ASX | TSX: FFM Page | 1 Green Bay Copper-Gold Project, Canada Preliminary Economic Assessment and Mineral Resource Update Economic study demonstrates scale, grade, long life, growth potential and robust financial returns

Resource Estimates Economic Studies

ASX | TSX: FFM

Page | 1

Green Bay Copper-Gold Project, Canada

Preliminary Economic Assessment and Mineral Resource Update

Economic study demonstrates scale,

grade, long life, growth potential and

robust financial returns

Preliminary Economic Assessment completed for the Green Bay Ming Mine Copper-Gold

Project demonstrates positive economics across 1.8Mtpa base case and 4.6Mtpa alternative

KEY POINTS

• Preliminary Economic Assessment (PEA)1 into the restart of production at the Green Bay Ming

Mine Copper-Gold Project demonstrates a robust large-scale, multi-decade operation

• FireFly’s study establishes Green Bay’s potential as one of the best undeveloped copper

projects in the world based on its high-grade Resource, production profile, growth outlook

and superior financial returns

• FireFly is in an strong financial position comprising existing cash and liquid investments of

A$183m2, anticipated equity raise proceeds of up to A$190m, and abundant scope to support

a conventional debt component

• The PEA considered two production scenarios: a 1.8Mtpa (4,800tpd) base case and a larger

4.6Mtpa (12,500tpd) alternative, with key results as follows:

• 1.8Mtpa (4,800tpd) base case

o After tax Net Present Value (NPV7%) of ~A$2.2B and Internal Rate of Return (IRR) of 41% over an initial

~32 year mine life

o Annual projected average production of 50kt copper equivalent (CuEq) metal over a 14-year period

at steady state after ramp up to peak at 60kt of CuEq metal per annum

o ~A$290M post-tax annual free cash flow over a 15-year period (LOM ~A$5.4B post-tax)

o C1 Cash Costs3 of US$2.05/lb CuEq in the lower quartile (US$1.17/lb Cu net of by-product credits)

o Rapid payback of just 1.9 years

o Released from further Environment Assessment; All environmental permits received to commence

select early works

o Low Initial capital is estimated at A$513M4 (net of refundable Canadian tax credits of ~A$58M)

1 The PEA meets the requirements of a Scoping Study as defined by the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral

Resources and Ore Reserves (JORC Code 2012).

2 Cash and liquid investments (unaudited) at 31 July 2026.

3 C1 cash Costs comprise mining costs, processing costs, mine-level G&A, and off-site charges.

4 Includes potential Canadian refundable Clean Technology Manufacturing Investment Tax Credit (CTM-ITC). The CTM-ITC estimate is based on a preliminary

assessment of expenditure estimated in the PEA and current legislative requirements. The availability, timing and value of any tax credits or incentives are

subject to final project design, execution and satisfaction of applicable legislative eligibility requirements. There is no assurance that the full benefit of the CTM-

ITC or other incentives will be realised.

ASX | TSX: FFM

Page | 2

• 4.6Mtpa (12,500tpd) alternative

o After tax NPV7% of ~A$3.0B and IRR of 39% over an initial ~22 year mine life

o Annual projected average production of ~90kt CuEq metal over an 11-year period at steady state

after ramp up including 6 years where annual production averages ~100kt CuEq . Production is

expected to peak at ~106kt of CuEq metal per annum

o ~A$550M post-tax annual free cash flow over the same 11-year period (LOM - ~A$6.5B post-tax)

o C1 Cash Costs of US$1.84/lb CuEq in the lower quartile (US$1.02/lb CuEq net of by-product credits)

o Rapid payback of ~3.7 years

o Expansion capital is estimated at A$476M 5 (net of refundable Canadian tax credits of A$53M),

expected to be mostly funded from cash flow from the 1.8Mtpa base case

• Based on the strong economics defined in the PEA, work has now commenced to rapidly

progress the Feasibility Study, which is expected to be delivered in Q1 2027 and is targeted to

support a Final Investment Decision (FID) and construction in H1 2027

• Regulatory approvals have been received to commence early works prior to FID. This will

fast-track construction timeli nes on the 1.8Mtpa case with potential for first concentrate

production in mid-2029

• The Green Bay Copper-Gold Project is now und erpinned by a revised independent Mineral

