Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

FF.TO ·

First Mining Announces Positive Updated Preliminary Economic Assessment for the Springpole Gold Project Pre-Tax NPV5% of US$1.23 billion, Pre-Tax IRR of 26% and AISC of US$552/oz Average Annual Gold Production of 410,000 ounces in Years 2 through 9

Economic Studies Production Results

TSX: FF

OTCQX: FFMGF

FRANKFURT: FMG

- 1 -

NEWS RELEASE

First Mining Announces Positive Updated Preliminary Economic

Assessment for the Springpole Gold Project

Pre-Tax NPV5% of US$1.23 billion, Pre-Tax IRR of 26% and AISC of US$552/oz

Average Annual Gold Production of 410,000 ounces in Years 2 through 9

This news release constitutes a “designated news release” for the purposes of First Mining Gold’s prospectus

supplement dated August 19, 2019 to its short form base shelf prospectus dated June 24, 2019.

October 16, 2019 – Vancouver, BC – First Mining Gold Corp. (“First Mining” or the “Company”) (TSX: FF)

(OTCQX: FFMGF) (FRANKFURT: FMG) is pleased to announce the positive results of an updated

independent Preliminary Economic Assessment (“PEA”) completed for its 100% -owned Springpole Gold

Project (the “Project”) located in northwestern Ontario, Canada. The PEA contemplates an open pit mine

and milling operation and reflects updated metallurgical testwork that has demonstrated the potential

for significantly improved recoveries. The PEA also reflects updated operating and capital cost estimates.

PEA Highlights

• $1.23 billion pre-tax net present value discounted at 5% (“NPV5%”) ($1.75 billion at $1,500/oz gold)

• $841 million after-tax NPV5% ($1.22 billion at $1,500/oz gold)

• 26% pre -tax internal rate of return (“IRR”) (33% at $1,500/oz gold), 22% after-tax IRR (28% at

$1,500/oz gold)

• Mine life of 12 years with a 2.5-year pre-production period

• Average annual gold produc tion in years 2 through 9 of 41 0,000 ounces gold and 2.4 million ounces

silver; 3.9 million ounces gold and 22 million ounces silver recovered over the Life of Mine (“LOM”)

• Low LOM strip ratio of 2.1 to 1 with a LOM mill grade of 1.0 g/t gold and 5.3 g/t silver

• LOM overall metal recoveries of 88% for gold and 93% for silver

• LOM direct operating cash costs (1) estimated at $575/oz of gold equivalent ($514/oz of gold on a by-

product basis)

• LOM all-in sustaining costs (AISC) (2) estimated at $611/oz of gold equivalent ($552/oz of gold on a by-

product basis)

• Initial capital costs estimated at $809 million, using an owner-operated mining scenario

• LOM sustaining capital costs estimated at $124 million, plus $26 million for closure costs

Note: Base case parameters assume a gold price of $1,300/oz and a silver price of $20/oz (the same prices used in the 2017 PEA),

and an exchange rate (C$ to US$) of 0.75. All currencies are reported in U.S. dollars unless otherwise specified. NPV calculated as

of the commencement of construction and excludes all pre-construction costs.

(1) Cash costs consist of mining costs, processing costs, mine-level G&A, treatment and refining charges and royalties.

(2) AISC consists of cash costs plus sustaining and closure costs.

“This updated PEA is an important step forward as we continue to advance and de-risk the Springpole

Gold Project,” stated Dan Wilton, CEO of First Mining. “ The updated PEA incorporates the potential for

improved gold and silver recoveries as a result of the updated metallurgical results that we announced in

February 2019. It reinforces the potential for the Springpole Gold Project to become one of Ca nada’s

largest gold mines when in production, with average annual gold production in excess of 400,000 ounces

between year 2 and year 9, with a very attractive operating cost profile. The results demonstrate a robust

TSX: FF

OTCQX: FFMGF

FRANKFURT: FMG

- 2 -

project, with further opportunity to improve on the economics through the optimization studies that will

be completed as we advance the Project through a Pre-Feasibility Study.”

This updated PEA for the Springpole Gold Project was prepared by SRK Consulting (Canada) Inc. (“SRK”)

of Vancouver, Canada, in accordance with National Instrument 43-101 Standards of Disclosure for Mineral

Projects (“NI 43-101”), and a technical report for the PEA will be filed by the Company on SEDAR within

45 days of this news release.

