Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

FLCN.V ·

SRG Announces Positive Feasibility Study Results for Its Lola Graphite Project - Pre-Tax NPV of USD 277M and IRR of 28% Over a 29- Year Mine Life

Economic Studies

SRG Announces Positive Feasibility Study

Results for Its Lola Graphite Project - Pre-Tax

NPV of USD 277M and IRR of 28% Over a 29-

Year Mine Life

MONTREAL

,

July 4, 2019

/CNW Telbec/ -

SRG Mining Inc.

(TSXV: SRG) ("SRG" or the

"Company") is pleased to announce the results of its Feasibility Study ("FS") for the development of

the Lola graphite project in the Republic of

Guinea

,

West Africa

. The FS was prepared by

Montreal

-

based DRA/Met-Chem, a division of DRA Americas Inc. ("DRA/Met-Chem"). All dollar figures are in

United States

dollars.

The FS was officially started in

September 2018

and has been produced with the input of numerous

engineering and consulting firms, notably DRA/Met-Chem, Epoch, BBA, Sahara Natural Resources,

MDEng, SGS Canada, CCIC, and Jenike & Johanson. Included in the FS is an updated resource

calculation, which follows the Company's 2018 drilling campaign, bringing the total resource to 46.0

million tonnes ("Mt") of measured and indicated resources grading 4.09% graphitic carbon ("Cg").

The following lists the highlights of the Feasibility Study:

Average annual production of 54,600 tonnes of graphite flakes over a 29-year mine life

Proven & probable reserves of 42.0Mt @ 4.17% Cg

Capital costs of

$123 million

("M") including a power plant of

$5.8M

, concentrate transport

equipment of

$3.6M

, and contingency of

$12M

Added flexibility of the plant to process soft saprolite and fresh rock, provides optionality and

the ability to expand the production profile

Average operational costs of

$470

/tonne ("t") and

$38

/t of transport. For the first 16 years of

production, the average operational costs are

$447

/t.

Pre-tax NPV(8%) of

$277M

and internal rate of return ("IRR") of 28%

Post-tax NPV(8%) of

$159M

and IRR of 21%

Average grade of graphite flakes over 95%

A low strip ratio of 0.69

This

video

is a flyby simulation of the project layout.

"These results are the culmination of many months of studies to de-risk the project and add to its

robustness" said

Ugo Landry-Tolszczuk

, President and Chief Operating Officer of SRG. "The

economic highlights present a highly profitable business using reasonable estimates for graphite

selling price. Basic engineering will focus on improvements in the front-end of the plant, tailings

management, and reducing the mining footprint."

A technical report detailing the completed feasibility study in accordance with National Instrument

(NI) 43 – 101 guidelines will be filed and available on SEDAR within 45 days from

July 4, 2019

.

The effective date of the technical report is

June 18, 2019

.

Commercial Sales, Revenues & Project Economic Sensitivities

Over the life of the mine, the Lola project will produce an average of 54,600 tonnes of saleable

graphite flakes per year. At an average sale price of

$1,321

/t, this represents $72.2M annual

revenue incurring average operating costs of

$508

/t representing

$27.7M

annually. Given the

volatility of graphite prices in recent years and the bilateral nature of sales contracts, a sensitivity

analysis of the project's economics is presented below in Table 1.

Table 1 Project economics sensitivity analysis

LOM Average Sale Price ($/t)

1,056

1,189

1,321

1

1,453

1,585

Average annual revenue (million)

2

57.8

65.0

72.2

79.5

86.7

Pre-tax returns

Average annual cash flow (million)

2

25.6

32.9

40.1

47.3

54.6

NPV (million) @ 8% discount

135

206

277

348

420

IRR (%)

18.5%

23.4%

28.1%

32.6%

36.9%

Payback (years)

5.0

4.0

3.4

3.0

2.7

Post-tax returns

Average annual cash flow (million)

2

17.4

22.2

27.0

31.8

36.6

NPV (million) @ 8% discount

64

111

159

206

253

IRR (%)

