Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

FLCN.V ·

SRG: Positive Preliminary Economic Assessment and Resource Additions at Lola Pre-tax IRR of 35% over a 16-year mine life

Economic Studies

SRG: Positive Preliminary Economic Assessment and Resource Additions at Lola

Pre-tax IRR of 35% over a 16-year mine life

MONTREAL, July 10, 2018 /CNW Telbec/ - SRG Graphite Inc. (TSXV: SRG) ("SRG" or the "Company")

is pleased to announce results of a Preliminary Economic Assessment study ("PEA") for the development

of its Lola graphite project in the Republic of Guinea, West Africa. The PEA was prepared by Montréal-

based Met-Chem, a division of DRA Americas Inc. ("Met-Chem/DRA"). All dollar figures are in United

States dollars.

Highlights of the Lola graphite PEA:

• Production of 50,200 tons of graphite concentrate per year over a 16-year mine life

• Capital costs of $105 million ("M') including contingency of $15M

• Operational costs of $372/tonne ("t") of concentrate and $130/t of transport

• Pre-tax NPV(8%) of $204M (post-tax NPV(8%) of $121M) at an average sales price of $1,328/t

• Finished grade of over 94% and up to 98% over all size fractions

• Strip ratio of 0.39

"These results highlight the value of the Lola graphite asset for the company" said Ugo Landry-Tolszczuk,

President and Chief Operating Officer of SRG, "that said, the team will continue to work on improving the

design and economics of the project. During our trade-off assessment work, we have found several key

points of improvement to incorporate in the feasibility study. Early works which will contribute to the next

stage in the development of the project is underway and we are dedicated to meeting our objectives for

the year."

The PEA follows the Mineral Resource Estimate published on June 18, 2018. A technical report detailing

the PEA, and completed in accordance with National Instrument (NI) 43–101 guidelines, will be filed and

available on SEDAR within 45 days from June 18, 2018, the release date of the mineral resource update

published by the Company. Effective date of the estimate is June 14, 2018.

COMMERCIAL SALES, REVENUES & PROJECT ECONOMIC SENSITIVITIES

The Lola mine will produce an average of 50,200 tonnes of saleable graphite annually. At an average

sale price of $1,328 per tonne, this represents $66.6M annual revenue. Given the volatility of graphite

prices in recent years and the bilateral nature of sales contracts a sensitivity analysis of the project

economics is presented below in Table 1.

Table 1 Project economics sensitivity analysis (pre-tax)

Average Sale Price ($/t) 1,195 1,261 13281 1,394 1,460

Average annual revenue (million)2 60.0 63.3 66.6 70.0 73.3

Pre-tax returns

Average annual cash flow (million) 2 31.2 34.5 37.9 41.2 44.5

NPV (million) @ 8% discount 151 177 204 231 257

IRR (%) 28.5 31.7% 34.8% 37.9% 41.0%

Payback (years) 3.1 2.8 2.6 2.4 2.3

Post-tax returns

Average annual cash flow (million) 2 22.7 25.0 27.3 29.5 31.8

NPV (million) @ 8% discount 84 102 121 139 157

IRR (%) 20.3% 22.7% 24.9% 27.2% 29.4%

Payback (years) 4.2 3.9 3.5 3.3 3.0

1 Base case

2 Does not include year 16 as it is not a full year

MINERAL RESOURCES UPDATE

The PEA was prepared using data from the Mineral Resource Estimate published on June 18, 2018, and

including the latest drill campaign. To maximize the life of mine of the project, the PEA uses the resource

at a cut-off grade of 1.64% graphitic carbon ("Cg"), which includes measured resources of 2.1 million

tonnes ("Mt") grading 4.31% Cg, indicated resources of 17.0Mt grading 4.39% Cg and inferred resources

of 2.1Mt grading 4.79% Cg. The resource has been pit-constrained at $1,300/t. Figure 1 depicts the

resource locations on the deposit and represents approximately 30% of the deposit outline.

Figure 1 Map of the Deposit With Resource Classification

Figure 1 Map of the Deposit With Resource Classification (CNW Group/SRG Graphite)

The mineral resources update was estimated as at June 14, 2018, in accordance with the definitions

adopted by the Canadian Institute of Mining Metallurgy and Petroleum and incorporated into National

Instrument 43-101 – Standards of Disclosure for Mineral Projects (NI 43-101). Mineral resources estimate

update for the Lola graphite project was carried out by Dr. Marc-Antoine Audet, P.Geo., Lead Geologist

and SRG's Qualified Person.