Readers are cautioned that the PEA is preliminary in nature and includes I nferred mineral resources that

are too speculative geologically to have economic considerations applied to them that would enable them

to be categorized as mineral reserves. There is no certainty tha t PEA results will be realized. Mineral

resources are not mineral reserves and do not have demonstrated economic viability.

PEA Overview

The Springpole Gold Project, located in northwestern Ontario, Canada, is one of the largest undeveloped

open pit gold projects in North America. The Project is located approximately 110 kilometres northeast of

the town of Red Lake.

The PEA update evaluates recovery of gold and silver from a 36,000 tonne -per-day (“tpd ”) open pit

operation, with a process plant that includes crushing, grinding, flotation, with fine grinding of the

flotation concentrate and agitated leaching of both the flotation concentrate and the flotation tails

followed by a carbon-in-pulp recovery process to produce doré bullion.

Important parameters of the updated PEA are presented in the following table.

Key Assumptions

Base Case Commodity Prices $1,300/oz Au, $20/oz Ag

Exchange Rate (C$ to US$) 0.75

Production Profile

Total Tonnes Processed (mt) 138.5

Total Tonnes Waste (mt) 319.0

Mill Grade - Gold, Silver 1.00 g/t Au, 5.28 g/t Ag

Mine Life 12 years

Throughput (tonnes per day) 36,000 tpd

Strip Ratio (waste:ore) 2.1 : 1

Overall Recovery - Gold, Silver 88% Au, 93% Ag

LOM Metal Recovered - Gold, Silver 3.9 mozs Au, 21.9 mozs Ag

Average Annual Production - Gold, Silver (Years 1 - 11) 356 kozs Au, 2.0 mozs Ag

Peak Production in Year 5 - Gold, Silver 529 kozs Au, 2.9 mozs Ag

Average Annual Production Years 2 to 9 - Gold, Silver 410 kozs Au, 2.4 mozs Ag

TSX: FF

OTCQX: FFMGF

FRANKFURT: FMG

- 3 -

Unit Operating Costs (1)

LOM Average Cash Cost (2) $575/oz gold eq., $514/oz gold (by-product)

LOM Cash Cost plus Sustaining Cost (AISC) (3) $611/oz gold eq., $552/oz gold (by-product)

Project Economics - $1,300/oz Gold Price

NPV5% - Pre-Tax, After-Tax $1.23 billion, $841 million

IRR - Pre-Tax, After-Tax 26%, 22%

Payback Period from Production Date 3.4 years

LOM Cash Flow - Pre-Tax, After-Tax $2.10 billion, $1.49 billion

Project Economics - $1,500/oz Gold Price

NPV5% - Pre-Tax, After-Tax $1.75 billion, $1.22 billion

IRR - Pre-Tax, After-Tax 33%, 28%

Payback Period from Production Date 2.9 years

LOM Cash Flow - Pre-Tax, After-Tax $2.88 billion, $2.05 billion

(1) All unit operating costs are shown on both equivalent as well as net of silver by-product credits

(2) Cash costs consist of mining costs, processing costs, mine-level G&A, treatment and refining charges and royalties

(3) AISC includes cash costs plus sustaining capital and closure costs

Economic Sensitivities

The Project economics and cash flows are highly sensitive to changes in the price of gold.

Springpole Economic Sensitivity to Gold Price

Gold Price (US$/oz) $1,200 $1,300 $1,400 $1,500

Pre-Tax NPV5% $972 million $1.23 billion $1.49 billion $1.75 billion

Pre-Tax IRR 23% 26% 30% 33%

After-Tax NPV5% $652 million $841 million $1.03 billion $1.22 billion

After-Tax IRR 19% 22% 25% 28%

Springpole Economic Sensitivity to Capital Costs

Initial Capital Costs +10% $809 million -10%

Pre-Tax NPV5% $1.15 billion $1.23 billion $1.32 billion

Pre-Tax IRR 24% 26% 29%

After-Tax NPV5% $773 million $841 million $909 million

After-Tax IRR 19% 22% 24%

TSX: FF

OTCQX: FFMGF

FRANKFURT: FMG

- 4 -

Springpole Economic Sensitivity to Operating Costs

Operating Costs +10% $2.36 billion -10%

Pre-Tax NPV5% $1.07 billion $1.23 billion $1.39 billion

Pre-Tax IRR 24% 26% 28%

After-Tax NPV5% $726 million $841 million $956 million

After-Tax IRR 20% 22% 24%

Mineral Processing and Metallurgical Testing

The updated PEA reflects higher recoveries for both gold and silver that were a result of the updated

metallurgical testwork completed in 201 8 and 201 9. First Mining contracted M3 Engineering and