13.7%

17.6%

21.2%

24.6%

27.8%

Payback (years)

5.8

4.8

3.9

3.6

3.2

1

Base case

2

Does not include years 1 and 29 as they do not represent full production

Mineral Resource Update

The resource estimate was established using data from boreholes drilled and sampled up to

December 1, 2018

. The total resource estimate of the Lola Project includes 6.84Mt grading 4.39%

Cg, indicated resources of 39.2Mt grading 4.04% Cg, and inferred resources of 4.25Mt grading

3.75% Cg. The resource estimate has been prepared using a cut-off grade of 1.65% Cg, and has

an optimized physical pit shell constrained at

$1,400

/t of concentrate.

Figure 1

depicts the resource

location which, represents approximately 40% of the deposit outline.

The mineral resources update was estimated as of

June 18

, 2019, in accordance with the definitions

adopted by the Canadian Institute of Mining, Metallurgy and Petroleum and incorporated into

National Instrument 43-101 – Standards of Disclosure for Mineral Projects (NI 43-101). The mineral

resources estimate update for the Lola graphite project was carried out by

Desmond Subramani

(Pri. Sci. Nat - 400184/06), Independent QP and Principal Geologist – Mineral Resource Estimation

at Caracle Creek International Consulting MINRES (Pty) Ltd. (CCIC MINRES).

Mining

The Lola deposit is characterised by its saprolite surface mineralization, which continues at depth

into the fresh rock bed. For the FS, mining operations considered the mineralized material contained

in the weathered zones (lateritic and saprolitic ore), as well as the mineralized material contained in

the fresh-rock formation.

This results in a total Mineral Reserves estimate of approximately 42.0Mt grading 4.17% Cg, and an

overall strip ratio of the operation (all the pits combined) of only 0.69.

Figure 2

presents the overall

site layout. The table below shows the proven and probable reserves.

Table 2 Proven & probable reserves

Category

Tonnage (Mt)

1

Cg grade (%Cg)

Proven Reserves

6.7

4.43%

Probable Reserves

35.4

4.13%

Proven & Probable Reserves

42.0

4.17%

1: The totals may not add up due to rounding.

The average grade fed to the processing plant over the 29-year mine life is 4.17% Cg, and the total

material mined per year is 2.5Mt (ore and waste). Mining costs were established at

$2.23

/t material

moved, considering pit design and access roads.

Table 3 Mining highlights

Mining costs ($/t material moved)

2.23

Average graphite grade (% Cg)

4.17%

Stripping ratio (waste/ore)

0.69

Average ore material mined per year (t/y)

1,450,000

Life of mine (years)

29 years

Process

The mineral processing plant consists of a crushing area and a concentrator where material

beneficiation and concentrate dewatering, screening, and packaging takes place.

The process flowsheet includes crushing, scrubbing and grinding, rougher flotation, polishing, and

cleaner flotation. The back end of the concentrator includes tailings and concentrate thickening,

concentrate filtration and drying, dry screening and bagging of graphite products, and material

handling.

All the tailings from the concentrator will be thickened and pumped to the tailings ponds. Reclaiming

water from the tailings ponds has been considered in the process design to minimize fresh water

makeup to the concentrator.

The graphite concentrate will be recovered by a conventional flotation process. Saprolite ore

beneficiation process has an overall graphite recovery of 73.1%, producing a graphite concentrate

grade of 95.4 % Cg. The addition of up to 45% of fresh rock in the feed blend improves the overall

graphite recovery to 84.2%. A suitable process flowsheet able to handle saprolite as well as a feed

blend with fresh rocks has been developed for the feasibility study.

Over the life of the mine, the plant will produce graphite concentrate divided into four (4) standard-

size fractions: +48 mesh, -48+80 mesh, -80+100 mesh and -100 mesh presented in Table 5.

Figure 3

depicts the simplified flowsheet.

