Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

EXG.V ·

Exgen: Empire MINE Project Update

Corporate Updates

NEWS RELEASE

NOT FOR DISTRIBUTION TO UNITED STATES NEWSWIRE SERVICES OR FOR

DISSEMINATION IN THE UNITED STATES

FOR IMMEDIATE RELEASE – AUGUST 24, 2023

EXGEN: EMPIRE MINE PROJECT UPDATE

VANCOUVER, British Columbia, August 24, 2023 -- ExGen Resources Inc. (TSX.V: EXG; OTC: BXXRF) (“ExGen”,

the “Company”) is pleased to provide an update in respect of Phoenix Copper Ltd.’s (“Phoenix”)

exploration and development activities at the Empire Mine Project in Custer County, Idaho, USA. Further

to previous ExGen news releases, ExGen owns 20% and Phoenix owns 80% of Konnex Resources, Inc.

(“Konnex”), which holds the leases and claims to the Empire Mine Project. ExGen further owns

1,330,000 common shares of Phoenix.

Directors of ExGen conducted a site visit of the Empire Project on July 17th – 19th in the company of

Ryan McDermott, CEO of Phoenix Copper, to appraise progress on the project. ExGen was pleased to

note significant progress in metallurgical testing of ATS, an environmentally friendly agent, on

mineralization from the Empire Mine open pit which may allow the recovery and processing of copper,

gold and silver in one process. Testing is ongoing. ExGen is also excited that drilling has started on the

Navarre Creek prospect – 60 holes are planned. This large claim block (14.48 km² (3,577 acres))

represents over 6 kms of prospective strike length, including an area of secondary alteration thought to

be epithermal in nature, with over 2.5 kms of highly brecciated, west-trending jasperoid intersecting

argillically and silicically altered Eocene Challis volcanics. The drilling, with success, has the potential to

be a major game-changer for the project.

Jason Riley, CEO of ExGen commented: “ExGen is excited about this maiden drill program at Navarre Creek.

The project has the potential to be a true company maker and we eagerly await future progress updates and

assay results.”

EMPIRE MINE

As reported by Phoenix on June 6, 2023, preliminary metallurgical testing of the Empire Mine open pit

oxide material using ammonium thiosulfate ("ATS") as a reagent, has been completed by Resource

Development Inc of Wheat Ridge, Colorado ("RDI"), and has resulted in robust metallurgical recoveries

of copper, gold and silver using representative bulk samples of mineralization from metallurgical drilling

at the Empire Mine open pit oxide deposit. ATS is considered an environmentally friendly reagent,

intended to replace the use of sulphuric acid and cyanide in the recovery and processing of copper and

precious metals respectively. In addition to positive environmental impacts, this technology would

enable recovery and processing copper, gold and silver in one proces, thus bringing forward the

production of precious metals from the Empire Mine open pit. ATS is produced and sold in bulk in Idaho

and is commonly used as a fertilizer for the agricultural sector. The current focus is on optimizing metal

recovery balanced with reagent consumption and applying appropriate capital and operating costs to

the proposed process design. Assuming the process is commercially viable, Phoenix would plan to

formally incorporate it into its Plan of Operations for final submission to the regulatory authorities.

ExGen looks forward to receiving additional results from the ATS metallurgical program.

NAVARRE CREEK

ExGen is pleased that reverse circulation drilling (RCD) has commenced on the Navarre Creek exploration

project located 5 kms west of the Empire Mine site (Phoenix News Release of July 17,2023). Up to 60 RCD

holes form 30 drill pads are planned. Drill targets were identified by Phoenix from geologic mapping,

surface geochemistry, airborne hyperspectral mineral imaging, and geomagnetic ground surveys. Phoenix

considers that the Navarre Creek area exhibits geological traits consistent with hydrothermal precious

metal deposition common in volcanic terrains in the Western United States. The Navarre Creek project is

located within an intrusive dome complex, where the magnetic components in overlying volcanic

lithologies are destroyed by silicic alteration associated with steam -heated, acidic, and oxidised

hydrothermal fluids. The hyperspectral survey highlighted several such areas including the Lehman

Creek fault, one or more porphyry plugs, and several contacts/faults. Prospecting samples with a gold

value greater than 0.1 g/t (2020 sampling) occur predominantly in a jasperoid-hosted quartz stockwork

and micro -veining system in felsic volcanic tuff units . Volcanics outcropping across the Navarre

Creek area are strongly weathered and highly leached to depths of two to four meters.