Resource Estimate (MRE) that stands at 60.2Mt @ 2.4% CuEq in the Measured and Indicated

(M&I) Resource categories and a further 23.5Mt @ 2.5% CuEq of Inferred Mineral Resources

• The high-grade core zone (Core Zone) now stands at 18.1Mt @ 4.3% CuEq in M&I plus a further

7.0Mt @ 4.4% CuEq in Inferred Mineral Resource, and remains open

• Importantly, 77% of the Ming Mine Mineral Resource is in the higher-confidence M&I category

• Growth remains central to the FireFly strategy. Continued expansion of the upper mine level

high-grade Volcanogenic Massive Sulphide (VMS) and Core Zone has the potential to

significantly extend high-grade production beyond peak years and further enhance project

economics earlier in the mine life. Six drill rigs continue underground focused on immediate

high-grade extensions for further Resource growth

• The mineralisation at Ming re mains open at depth with a large conductive geophysical

anomaly beyond the deepest drillhole that returned 49m @ 6.1% CuEq (See ASX announcement

dated 16 October 2025)

• On a district scale, drilling has commenced on several high-priority historical VMS copper

and gold mine targets that sit within only 5km of the Ming Mine. It is anticipated that a maiden

Resource will be established at the first target in the coming quarter. Furthermore, surface

exploration continues regionally with three rigs on numerous surface VMS targets

Equity Raising

• FireFly is undertaking a A$180 million (before costs) equity raising at an issue price of A$1.78

(C$1.76) per share via a single-tranche ASX institutional placement and Canadian bought

5 Refer to note 3.

ASX | TSX: FFM

Page | 3

deal financing (See ASX Announcement dated 25 August 2026 titled ‘FireFly Bolsters Funding for Project

Development and Growth’)

• FireFly also intends to undertake a non-underwri tten Share Purchase Plan to raise up to an

additional A$10m (before costs) (See ASX Announcement dated 25 August 2026 titled ‘FireFly Bolsters Funding

for Project Development and Growth’)

• The raising, combined with ~A$183 million 6 of existing cash reserves and liquid investments

and initial advice that the debt carrying capacity of the 1.8Mtpa base case scenario could

support commercial debt in excess of US$350 million (A$500 million), puts FireFly in an

strong financial position, particularly when viewed against the estimated initial project

capital cost of A$513 million7

FireFly Managing Director Steve Parsons said: “The findings of the economic study prove that

Green Bay is one of the best undeveloped copper projects in the world based on a range of key

metrics, ranging from scale and production profile through to financial returns and growth.

“The base case of 50,000t a year generates strong returns and we have a clear pathway to

double that. And that is before allowing for the growth we aim to unlock through our ongoing

drilling programs in the high-grade areas of the mine and the highly prospective regional

exploration program now cranking up.

“The project simply ticks every box and is clearly poised to generate outstanding returns for all

our stakeholders. The highly enviable nature of Green Bay is reflected in the fact that we have

just launched a A$180m share placement across the ASX and TSX exchanges.

“Once in production, Green Bay has the potential to be one of the biggest copper mines in the

world outside those owned by the multi-nationals and diversified mining giants. This means

FireFly offers investors virtually pure copper exposure via an asset with genuine world-scale in

a tier-one location.

“Our scale, our concentrated copper exposure and our outstanding growth outlook is a very rare

combination in global markets. It is unique on the ASX. FireFly offers concentrated exposure to

high-grade copper production in a tier-one location with ongoing growth potential”.