Table 4 Process highlights

Processing costs ($/t plant feed) -100% Saprolite feed

8.91

Processing costs ($/t plant feed) - blend of 55% Saprolite / 45% Fresh rocks feed

10.86

Average concentrate grade (%Cg)

95.4%

Graphite plant recovery based on 100% Saprolite feed

73.1%

Graphite plant recovery based on blend of 55% Saprolite / 45% Fresh rocks feed

84.2%

Table 5 Size fraction profile & grade

Size Fraction (mesh)

LoM Expected

Distribution (%)

Grade (%Cg)

+ 48

16.6

97.0

- 48 + 80

27.5

96.0

- 80 + 100

8.8

94.5

- 100

47.1

94.9

Total

100.0

95.4

Capital & Operating Costs

The capital costs for the project are presented below in Table 6. The capital costs shown include the

Company's assumed mining operations, graphite flake transport from-plant-to-port operations, and

production of its own power using generators. All three of these items could be contracted to third

parties. The average annual sustaining capital expenditure over a 29-year period is

$4.4M

.

Table 6 Capital cost summary

Capital Costs

Initial ($M)

Mining

9.3

Process

31.5

Tailings

8.4

Site infrastructure

11.8

Off-site infrastructure

1.4

Preliminary & general

16.6

Sub-total

79.2

Power plant

5.8

Graphite transport equipment

3.6

Total Direct Costs

88.5

EPCM

10.3

Pre-production

5.6

Other indirect costs

0.7

Total Indirect Costs

16.6

Contingency

12.4

Owner's costs

5.5

Total Costs

1

123.1

1: The totals may not add up due to rounding.

The operating costs presented in Table 7 indicate the average operating costs, including graphite

flake transport from mine-site to the port of

Monrovia

as well as port fees. These operating costs

also assume the Company will mine and produce its own power using generators.

The average operating costs without transport for the first 16 years is

$447

/t, increasing thereafter.

Table 7 Operating cost summary

Operating Costs Breakdown

Average Annual Costs ($M)

2

Average $ per tonne of concentrate

Mining

5.9

108

Process

16.1

294

General and Administration

3.3

60

Tailings

0.4

7

Total operating costs

25.7

470

Graphite Transportation to port

2.1

38

Total OPEX

1

27.7

508

1: The totals may not add up due to rounding.

2: Excludes the first and last year.

Quality Control And Assurance

Qualified Persons ("QP") have reviewed and verified that the technical information with respect to

the FS contained in this press release is accurate, and have approved the written disclosure of such

information. For readers to fully understand the information in this press release, they should read

the Technical Report in its entirety when it is available on SEDAR, including all qualifications,

assumptions, and exclusions that relate to the information to be set out in the Technical Report,

which qualifies the technical information contained in the Technical Report. The Technical Report is

intended to be read as a whole, and sections should not be read or relied upon out of context.

The QPs who will prepare the Technical Report are:

DRA:

Silvia Del Carpio

, P.Eng., MBA (Project Manager and Financial Modelling),

Yves Buro

, P.

Eng. (Geology),

Patrick Perez

, P.Eng. (Mineral Reserves and Mining), Volodymyr Liskovych,

PhD, P.Eng. (Metallurgy),

William Shadeed

, P.Eng. (Processing)

CCIC:

Desmond Subramani

, Pri. Sci. Nat. (Mineral Resources)

MDEng:

Kathy Kalenchuk

, PhD, P.Eng. (Geotechnical Design)

BBA:

Luciano Piciacchia

, PhD, P.Eng. (Water Management, Closure and Rehabilitation Plan)

David Sims Inc.:

David Sims

, Geo, P. Geo (Hydrogeology)

Epoch: Guy Wiid, Pr.Eng. C.Eng,

George Papageorgiou

, PhD, MSc, BSc Eng. (Tailings Design)

By virtue of education and relevant experience, the aforementioned are independent "Qualified

Persons" for the purpose of NI 43 - 101. Other than as set forth above, all scientific and technical

information contained in this press release has been reviewed, verified, and approved by Raphaël

Beaudoin, P. Eng., Director of Operations and a Qualified Person for SRG under NI 43 - 101.