A magnetite skarn sample from the southern end of the claim block contained 0.387 g/t gold and the

presence of limestone in surface float near the skarn sample location is evidence that the Paleozoic

sedimentary rocks that occur at the Empire Mine may be near the surface. The Empire orebody is partly

comprised of a magnetite skarn body hosted in Paleozoic limestone.

RED STAR

On April 12, 2023 Phoenix press released the results of 268 meters (‘m’) of reverse circulation drilling

completed in late 2022 on the Red Star prospect to provide samples and technical information for

geological and resource modeling. Significant drill results are listed in Table 1.

Phoenix noted:

➢ Holes RS22 -02 and RS22 -04 show robust metal values consistent with the results of previous

drilling in the area. Hole RS22 -02 includes 1.52 m grading 1.01 g/t of gold, 332 g/t silver, 1.35%

copper, 2.18% lead, 1.39% zinc and 156 ppm molybdenum. Hole RS22 -04 also returned robust

metal values, including 4.99 1.52 m of 7.59 g/t gold and 0.58% copper.

➢ Only 268 m of drilling was completed due to the limited availability of the drill rig, nonetheless,

the data and results have added significantly to our understanding of the mineralization and the

boundaries of the magnetic anomalies and will aid in future drilling, modeling and ultimately

updating of the resource.

➢ The drilling results seen thus far in the Red Star area are indicative of higher -grade, narrow vein

mineralization which may best lend itself to underground mining methods. Conversely, the longer

and lower grade drilling intercepts in the Empire open pit area lend themselves to bulk tonnage,

open pit mining methods. The close proximity of both styles of mineralization speaks volumes

about the potential size and complexity of the Empire system.”

Table 1 – Red Star Drilling Results

Drill Hole Intersection Meters g/tonnes % % % ppm ppm

Number From To Interval* Au Ag Cu Pb Zn Mo W

RS22-

01** 30.48 32 1.52 0.05 19.9 0.02 1.44 0.07 565 20

RS22-

02*** 32 39.62 7.62 0.42 142.7 0.36 2.94 1.54 74.6 52

including 33.53 35.05 1.52 1.01 332 1.35 2.18 1.39 156 70

35.05 36.58 1.52 0.15 116 0.11 3.01 2.31 36 60

36.58 38.1 1.52 0.29 119 0.05 4.71 2.06 33 60

38.1 39.62 1.52 - 134 0.07 4.8 1.78 139 40

RS22-03 3.05 6.1 3.05 0.53 11.4 0.21 0.007 0.19 2 12.5

including 4.57 6.1 1.52 0.87 18 0.28 0.007 0.16 2 5

RS22-04 1.52 10.67 9.15 1.56 15.8 0.32 0.004 0.02 2.3 5

including 3.05 4.57 1.52 0.62 42.7 0.64 0.009 0.03 3 5

including 9.14 10.67 1.52 7.59 22.5 0.58 0.005 0.03 2 5

* Length along hole (not necessarily equivalent to true width).

**RS22-01 was terminated due to the hole collapsing. RS22-01A was collared and redrilled approximately 10 feet to the southwest

of the original hole. RS22-01A did not have any significant intervals to report.

***RS22-02 sample starting at 38.10 m did not have sufficient material for an Au assay after the completion of multi -element

digest and over limit assays.