PERTH, Australia and TORONTO, Canada, FireFly Metals Ltd (ASX, TSX: FFM) is pleased to announce

the results of the Green Bay Ming Mine Prel iminary Economic Assessment / Scoping Study ( PEA)

and an updated Mineral Resource Estimate ( MRE) for the Green Bay Ming Mine Copper-Gold

Project (Project).

The results of the PEA demonstrate that the Projec t is a large-scale, long-life copper-gold project

that combines high-grade mineralisation, ro bust economics, and a substantial Resource

endowment to deliver sustained and substantial production over multiple decades.

6 Refer to note 1.

7 Refer to note 4.

ASX | TSX: FFM

Page | 4

Two compelling development considerations are presented in the PEA, one contemplating a base

case processing 1.8 million tonnes per annum ( Mtpa) and a larger scale 4.6Mtpa operation case.

Both scenarios returned positive and robust economic results.

The study has only taken into account the Ming De posit Mineral Resource Estimate and does not

include anything outside of the immediate Ming area such as Little Deer or any of the other regional

targets and historical copper-gold VMS mines that still remain to be drill tested by FireFly such as

Rambler, East mine, Main mine, Tilt Cove or Nugget Pond. These areas will be targeted for additional

growth throughout 2026/27.

The PEA is based on a high qual ity and robust Mineral Resource Estimate with the 1.8Mtpa case

supported by 79% in the higher confidence Measured and Indicated ( M&I) Mineral Resource

categories over the 32-year life of mine, including 89% over the first 10 years. The 4.6Mtpa case is

underpinned by 80% M&I over the life of mine plan.

Given the overwhelmingly positive results from the PEA study, the Company will now work towards

completing Feasibility level analysis targeted to be completed in Q1 2027 and followed by a Final

Investment Decision (FID) shortly thereafter.

Discount rate and commodity prices

The Project economics were estimated using conservative commodity price assumptions that are

materially below prevailing spot market prices as at 18 August 2026 (Spot Price)8. The study utilised:

o copper price of US$5.00/lb, 24% below current Spot Price of US$6.60/lb;

o gold price of US$3,500/oz, 19% below the Spot Price of US$4,335/oz; and

o silver price of US$44/oz, 30% below the Spot Price of US$63/oz.

A discount rate of 7% was applied in the NPV analysis, which has a material impact on the valuation

of a long-life, multi-decade project.

Globally recognised technical services consul tants generated the capital and operating costs

based on known similar industry benchmarking costs.

Appropriate contingencies have been applied to all capital cost estimates.

Green Bay Mining & Processing Operations

The PEA was prepared with contributions by se ctor leading independent consultants including

Ausenco, Stantec, Knight Piésold, Entech Mining, WSP, T Engineering, Egis Canada and Gemtec

Detailed review of numerous mining methods was completed as part of the PEA. Industry-

standard Long Hole Open Stoping (LHOS) with paste backfill was selected as the preferred mining

method for both the 1.8Mtpa (4,800tpd) base case and the alternate 4.6Mtpa (12,500tpd) option.

Utilising a combination of transverse LHOS and longitudinal LHOS provided the best economic

outcomes by balancing productivity levels and minimising dilution.

Haulage options for the operations differed between the two scenarios presented in the PEA. The

1.8Mtpa (4,800tpd) base case utilised truck haulage over the life of mine. A bypass decline around

8 Spot prices as at 18 August 2026.

ASX | TSX: FFM

Page | 5

the narrower sections of the historic decline has been factored into the cost estimates. This allows

larger 63t trucks to be used. Simulation of truck haulage conducted by external contractors on the

design demonstrated that it is feasible for the mine to produce 1.8Mtpa via trucking.

The 4.6Mtpa (12,500tpd) case requires a haulage shaft to achieve the upscaled productivity. A

7.6m diameter shaft is envisioned that can hoist 12,500tpd. A geotechnical hole completed by the

Company in the proposed shaft position shows exceptional ground conditions. Costing estimates

included in the PEA for the 4.6Mtpa case have been provided by world-leading Canadian shaft

specialists Redpath Mining.