MINING

The Lola deposit is characterised by its saprolite surface mineralisation, which continues at depth into the

fresh rock bed. For the PEA, mining operations were exclusively focused on the weathered zone,

ensuring operation efficiency and competitive cost of operations. The first 30 metres of the deposit

represent the weathered material. Constraining mining to the weathered portion of the deposit ensures

minimal utilisation of blasting, and results in a strip ratio of only 0.39.

The average grade fed to the processing plant over the 16-year mine life is 4.43% Cg, and the total

material mined per year is 1.8Mt (mineralised material and waste). Mining costs were established at

2.13$/t, considering preliminary pit design and access roads.

Table 2 Mining highlights

Mining costs ($/t material mined) 2.13

Average graphite grade (% Cg) 4.43%

Stripping ratio (waste/mineralised) 0.39

Average graphite bearing material mined per year (t/y) 1,294,763

Average waste mined per year (t/y) 510 178

Mine of Life (years) 16 years

PROCESS

The processing plant and waste dump are located on a plateau, west of the main pit, where the land is

already conveniently flat and barren of trees. It is currently less than one kilometre from the visual

mineralisation. This proximity will ensure short cycle times and contribute to the control of production

costs.

Efforts were made to keep a simple flowsheet with limited polishing and flotation stages. Concentrate

grade higher than 94% Cg is expected, with a recovery of 79%. Reagents used for processing are diesel

as a collector and methyl isobutyl carbinol ("MIBC") as a frother, both commonly available and routinely

used reagents in the graphite sector. The processing costs are $9.24/t of processed material resulting in

$248/t of graphite concentrate produced. Table 3 provides a summary of results.

Table 3 Process highlights

Processing costs ($/t plant feed) 9.24

Processing costs ($/t concentrate) 248

Average concentrate grade (%Cg) >94%

Graphite plant recovery 79%

Average material fed to the plant (t/year) 1,294,763

Process description:

Mineralised material handling, crushing, scrubbing, grinding and de-sliming circuits were designed

considering the saprolitic properties of the deposit. The relatively low competency of the material allows

the design to use two mineral sizers at the front end instead of a jaw crusher or cone crusher. These

processing units are known for their low operational cost and reliability compared with conventional jaw

and cone crushers.

The crushed material is fed into a scrubber which promotes flake preservation and consumes less energy

compared with conventional milling methods. The scrubber discharge is screened, where the coarse

fraction is fed to a closed-circuit ball mill, before being recombined with the screen fines. The combined

slurry is then fed through a de-sliming stage, where ultra-fines, including slime, clay and organic material

are removed. This leads to an upgraded and cleaner material feeding the flotation circuit, resulting in an

overall simpler flowsheet.

After de-sliming, the material is fed to the rougher flotation bank producing a rougher concentrate. A first

polishing stage further liberate the graphite flakes. The polished rougher concentrate goes through a first

cleaning stag and is then fed into a splitting screen, dividing the fine from the coarse graphite, in order to

apply the relevant specific polishing energy to each stream. After their respective polishing and cleaning

stages, the two streams are recombined, thickened, filtered and dried. The dried concentrate is then

screened into four different size fractions before being bagged, and finally stored and shipped to clients.

Figure 2 Process flowsheet

Figure 2 Process flowsheet (CNW Group/SRG Graphite)

Quality Control and Assurance

Silvia Del Carpio, P.Eng., MBA Met-Chem/DRA., independent Qualified Person as defined by National

Instrument 43-101, for the purposes of the PEA has reviewed the technical content of this press release.

Raphaël Beaudoin P. Eng., Director of Operations and a Qualified Person for SRG has read and

approved this press release.

Cautionary Note

The PEA completed for the Company is preliminary in nature and includes inferred mineral resources,

considered too speculative in nature to be categorized as mineral reserves. Mineral resources that are

not mineral reserves have not demonstrated economic viability. Additional trenching and/or drilling will

be required to convert inferred mineral resources to indicated or measured mineral

resources. There is no certainty that the resources development, production, and economic forecasts on

which this PEA is based will be realized.

About Met-Chem/DRA

Met-Chem, a division of DRA Americas Inc., was originally established in 1969 as a consulting

engineering company, headquartered in Montreal, and provides a wide range of technical and

engineering services. Met-Chem is well recognized for its capabilities in mining, geology and mineral

processing and has a talented team of engineering, technical and project management personnel with

experience in North America, Latin America, Europe, West Africa and India. DRA is a multidisciplinary

global engineering group that originated in South Africa and delivers mining, mineral processing, energy,

water treatment and infrastructure services from concept to commissioning, as well as comprehensive

operations and maintenance services for the mineral resources, water, agriculture and energy sectors.

