Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

FM.TO ·

FIRST QUANTUM MINERALS AND RIO TINTO FORM PARTNERSHIP TO PROGRESS THE LA GRANJA COPPER PROJECT IN PERU (In United States dollars, except where noted otherwise)

Partnerships & JV

NEWS RELEASE

23-15

March 30, 2023

www.first-quantum.com

FIRST QUANTUM MINERALS AND RIO TINTO FORM PARTNERSHIP

TO PROGRESS THE LA GRANJA COPPER PROJECT IN PERU

(In United States dollars, except where noted otherwise)

Toronto, Ontario (March 30, 2023) - First Quantum Minerals Ltd. (“First Quantum” or “the Company”) (TSX: FM) is

pleased to announce that it has entered into an agreement with Rio Tinto to progress the next phase of the La Granja

copper project (the “Project”) in Peru.

The Project is located in the district of Querocoto in the northern region of Cajamarca, Peru, approximately 90

kilometers northeast of Chiclayo, the capital of Lambayeque region, at an altitude of between 2,000 and 2,800 meters.

La Granja is one of the largest undeveloped copper resources in the world with a published Inferred mineral resource

of 4.32 billion tonnes at 0.51 percent copper and potential for substantial expansion. Rio Tinto has operated the

Project since 2006, carrying out an extensive drilling program that has significantly expanded the resource and has

managed a world-class community relations program that has ensured strong local support for the Project. First

Quantum will acquire a majority stake in the Project and will undertake the feasibility study and possible further

development of what has the potential to be a large, long-life operation.

“I am very pleased to announce today’s partnership with Rio Tinto, a global leader in the mining industry. Rio Tinto’s

work on La Granja has been extensive to date and w e share our partner’s view that the Project has the potential to

be a Tier 1 copper mine. We look forward to working together to build on this foundation, leveraging First Quantum’s

core strengths in mine design, project development and community engagement. This partnership will provide First

Quantum access to an attractive copper project , offering additional future optionality in the Company’s project

pipeline while we focus on strengthening the balance sheet in the interim,” said Tristan Pascall, Chief Executive Officer

of First Quantum . “First Quantum is excited about broadening our existing relationships in Peru and we are

appreciative of the support provided by the Government of Peru to this important partnership for its future

investment in the country.”

“La Granja is an exciting but complex project that has the potential to be a significant new source of the copper that

is needed for the energy tra nsition. We are pleased to enter into this agreement with First Quantum, that will bring

our combined development capabilities and deep knowledge of La Granja to progress the Project,” said Bold Baatar,

Chief Executive of Rio Tinto Copper. “This partnership underscores not only La Granja’s potential to be a significant

copper producer, but Peru’s position as one of the world’s most important mining investment destinations.”

KEY TERMS OF THE AGREEMENT

Upon completion, First Quantum will acquire a 55% interest in La Granja for a consideration of $105 million and will

become the operator of the Project. Following the acquisition, the Company will be responsible for $546 million of

funding (the “initial funding”). Part of the initial funding will be used to complete a feasibility study after which the

remaining majority of the initial funding is expected to be spent on construction of the Project following a positive

investment decision. Upon satisfaction of this initial funding amount, all subsequent expenditures will be applied on

a pro-rata basis according to the share ownership of the Project.

The completion of the transaction is subject to certain conditions, including regulatory approvals by the Government

of Peru that are currently underway. The transaction is expected to close before the end of Q3 2023.

First Quantum Minerals Ltd. 23-15

Page 2 of 2

WORK PLAN AND GUIDANCE

Work over the initial years will continue to progress community engagement and the feasibility study. The feasibility

study will focus on developing an updated geological resource and reserve model, which will require additional infill

drilling to upgrade Inferred resources to Measured and Indicated categories. Additional metallurgical studies to

establish optimal processing co nfigurations are expected to be carried out in parallel, together with a high -level

project layout and configuration of associated infrastructure requirements and logistical routes.

With work on La Granja focused mainly at the studies level, there is no change to the Company’s three-year guidance

provided in January 2023 on capital expenditures.

Further to the agreement on La Gran ja, First Quantum and Rio Tinto have also entered into a memorandum of

understanding to support co -operation in relation to bas e metals development opportunities and the sharing of

technology and know -how on certain mining methods, such as the application of trolley -assist and autonomous

mining fleets.

For further information, visit our website at www.first-quantum.com or contact:

Bonita To, Director, Investor Relations

(416) 361-6400 Toll-free: 1 (888) 688-6577

E-Mail: [email protected]

CAUTIONARY STATEMENT ON FORWARD-LOOKING INFORMATION

Certain statements and information herein, including all statements that are not historical facts, contain forward -looking statements and forward -looking information within the

meaning of applicable securities laws. The forward -looking statements in this n ews release include statements regarding the expected timing for closing of the transaction; the

satisfaction of closing conditions in respect of the Acquisition, including regulatory approvals; the work, including feasibility and metallurgical studies, to be completed to progress

the Project; the funding of expenditures related to the Project; the impact and expected benefits of the Acquisition and the Company’s partnership with Rio Tinto on the Company’s

business and operations; and expectations regarding the future demand for copper. With respect to forward -looking statements and information contained herein, the Company

has made numerous assumptions, including as to the receipt of necessary regulatory approvals required to complete Acquisition ; Rio Tinto and the Company maintaining strong

local support for the Project; the successful completion of the feasibility and metallurgical studies required to progress th e Project; and the ability of the Company to fund the

Acquisition, including the first $546 mil lion in study and development work and subsequent expenditures related to the Project. Forward -looking statements and information by

their nature are based on assumptions and involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements to

be materially different from any future results, performance or achievements expressed or implied by such forward -looking statements or information. These factors include, but

are not limited to, political stability in Peru, joint venture risks, potential social and environmental challenges, and events generally impacting global economic, political and social

stability. There may also be other factors that cause actual results, performance, achievements or events not as anticipated, estimated or intended, including the risks, uncertainties

and other factors discussed in the Company’s Annual Information Form. The Company undertakes no obligation to reissue or upda te forward-looking statements or information

as a result of new information or events after the date hereof except as may be required by law.