Detailed analysis of mine ventilation has been conducted by specialist consultants BBE Group. Two

exhaust raise bores have been factored into the mine design. Vent simulations show these provide

sufficient volumes of air for the entire Life of Mine (LOM) in both scenarios.

Development of the mine is significantly fast-tracked with lower upfront capital expenditure,

leveraging more than A$250M of existing site in frastructure, including over 20km of accessible

underground development.

Extensive metallurgical testwork completed at SGS Lakefield in Canada shows the ore-grade

material has favourable physical properties (strength, grindabi lity, abrasiveness etc.) and is

amenable to high recoveries of copper and precious metals via industry standard processes as

demonstrated by the previous operation.

The proposed processing plant utilises a standard simple flow sheet to extract copper and

precious metals into a concentrate. Comminut ion is achieved through a standard jaw crusher

followed by a Semi Autogenous Grinding ( SAG) mill and a Ball Mill. Two stage flotation (rougher

and cleaner) provide exceptional recoveries an d production of a high-grade concentrate for

shipping (21-28% Cu, 6-12g/t Au). Precious metal recovery is further enhanced by the collection of

a pyrite tail from the cleaner fl otation which is leached and a doré produced on site. Based on a

combination of test work and historical performa nce, recoveries are anticipated to be >98% for

copper and >80% on precious metals (gold and silv er). There are no deleterious elements in the

concentrate. The concentrate will be shipped from a port located ~6km from the mine.

The mill has been designed by Ausenco in a mo dular fashion allowing for future growth and

expansion. To expand from 1.8Mtpa to 4.6Mtpa requires a simple twinning of the circuit and

installation of additional crushing capacity at the front-end of the process.

Approximately 55% of the tailings will be used in the paste backfill and stored underground whilst

providing geotechnical stability to allow for total extraction of the mineralisation. The remainder

of the tailings will report to a new Tailings Management Facility ( TMF) that has been designed to

international standards by Knight Piésold. The TMF capacity is sufficient for LOM production for both

scenarios. Further TMF expansion options are available should the LOM continue to grow with future

mine extensions.

Copper Marketing & Concentrate

Ocean Partners UK Ltd. ( OP) were engaged to provide specialist marketing advice regarding

maximising value generated by the Green Bay concentrate.

ASX | TSX: FFM

Page | 6

For the 1.8Mtpa (4,800tpd) base case the Project is expected to produce 3,723kt of copper

concentrate (dry) that equates to ~132kt per annum over the LOM. Based on concentrate test work,

the projected average concentrate grades are 24.5% Copper, 6g/t gold and 54g/t silver.

A portion of the gold is captured in the cleaner flotation pyrite tail and leached on-site. Gold grades

are locally higher early in the mine plan and correlate with VMS mill feed.

The concentrate is regarded as a clean, medium-grade copper-gold concentrate.

OP forecast a strong market for the high-quality concentrate produced by Green Bay. With

smelting capacity currently exceeding mine su pply, OP see negative treatment and refining

charges (TCRC) continuing to at least 2030 and costs remaining below US$30/dmt until 2036.

OP note that the proximity of Newfoundland an d Labrador to European shipping routes and

Canadian smelters make these facilities the logi cal options for maximising concentrate value.

However, the Company will continue to engage wi th Asian trading groups who remain keen to

secure the concentrate.

The Company has not committed to any offtake agreements and is considering potential pre-

payments as a non-dilutive funding opportunity.

Resource Growth

The Ming Deposit August 2026 MRE (Table 1) was prepared in accordance with the JORC Code (2012

Edition) and NI 43-101 by independent consultants, WSP Canada Inc.

The combined MRE (Table 3) for the Green Bay project has grown to 60.2Mt @ 2.4% CuEq in M&I

and 23.5Mt @ 2.5% CuEq in Inferred. All additions come from the Ming Deposit with no change to

the Little Deer MRE (Table 2).