Technology Corporation ( “M3”), with input from First Majestic Silver Corp.’s metallurgical team, to

manage a metallurgical testwork program to improve the gold an d silver recoveries and to define the

process flowsheet.

Based on the testwork carried out, a flowsheet that includes flotation followed by leaching of reground

concentrate and combined (rougher plus cleaner) tails presents as the more beneficial processing route

for the Project. This flowsheet is based on a primary grind of P 80 150 microns (“µm”) ahead of flotation,

with a cleaner flotation concentrate being re ground to ~17 µm ahead of agitated leaching. Under these

conditions, overall extractions achieved were 9 1% for gold and 9 6% for silver . When accounting for

carbon-in-pulp, carbon stripping and electrowinning circuit losses, the overall recoveries expected and

used for the economics presented in the PEA are 88% for gold and 93% for silver.

A proposed flowsheet for processing can be viewed at the following link:

https://www.firstmininggold.com/_resources/maps/2019-10-PEA-Process-Flow-Sheet.pdf

Capital Costs

The capital cost estimate for the proposed open pit operation is based on the scheduled plant throughput

rates, as well as a review of similar sized open pit gold operations.

Capital Cost Estimate Details

Initial Capital Cost Initial ($M) Sustaining ($M) LOM ($M)

Open Pit Mining $149 $52 $201

Processing $519 $6 $525

Infrastructure $38 - $38

Dike and Lake Dewatering (1) $29 - $29

Tailings Management Facility $74 $67 $141

Closure - $26 $26

Total $809 $150 $959

(1) Includes water management

TSX: FF

OTCQX: FFMGF

FRANKFURT: FMG

- 5 -

Mining Capital Costs

The open pit mining activities for the Project were assumed to be undertaken by an owner-operated fleet.

Mining capital costs were estimated based on a detailed equipment schedule matched to the mining

production schedule. Total initial mining equipment capital was estimated at $149 million for the life of

the project, inclusive of a 10% contingency and a 5% spares allowance.

Processing Capital Costs

Capital costs for the processing facility were estimated to be $519 million, inclusive of a $104 million

contingency. No major plant re-build or expansion was considered during the LOM, with sustaining capital

set to maintain the equipment in operating condition. No allowance for salvage value was made.

Site Infrastructure

An overall site plan for the Project can be viewed at the following link:

https://www.firstmininggold.com/_resources/maps/2019-10-PEA-Site-Layout.pdf

Springpole Lake Dewatering

The deposit sits underneath a small portion of the northern bay of Springpole Lake. Three dewatering

dikes (coffer dams), with a total length of approximately 510 metres, will need to be constructed to allow

this small portion of Springpole Lake to be dewatered. The coffer dams will have a height of 3 metres

above the waterline. The small area proposed to be dammed and dewatered totals 152 hectares and

represents approximately 6% of the entire surface area of the lake (and approximately 3% of the volume).

A map showing the portion of the lake proposed to be dammed and dewatered within the entire area of

Springpole Lake can be viewed at the following link:

https://www.firstmininggold.com/_resources/maps/2019-10-PEA-Springpole-Lake.pdf

Tailings Management Facility

The tailings management facility (“TMF”) has been relocated in the updated PEA to reduce the footprint

and haulage costs. It has also been designed to spread the required costs over the LOM . The TMF will be

located immediately west of the pit, and in the initial stages will occupy a smaller footprint to reduce the

construction period and to minimize the initial capital requirement. The TMF will be constructed with a

synthetic liner over the entire footprint to prevent exfiltration of contact water, and the dams will be

raised as needed as a measure to spread out the sustaining capital. The dams will be constructed using

waste rock that will be hauled directly from the pit.