DRA has offices in Africa, Australia, Canada, China, India and the United States.

ABOUT SRG

SRG is a Canadian-based company focused on developing the Lola graphite deposit and the Gogota

nickel-cobalt-scandium deposit, both located in the Republic of Guinea, West Africa. SRG is committed to

operating in a socially, environmentally and ethically responsible manner.

For additional information, please visit SRG's website at www.srggraphite.com.

Neither the TSXV nor its Regulation Services Provider (as that term is defined in the policies of the TSXV)

accepts responsibility for the adequacy or accuracy of this release.

Forward-Looking Statements

This press release contains "forward-looking information" within the meaning of Canadian securities

legislation. All information contained herein that is not clearly historical in nature may constitute forward-

looking information. Generally, such forward-looking information can be identified by the use of forward-

looking terminology such as "positive", "result", "improve", "dedicate", "will", "sale", "revenue", "includes",

"continue", 'ensuring", "low", "demonstrate", "potential", or variations of such words and phrases or state

that certain actions, events or results "may", "could", "would" or "might". Forward-looking information is

subject to known and unknown risks, uncertainties and other factors that may cause the actual results,

level of activity, performance or achievements of the Company to be materially different from those

expressed or implied by such forward-looking information, including but not limited to: (i) volatile stock

price; (ii) the general global markets and economic conditions; (iii) the possibility of write-downs and

impairments; (iv) the risk associated with exploration, development and operations of mineral deposits; (v)

the risk associated with establishing title to mineral properties and assets; (vi) fluctuations in commodity

price; (viii) the risks associated with uninsurable risks arising during the course of exploration,

development and production; (ix) competition faced by the Company in securing experienced personnel

and financing; * access to adequate infrastructure to support mining, processing, development and

exploration activities; (xi) the risks associated with changes in the mining regulatory regime governing the

Company; (xii) the risks associated with the various environmental regulations the Company is subject to;

(xiii) risks related to regulatory and permitting delays; (xiv) risks related to potential conflicts of interest;

(xv) the reliance on key personnel; (xvi) liquidity risks; (xvii) the risk of potential dilution through the issue

of common shares; (xviii) the risk of litigation; and (xix) risk management as well as other risks and factors

described or referred to in the section entitled "Risk Factors" in the MD&A of the Company and which is

available at www.sedar.com, all of which should be reviewed in conjunction with the information found in

this news release.

Forward-looking information is based on assumptions management believes to be reasonable at the time

such statements are made, including but not limited to; the capacity of the Company to execute on its

plans for production of 50,200 tons of graphite per year over a 16-year mine life, to have capital costs of

$105M for the project including operational costs of $372/t of concentrate, $130/t of transport cost; to

produce at a finished grade of over 95% and up to 98%; a strip ratio of 0.39; to sell its products at an

average selling price of $1,328; continued exploration activities and no material adverse change in

mineral prices, exploration and development plans to proceed in accordance with plans and such plans to

achieve their stated expected outcomes, receipt of required regulatory approvals, and such other

assumptions and factors as set out herein. Although the Company has attempted to identify important

factors that could cause actual results to differ materially from those contained in the forward-looking

information, there may be other factors that cause results not to be as anticipated, estimated or intended.

There can be no assurance that such forward-looking information will prove to be accurate, as actual

results and future events could differ materially from those anticipated in such forward-looking

information. Such forward-looking information has been provided for the purpose of assisting investors in

understanding the Company's business, operations and exploration plans and may not be appropriate for

other purposes. Accordingly, readers should not place undue reliance on forward-looking information.

Forward-looking information is given as of the date of this press release, and the Company does not

undertake to update such forward-looking information except in accordance with applicable securities

laws.

SOURCE SRG Graphite

View original content with multimedia:

http://www.newswire.ca/en/releases/archive/July2018/10/c6775.html

%SEDAR: 00008697E

For further information: Ugo Landry-Tolszczuk, Tel: +1 (514) 679-4196, Email:

[email protected]; Benoit La Salle, FCPA FCA, Tel: +1 (514) 951-4411, Email:

[email protected]

CO: SRG Graphite

CNW 07:00e 10-JUL-18