The Ming Deposit Mineral Resource has grown to 57.3Mt @ 2.4% CuEq in M&I and 17.3Mt @ 2.8%

CuEq in Inferred. Infill drilling completed at Ming resulted in the M&I increasing by 21% since the

previous updates. Copper equivalent grade also increased by 22% driven primarily by infill drilling

of the high-grade core and high-grade VMS zones.

The high-grade core and VMS now totals 18.1Mt @ 4.3% CuEq in M&I plus 7.0Mt @ 4.4% CuEq in

Inferred. This zone drives the high production years in the mine schedule and remains open with

the deepest hole into the deposit intersecting 49.0m @ 6.1% CuEq.

Ming Deposit Mineral Resource Estimate

MING

DEPOSIT

TONNES COPPER GOLD SILVER CuEq

(Mt) Grade Metal Grade Metal Grade Metal Grade

(%) (‘000 t) (g/t) (‘000 oz) (g/t) (‘000 oz) (%)

Measured 3.5 1.5 52 0.2 20 1.3 147 1.67

Indicated 53.8 1.9 1,041 0.5 878 4.5 7,707 2.49

TOTAL M&I 57.3 1.9 1,093 0.5 899 4.3 7,853 2.44

Inferred 17.3 2.0 344 0.7 404 6.3 3,522 2.77

Table 1: August 2026 Mineral Resource Estimate for the Ming Deposit.

Commented [DC1R2]: This is correct

Commented [LN1]: @Darren Cooke please check this is

correct

ASX | TSX: FFM

Page | 7

Little Deer Mineral Resource Estimate

LITTLE DEER

TONNES COPPER GOLD SILVER CuEq

(Mt) Grade Metal Grade Metal Grade Metal Grade

(%) (‘000 t) (g/t) (‘000 oz) (g/t) (‘000 oz) (%)

Measured - - - - - - - -

Indicated 2.9 2.1 62 0.1 9 3.4 320 2.3

TOTAL M&I 2.9 2.1 62 0.1 9 3.4 320 2.3

Inferred 6.2 1.8 110 0.1 10 2.2 430 1.8

Table 2: Little Deer Mineral Resource Estimate as at November 2025. Note that this MRE remains unchanged from the

previous MRE.

GREEN BAY TOTAL MINERAL RESOURCE ESTIMATE

GREEN BAY TONNES COPPER GOLD SILVER CuEq

TOTAL MRE (Mt) Grade Metal Grade Metal Grade Metal Grade

(%) (‘000 t) (g/t) (‘000 oz) (g/t) (‘000 oz) (%)

Measured 3.5 1.5 52 0.2 20 1.3 147 1.67

Indicated 56.7 1.9 1,103 0.5 887 4.4 8,027 2.48

TOTAL M&I 60.2 1.9 1,155 0.5 908 4.2 8,173 2.43

Inferred 23.5 1.9 454 0.6 414 5.2 3,952 2.51

Table 3: Green Bay total Mineral Resource Estimate.

1. FireFly Metals Ltd Mineral Resource Estimates for the Green Bay Copper-Gold Project, incorporating the Ming Deposit

and Little Deer Complex, are prepared and reported in accordance with the JORC Code 2012 and NI 43-101.

2. Mineral Resources have been reported at a 1.0% copper cut-off grade.

3. Metal equivalents for the Mineral Resource Estimates have been calculated at a copper price of US$10,626/t, gold price

of US$3,587/oz and silver price of US$50.22/oz. Metallurgi cal recoveries have been set at 95% for copper and 85% for

both gold and silver. These assumptions are made of the basis of historical production at the Ming Mine and additional

metallurgical test work. Copper equivalent was calculated based on the formula: CuEq(%) = Cu(%) + (Au(g/t) x

0.97106) + (Ag(g/t) x 0.01360).

