAP ratios which do not have a

standardized meaning prescribed by IFRS and might not be comparable to similar financial measures disclosed by other issuers. See “Regulatory Disclosures”.

ENVIRONMENT, SOCIAL AND GOVERNANCE (“ESG”)

Reporting - The Company will publish its primary sustainability report, the 2022 ESG Report, in May 2023. The

latest reports can be found in the ESG Analyst Centre on the Company’s website: https://www.first-quantum.com/

English/sustainability/esg-analyst-centre/default.aspx. These include the TCFD-aligned Climate Change Reports,

ESG Reports, Tax Transparency and Contributions to Government Reports, as well as Company’s sustainability

policies.

Innovation driving sustainability - On March 1, 2023, Hitachi Construction Machinery Co. Ltd (“Hitachi”) and the

Company announced a technology partnership for the development of Hitachi Construction Machinery ’s first

battery mining trucks at the Kansanshi mine. As First Quantum seeks to lower the greenhouse gas (“GHG”)

intensity of copper produced, this initiative represents an important milestone towards future commercialization of

battery technology to further decarbonize mining operations, consistent with the Company’s 2025 30% and 2030

50% GHG emissions reduction targets. It is expected that these battery dump trucks will be supplied to Kansanshi

by December 2023 for feasibility trials as part of the commissioning of the Kansanshi S3 Expansion.

Health & Safety - The health and safety of the Company’s employees and contractors is a top priority and the

Company is focused on the continuous strengthening and improvement of the safety culture at all of its operations.

Tragically, on February 1, 2023, there was a fatal road traffic accident in the Sentinel pit involving a dump truck and

a light vehicle. The site emergency response team attended immediately and the relevant local authorities were

notified. This tragic incident is subject to internal and external investigation, as well as a Board review, and the

Company is committed to improve practices from this incident.

First Quantum Minerals Ltd. 23-16

Page 5 of 12

CONSOLIDATED OPERATING HIGHLIGHTS

QUARTERLY

Q1 2023 Q4 2022 Q1 2022

Copper production (tonnes)1 138,753 206,007 182,210

Cobre Panamá 65,427 89,652 78,337

Kansanshi 28,683 34,802 41,899

Sentinel 36,232 73,409 52,475

Other Sites 8,411 8,144 9,499

Copper sales (tonnes) 150,287 198,912 196,702

Cobre Panamá 70,028 85,330 74,885

Kansanshi2 31,538 32,496 53,240

Sentinel 40,313 71,642 58,550

Other Sites 8,408 9,444 10,027

Gold production (ounces) 47,874 70,493 70,357

Cobre Panamá 23,878 38,302 29,947

Kansanshi 15,960 24,479 32,640

Guelb Moghrein 7,585 7,434 6,912

Other sites 451 278 858

Gold sales (ounces)3 51,941 59,568 76,195

Cobre Panamá 28,853 34,208 30,168

Kansanshi 17,244 16,156 38,828

Guelb Moghrein 5,482 8,601 5,523

Other sites 362 603 1,676

Nickel production (contained tonnes) 5,917 5,705 5,122

Nickel sales (contained tonnes) 5,846 6,840 4,350

Cash cost of copper production (C1) (per lb)4,5 $2.24 $1.86 $1.61

Total cost of copper production (C3) (per lb)4,5 $3.30 $2.79 $2.65

Copper all-in sustaining cost (AISC) (per lb)4,5 $2.87 $2.42 $2.27

1 Production is presented on a contained basis, and is presented prior to processing through the Kansanshi smelter.

2 Sales include third-party sales of concentrate, cathode and anode attributable to Kansanshi (excluding copper anode sales attributable to Trident). Sales exclude the sale of

copper anode produced from third-party concentrate purchased at Kansanshi. Sales of copper anode attributable to third party concentrate purchases were 9,120 tonnes for

the three months ended March 31, 2023 (nil tonnes for the three months ended March 31, 2022).

3 Excludes refinery-backed gold credits purchased and delivered under the precious metal streaming arrangement (see “Precious Metal Stream Arrangement”).

4 Copper all-in sustaining cost (copper AISC), copper C1 cash cost (copper C1), and total cost of copper (copper C3) are non-GAAP ratios, which do not have a standardized

meaning prescribed by IFRS and might not be comparable to similar financial measures disclosed by other issuers. See “Regulatory Disclosures”.

5 Excludes the sale of copper anode produced from third-party concentrate purchased at Kansanshi. Sales of copper anode attributable to third-party concentrate purchases

were 9,120 tonnes for the three months ended March 31, 2023 (nil for the three months ended March 31, 2022).