Roads

The PEA contemplates a 12-metre-wide, two-lane unpaved, 39-kilometre access corridor road that would

extend from the Project to the existing Wenasaga Road , a Class 1 Forest Road that connects to the

provincial highway system near Ear Falls, Ontario. Alternative corridors for the access road will be further

assessed through trade-off studies as part of the Pre-Feasibility Study work for the Project.

TSX: FF

OTCQX: FFMGF

FRANKFURT: FMG

- 6 -

Power Infrastructure

It is anticipated that Springpole will be connected to the power grid via a 115 kV power line extending

along the planned road corridor. The electricity transmission infrastructure in the area is undergoing a

significant upgrade by Wataynikaneyap Power Inc. , who are in the process of building a new 230kV

transmission line to Pickle Lake. A direct connection to the new transmission line will be assessed through

trade-off studies as part of the Pre-Feasibility Study.

Operating Costs

Overall operating costs LOM, as well as on a unit cost, are summarized below.

Operating Costs LOM ($M) $/tonne milled $/oz AuEq.

Mining $763 $5.50 $180

Processing (1) $1,350 $9.75 $318

On-Site G&A $247 $1.78 $58

Total Operating Cost $2,360 $17.03 $556

Treatment & Refining Charges $4 n/a $1

Royalty $75 n/a $18

Cash Costs $2,439 n/a $575

Sustaining Capital (2) $150 n/a $35

All-in Sustaining Costs (AISC) $2,589 n/a $611

Note: $/oz AuEq. represent total revenue from payable metal divided by gold price

(1) Includes processing, TMF Opex and water management costs

(2) Includes closure capital

Operating Cost Estimate Details

Mining Costs

The PEA contemplates open pit mining undertaken by an owner -operated fleet. An average unit mining

cost of $1.74 per tonne of material mined was used in the economics. The cost estimate was built from

first principles and based on experience of similar sized open pit operations and local conditions. The open

pit mining costs consider variations in haulage profiles and equipment selection.

Processing Costs

An average cost of $9.71 per tonne of processed material was used in the PEA, based on the updated

process flowsheet. This i ncludes tailings handling, labour, consumables, maintenance and supplies. A

power cost of $0.08/kWh was assumed. An additional $0.04 per tonne of processed material was used in

the PEA for TMF Opex and water management costs.

TSX: FF

OTCQX: FFMGF

FRANKFURT: FMG

- 7 -

Mineral Resources

The mineral resources and resource methodology for the Project has not changed from the prior PEA. The

mineral resources stated in the PEA were prepared on March 15, 2017 and have been restated with this

updated PEA (with an effective date of September 1, 2019).

Category Tonnes

(Mt)

Grade

Au (g/t)

Grade

Ag (g/t)

Contained Metal

Au (mozs)

Contained Metal

Ag (mozs)

Indicated 139.1 1.04 5.4 4.67 24.19

Inferred 11.4 0.63 3.1 0.23 1.12

Source: Based on the technical report titled “Preliminary Economic Assessment Update for the Springpole Gold Project, Ontario, Canada”, prepared

by SRK Consulting (Canada) Inc. and dated September 1, 2019

*Mineral resources are reported in relation to a conceptual pit shell. Mineral resources are not mineral reserves and do not have demonstrated

economic viability. All figures are rounded to reflect the relative accuracy of the estimate. All composites have been capped where appropriate.

**Open pit mineral resources are reported at a COG of 0.4 g/t gold. COGs are based on a gold price of $1,400/oz and a gold processing recovery

of 80% and a silver price of $15/oz and a silver processing recovery of 60%.

The current mineral resource model prepared by SRK used 401 core boreholes drilled by previous owners

of the property during the period of 2003 to 2013 . Drilling subsequent to 2016 was completed by First

Mining for metallurgical and geotechnical purposes and hence did not affect the mineral resource. The

Project currently consists of three separate mineralized zones: East Extension, Camp (also known as Main)

and Portage. The Portage zone is by far the largest of the three and represents more than 90% of the

stated mineral resource. There is potential for further explo ration upside along strike from the Portage

zone in the Springpole Lake area, as well as within the broader Springpole land package. Other targets on

the property include Satterly Lake and Horseshoe Island which have undergone drilling by previous

operators and may warrant further follow-up exploration in the future.

Over 95% of the contained gold in the resource is classified as Indicated. First Mining does not anticipate

requiring any further drilling to convert the remaining Inferred resources in prepara tion for a Pre -

Feasibility level assessment.