4. Totals may vary due to rounding.

Ongoing Resource Growth and Regional Discovery Exploration

Growth and exploration remain a pivotal compon ent of the FireFly strategy at Green Bay.

Extensions and discoveries of additional high-grade VMS mineralisation have the potential to have

a material positive impact on the mine plans outlined in the PEA (Figure 1). Six underground drill rigs

will remain underground focusing on step out hi gh-grade VMS growth, infill for high grade M&I

resource conversion as well as down plunge extensions and potential shallow up dip extensions.

The Company anticipates releasing its maiden Ore Reserve estimate with its next Mineral Resource

Estimate update which, along with the DFS, the Company plans to complete in Q1 2027.

In addition, the Company is currently drill testing several high-priority shallow historical VMS

copper and gold mines that sit within 5km of th e Ming Mine. It is anticipated that a maiden

Resource will be established on the first target prior to the Q1 DFS.

ASX | TSX: FFM

Page | 8

Furthermore, surface exploration will continue wi th three rigs on surface exploring the numerous

geochemical and geophysical targets generated since acquisition across the Ming district,

Rambler regional, Tilt Cove regional and Little Deer regional areas.

Environmental, Community and Early Works

As previously announced, the Company has satisfied the initial conditions of Environmental

Assessment ( EA) for the 1.8Mtpa base case which is a si gnificant regulatory milestone in the

Canadian permitting framework and should accomm odate a faster route to first production.

Regulatory approval has been received to commence select early works prior to FID. This includes

seasonal works, camp construction and other critical surface infrastructure upgrades. All permits

required for full construction are expected before the end of Q2 2027.

The commencement of early works in addition to utilising current funds to secure select long-lead

time items is expected to fast track the construc tion timeframe, with first concentrate production

anticipated to be in mid-2029.

The Company has received strong support from the Province of Newfoundland and Labrador and

the Federal Canadian government who have recognised the importance of critical minerals to the

supply chain and broader economy. The cond itional release from further Environmental

Assessment was granted in 45 days. To date, the Company has received approximately C$1 million

in grants from the Federal and Provincial gove rnments to accelerate studies and early-stage

exploration. Further funding applications have be en submitted to the Can adian Critical Minerals

Infrastructure Fund now subsumed by the expande d mandate of the federal First and Last Mile

Fund.

The local community is aligned with the Company’s mine start up strategy, as demonstrated by

the overwhelmingly positive response during the consultation process for the Environmental

Assessment. There are many advantages to operating in the Baie Verte district, including low-cost

hydro-electric power, port access, sealed roads and a nearby skilled workforce.

Project Funding

Given the high quality of the Green Bay Copper Gold Project and the strong technical and

economic fundamentals underpinning the 1.8Mtpa base case operation, the Project’s debt carrying

capacity is considered to be high.

FireFly has appointed BurnVoir Corporate Finance Limited ( Burnvoir) as its project debt advisor

and they have provided initial advice that, based on the 1.8Mtpa base case, the Project has an

indicative debt carrying capacity in excess of US$350 million (A$500 million).9

With A$183.4 million 10 o f e x i s t i n g c a s h r e s e r v e s a n d l i q u i d investments, anticipated proceeds of

A$180 million (before costs) from the equity ra ising announced by the Company on 25 August

202611 and up to A$10 million from the Share Purchase Plan (before costs), and initial advice that

the debt carrying capacity of the 1.8Mtpa base case scenario could support debt of in excess of

9 Based on a rate of 1 AUD = 0.7 USD.

10 Refer to note 1.

11 Refer ASX announcement on 25 August 2026.

Commented [DC2R2]: Yes that wording may be beƩer. I

will update. For the record, we do have a leƩer from the

Minister saying we have been released original condiƟons

but are waiƟng on the government to install their own

monitoring

Commented [LN2]: @Darren Cooke we go on to say on

page 33 that two condiƟons remain to be saƟsfied - should

we modify this statement to say 'the majority' or the

'condiƟons required to be saƟsfied to commence early

works'?