REALIZED METAL PRICES1

QUARTERLY

Q1 2023 Q4 2022 Q1 2022

Average LME copper cash price (per lb) $4.05 $3.63 $4.53

Realized copper price (per lb) $3.95 $3.56 $4.45

Treatment/refining charges (“TC/RC”) (per lb) ($0.14) ($0.12) ($0.12)

Freight charges (per lb) ($0.02) ($0.04) ($0.04)

Net realized copper price1 (per lb) $3.79 $3.40 $4.29

Average LBMA cash price (per oz) $1,890 $1,728 $1,877

Net realized gold price1,2 (per oz) $1,766 $1,574 $1,772

Average LME nickel cash price $11.79 $11.47 $11.97

Net realized nickel price1,3 $10.25 $13.67 $13.52

1 Realized metal prices are a non-GAAP ratio, do not have standardized meanings under IFRS and might not be comparable to similar financial measures disclosed by other

issuers. See “Regulatory Disclosures” for further information.

2 Excludes gold revenues recognized under the precious metal stream arrangement.

3 The premium to the average LME cash price arose from the timings of sales across the periods, their respective quotation pricing periods and the impact from the

Company’s decision to temporarily suspend its nickel hedging program following the failure of the LME nickel platform in March 2023.

First Quantum Minerals Ltd. 23-16

Page 6 of 12

CONSOLIDATED FINANCIAL HIGHLIGHTS

QUARTERLY

Q1 2023 Q4 2022 Q1 2022

Sales revenues 1,558 1,832 2,163

Gross profit 280 361 908

Net earnings attributable to shareholders of the Company 75 117 385

Basic earnings per share $0.11 $0.17 $0.56

Diluted earnings per share $0.11 $0.17 $0.56

Cash flows from operating activities 299 237 666

Net debt1 5,780 5,692 5,815

EBITDA2,3 518 647 1,180

Adjusted earnings3 76 151 480

Adjusted earnings per share4 $0.11 $0.22 $0.70

Realized copper price (per lb)4 $3.95 $3.56 $4.45

Net earnings attributable to shareholders of the Company 75 117 385

Adjustments attributable to shareholders of the Company:

Adjustment for expected phasing of Zambian value-added tax (“VAT”) receipts (23) 56 22

Loss on redemption of debt – – –

Total adjustments to EBITDA2 excluding depreciation3 22 6 103

Tax and minority interest adjustments 2 (28) (30)

Adjusted earnings4 76 151 480

1 Net debt is a supplementary financial measure which does not have a standardized meaning under IFRS, and might not be comparable to similar financial measures disclosed

by other issuers. See “Regulatory Disclosures.

2 EBITDA and adjusted earnings are non-GAAP financial measures, which do not have a standardized meaning under IFRS and might not be comparable to similar financial

measures disclosed by other issuers. Adjusted earnings have been adjusted to exclude items from the corresponding IFRS measure, net earnings attributable to shareholders

of the Company, which are not considered by management to be reflective of underlying performance. The Company has disclosed these measures to assist with the

understanding of results and to provide further financial information about the results to investors and may not be comparable to similar financial measures disclosed by other

issuers. The use of adjusted earnings and EBITDA represents the Company’s adjusted earnings metrics. See “Regulatory Disclosures”.

3 Adjustments to EBITDA in 2023 relate principally to foreign exchange revaluations (2022 - foreign exchange revaluations and non-recurring costs relating to previously sold

assets).

4 Adjusted earnings per share, realized metal prices, copper all-in sustaining cost (copper AISC), copper C1 cash cost (copper C1), and total cost of copper (copper C3) are non-

GAAP ratios which do not have a standardized meaning prescribed by IFRS and might not be comparable to similar financial measures disclosed by other issuers. See

“Regulatory Disclosures”.

First Quantum Minerals Ltd. 23-16

Page 7 of 12

COMPLETE FINANCIAL STATEMENTS AND MANAGEMENT’S DISCUSSION AND ANALYSIS

The complete Consolidated Financial Statements and Management’s Discussion and Analysis for the three months

ended March 31, 2023 are available at www.first-quantum.com and at www.sedar.com and should be read in

conjunction with this news release.

CONFERENCE CALL DETAILS

The Company will host a conference call and webcast to discuss the results on Wednesday, April 26, 2023 at 9:00

am (ET).

Conference call and webcast details:

Toll-free North America: 1-800-319-4610

Toll-free International: +1-604-638-5340

Webcast: Direct link or on our website

A replay of the webcast will be available on the First Quantum website.

For further information, visit our website at www.first-quantum.com or contact:

Bonita To, Director, Investor Relations

(416) 361-6400 Toll-free: 1 (888) 688-6577

E-Mail: [email protected]

First Quantum Minerals Ltd. 23-16

Page 8 of 12