Production Schedule and Mine Plan

Mining would occur as a series of open pits with a maximum depth of approximately 400 metres. The

deposit is planned to produce a total of 139 Mt of plant process feed and 319 Mt of waste (2.1:1 overall

strip ratio) over a twelve-year mine operating life. The current LOM plan focuses on achieving consistent

processing feed production rates, mining of higher -grade material early in the schedule and balancing

grade and strip ratios.

A summary of the production schedule can be viewed at the following link:

https://www.firstmininggold.com/_resources/maps/2019-10-PEA-Production-Schedule.pdf

Project Enhancement Opportunities

The PEA identified a number of opportunities to enhance the project economics which will be investigated

as First Mining continues to advance the Springpole Gold Project. These parameters include:

• Mine Plan Optimization. Refined pit optimization parameters could result in better optimi zed open

pit limits which could reduce the overall strip rate.

TSX: FF

OTCQX: FFMGF

FRANKFURT: FMG

- 8 -

• Further Metallurgical Testing. Continued efforts to investigate opportunities to improve the

recoveries through further metallurgical testing and refining milling processes.

• Geotechnical Studie s. A better hydrogeological and geotechnical understanding may increase pit

slope angles, potentially reducing costs associated with mining waste material.

• Resource Expansion. There are other geophysical targets around the current resource where

additional drilling has the potential to add resources, which has the potential to extend the LOM.

Recommended Work

The PEA recommends that First Mining advance the Springpole Gold Project to a Pre -Feasibility Study.

Activities involved in advancing the project include additional metallurgical testwork, advanced

hydrogeological and geotechnical characteri zation, permitting and continued baseline environmental

studies. A number of these studies are ongoing right now as part of the data collection in suppor t of the

completion of an Environmental Impact Statement (“EIS”) for the Project.

Permitting and Environmental Baseline Data

First Mining has been actively collecting environmental baseline data necessary to support an

Environmental Assessment (“EA”) for the Springpole Gold Project since 2010. The studies, both completed

and ongoing, are focused on characterizing all relevant biological and physical components of the aquatic

and terrestrial environments that may be impacted by and may interact with the Project. The designs of

most of these programs were also vetted by representatives of the I ndigenous groups expressing an

interest in the project in order to ensure their valued components are consistent with those targeted in

the baseline studies. The databases compiled to date within these programs exceeds the level of

environmental baseline data one would typically have in support of a Preliminary Economic Assessment.

First Mining continues to advance the Project through the provincial and federal permitting process. The

Springpole Gold Project is subject to both provincial and federal EA processes. The goal is to prepare a

synchronized EIS that meets the f ederal and provincial requirements. Community consultation and

engagement with various stakeholders is ongoing with a number of consultation meetings taking place

with Indigenous communities and other stakeholders. The Company is now in its second round of

consultations in readiness for the preparation of the Terms of Reference and EIS preparation.

Qualified Persons and NI 43-101 Technical Report

The updated PEA for the Springpole Gold Project summarized in this news release was completed by SRK

and will be incorporated in a NI 43 -101 technical report which will be available under the Company’s

SEDAR profile at www.sedar.com, and on the Company’s website, within 45 days of this news release. The

compilation of the technical report was completed by Dr. Gilles Arseneau (SRK), Ph.D., P.Geo. - Qualified

Person for M ineral Resource Evaluation; Mr. Neil Winkelmann (SRK), FAusIMM - Qualified Person for

Economic Analysis; Mr. Grant Carlson (SRK), P.Eng. - Qualified Person for Open Pit Mine Engineering; Bruce

Andrew Murphy (SRK), P.Eng. - Qualified Person for Open Pit Geotechnical Aspects; Mark Liskowich (SRK),

P.Geo. - Qualified Person for Environmental and Social Aspects; Mauricio Herrera (SRK), Ph.D., P.Eng. -

Qualified Person for Hydrology; Michael Royle (SRK), M.App.Sci., P.Geo - Qualified Person for

Hydrogeology; Michel Noël (SRK), P.Eng. - Qualified Person for Tailings and Coffer Dams; Ms. Laurie Tahija

(M3), MMSA -OP - Qualified Person for Mineral Processing and Recovery Methods . By virtue of their

education, membership to a recognized professional association and relevant work experience, Dr.