EMPIRE MINE METALLURGICAL DRILLING

On March 16, 2023, Phoenix press released the results of 1,077 meters ('m') of a planned 1,500 m

metallurgical core drilling program on the Empire Mine open pit. The core drilling was completed

during 2022 to provide samples and technical information for further metallurgical testing,

geotechnical studies, and geological modeling. Significant drill results from the seventh, eighth and

ninth holes, the final three holes of the program, are presented on Table 2. The 2022 metallurgical

exploration program was designed to collect material from each of the metallurgical domains to

evaluate their variability within the Empire open pit while improving the understanding of the geologic

and structural controls on mineralization. The results confirmed the continuity of mineralization within

the Empire open pit, which appears along structures striking northeast and dipping steeply to the

southeast.

Phoenix noted:

➢ All of the core samples designated for metallurgical testing have now been shipped to the

metallurgical laboratory to complete the test program.

➢ The 2022 metallurgical drilling program targeted specific zones within the Empire resource, in

order to collect samples that are representative of the geology and grade characteristics of the

deposit as a whole. The samples will be used in the additional t esting of ammonium thiosulfate

as a recovery agent for copper, gold, and silver, which may enable us to bring forward the

production of gold and silver, currently scheduled as a second phase of the Empire Open Pit

project.

➢ Consistent with the copper, gold, and silver values previously reported for holes KXD22 -01

through KXD22-07, holes KXD22 -07B, KXD22-08, and KXD22 -09 continue to show robust metal

values. Hole KXD22-07B includes 24.38 m grading 1.99% copper and 107.4 g/t silver, including an

impressive 10.97 m averaging 3.94% copper and 214.5 g/t silver (including 1.1 m of 12.8% copper,

and 3.5 m averaging 2.06 g/t gold and 2.28% zinc). Holes KXD22 -08 and KXD22-09 also returned

robust values, including 8.84 m of 0.73% copper and 43.1 g/t silver, and 1.37 m of 1.63% copper

and 82.5 g/t silver, respectively.

➢ The intercepts in the drilling program thus far are consistent with the team's expectations and

meet the material type-grade-interval length necessary for the metallurgical test work currently

being undertaken. Intercepts cited do not necessarily represent true widths, unless otherwise

noted, however, drilling is generally intersecting interpreted mineralized zones at angles

between ±30°. True width determinations are not estimated due to the irregular shape of the

skarn mineralization.