About DRA/Met-Chem

Met-Chem, a division of DRA Americas Inc., was originally established in 1969 as a consulting

engineering company, headquartered in

Montreal

, and provides a wide range of technical and

engineering services. DRA is a multidisciplinary global engineering group that delivers mining, mineral

processing, energy, water treatment and infrastructure services from concept to commissioning and

into operation. DRA has offices in

Africa

,

Australia

,

Canada

,

China

and

the United States

.

About SRG Mining

SRG Mining is a Canadian-based mining company focused on developing the Lola graphite deposit

located in the Republic of

Guinea

,

West Africa

. SRG is committed to operating in a socially,

environmentally, and ethically responsible manner.

Neither the TSXV nor its Regulation Services Provider (as that term is defined in the policies of the

TSXV) accepts responsibility for the adequacy or accuracy of this release.

Forward-Looking Statements

This press release contains "forward-looking information" within the meaning of Canadian securities

legislation. All information contained herein that is not clearly historical in nature may constitute

forward-looking information. Generally, such forward-looking information can be identified by the use

of forward-looking terminology such as "will", "continue", "provide", "present", "reasonable",

"established", "has", "demonstrate", "potential", or variations of such words and phrases or state

that certain actions, events or results "may", "could", "would" or "might". Forward-looking information

is subject to known and unknown risks, uncertainties and other factors that may cause the actual

results, level of activity, performance or achievements of the Company to be materially different from

those expressed or implied by such forward-looking information, including but not limited to: (i)

volatile stock price; (ii) the general global markets and economic conditions; (iii) the possibility of

write-downs and impairments; (iv) the risk associated with exploration, development and operations

of mineral deposits including the accuracy of the current mineral reserve and mineral resource

estimates of the Company (including, but not limited to, ore tonnage and ore grade estimates) and

mine plans for the Company's mining operations (including, but not limited to, throughput and

recoveries being affected by metallurgical characteristics); (v) the risk associated with establishing

title to mineral properties and assets including permitting, development, operations and production

from the Company's operations being consistent with expectations and projections; (vi) fluctuations in

commodity prices and other risks and factors described or referred to in the section entitled "Risk

Factors" in the MD&A of the Company and which is available at

www.sedar.com

, all of which should

be reviewed in conjunction with the information found in this news release

Forward-looking information is based on assumptions management believes to be reasonable at the

time such statements are made, including but not limited to, the capacity to produce an average

production of 54,600 tonnes of graphite flakes per year over a 29-year mine life, the Capital costs of

being only

$123 million

, the capacity of the design to provide added flexibility of the plant to process

soft saprolite and fresh rock, the capacity to provide optionality and the ability to expand production

profile, the capacity of the average operational costs to be

$470

per tonne and

$38

/t of transport,

the Pre-tax NPV(8%) of being

$277M

and achieving internal rate of return ("IRR") of 28%, and Post-

tax NPV(8%) of

$159M

and IRR of 21% as well as the continued exploration activities and no

material adverse change in mineral prices. Although the Company has attempted to identify

important factors that could cause actual results to differ materially from those contained in the

forward-looking information, there may be other factors that cause results not to be as anticipated,

estimated or intended. There can be no assurance that such forward-looking information will prove

to be accurate, as actual results and future events could differ materially from those anticipated in

such forward-looking information. Such forward-looking information has been provided for the

purpose of assisting investors in understanding the Company's business, operations and exploration

plans and may not be appropriate for other purposes. Accordingly, readers should not place undue

reliance on forward-looking information. Forward-looking information is given as of the date of this

press release, and the Company does not undertake to update such forward-looking information

except in accordance with applicable securities laws.

For additional information, please visit SRG's website at

www.srgmining.com

.

SOURCE

SRG Mining Inc.

View original content:

http://www.newswire.ca/en/releases/archive/July2019/04/c4120.html

%SEDAR: 00008697E

For further information:

Ugo Landry-Tolszczuk, Email: [email protected];

Benoit La Salle, FCPA FCA, Email: [email protected]

CO: SRG Mining Inc.

CNW 07:00e 04-JUL-19