Table 2 - Empire Mine Open Pit Core Drilling Results

Drill Hole Intersection Meters g/tonne % % % ppm ppm

Number From To Interval* Au Ag Cu Pb Zn Mo W

KXD22-07B 12.80 37.19 24.38 0.015 107.4 1.99 0.008 0.05 247 421

including 21.49 22.86 1.37 0.010 97 2.36 0.004 0.01 32 540

23.01 23.93 0.91 0.010 104 2.24 0.005 0.04 259 210

23.93 24.99 1.07 0.040 302 5.77 0.012 0.02 211 2840

24.99 25.76 0.76 0.010 136 2.79 0.006 0.01 118 530

25.76 26.67 0.91 0.100 476 10.00 0.031 0.01 211 1650

26.67 27.74 1.07 0.005 691 12.8 0.025 0.03 445 700

27.74 29.11 1.37 0.030 173 2.08 0.014 0.06 427 110

29.11 31.09 1.98 0.020 96.2 0.72 0.013 0.05 459 210

31.09 32.61 1.52 0.010 65.1 1.71 0.007 0.04 698 140

KXD22-07B 41.45 58.22 16.76 0.019 17.2 0.81 0.210 0.17 324 149

including 41.45 43.28 1.83 0.005 6.5 1.07 0.004 0.09 195 150

43.28 44.81 1.52 0.010 17.6 1.36 0.501 0.33 963 170

44.81 46.63 1.83 0.005 1.2 0.10 0.002 0.01 139 80

46.63 48.16 1.52 0.005 10.6 0.68 0.002 0.20 99 110

48.16 49.38 1.22 0.010 7.1 0.83 0.002 0.10 542 280

49.38 50.60 1.22 0.010 8.5 0.45 0.006 0.09 167 170

50.60 51.66 1.07 0.050 27.4 3.02 0.010 0.09 211 180

51.66 53.19 1.52 0.030 7 1.03 0.004 0.16 730 290

including 55.17 56.69 1.52 0.040 70.1 0.52 0.939 0.43 233 110

56.69 58.22 1.52 0.050 26.6 0.34 0.765 0.26 225 70

KXD22-07B 81.38 100.28 18.90 0.421 5.5 0.09 0.006 1.71 55 13

including 87.36 88.09 0.73 0.060 3.3 0.09 0.005 2.37 48 20

88.09 89.61 1.52 0.030 9.5 0.17 0.003 4.54 95 20

89.61 91.44 1.83 0.320 3.8 0.02 0.004 3.58 27 20

91.44 92.96 1.52 2.890 3.8 0.02 0.004 2.48 18 10

92.96 94.49 1.52 1.230 4.5 0.02 0.005 2.08 31 5

KXD22-08 17.68 26.52 8.84 0.032 43.1 0.73 0.004 0.03 100 204

including 17.68 18.75 1.07 0.130 205 3.52 0.010 0.04 230 130

18.75 19.96 1.22 0.060 87.5 1.28 0.009 0.03 80 50

KXD22-09 174.04 183.00 8.96 0.195 22.0 0.62 0.084 0.78 86 25

including 174.04 175.41 1.37 0.100 82.5 1.63 0.509 3.43 505 70

* Length along hole (not necessarily equivalent to true width).

** KXD22-07 was terminated in a historical mine working at 18.3 m. KXD22-07B was collared and redrilled the original hole

QUALITY ASSURANCE AND QUALITY CONTROL PROTOCOLS

Phoenix states that all RC chips are logged by Konnex personnel at Phoenix's drill core facility located in

Mackay, Idaho, USA. The RC chips are split at the drill rig. One half is sent to a commercial laboratory for

assaying, and the other half is kept for future reference. A strict QA/QC programme is in place by

integrating duplicates, blanks, and certified reference standards into the RC sample sequence.

QUALIFIED PERSON

Kieran Downes, Ph.D., P. Geo., a Qualified Person as defined by National Instrument 43-101, has reviewed

and verified the technical information provided in this release.

ABOUT EXGEN RESOURCES INC.

ExGen, formerly Boxxer Gold Corp, is a project accelerator that seeks to fund exploration and development of

our projects through joint ventures and partnership agreements. This approach significantly reduces the

technical and financial risks for ExGen, while maintaining the upside exposure to new discoveries and

potential cash flow. The company intends to build a diverse portfolio of projects across exploration stages and

various commodity groups. ExGen currently has 5 projects in Canada and the US.

For more information on ExGen please contact ExGen Resources Inc.

Jason Tong

Chief Financial Officer

Email: [email protected]

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the

policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this

release.

Forward-Looking Information: This news release contains certain forward-looking information. All statements included herein,

other than statements of historical fact, are forward -looking information and such information involves various risks and

uncertainties. There can be no assurance that such information will prove to be accurate, and actual results and future events could

differ materially from those anticipated in such information. In particular, this news release contains forward -looking information

in relation to: the observations made on drill core from the diamond drilling program on the Empire Mine Project; the further

exploration and development of the Empire Mine Project; the exploration and development strategy of the Empire Mine Project,

including the exploration program, drilling, mine development, and permitting. There can be no assurance that such information

will prove to be accurate, and actual results and future events could differ materially from those anticipated in such inform ation.

There can be no assurance that the development of the Empire Mine Project will be completed, and if development is completed,

that such development will result in a producing mine. In the forward looking information contained in this news release, ExG en

has made numerous assumptions, based upon practices and methodologies which are consistent with the mineral industry. In

addition, ExGen has assumed: the continued market acceptance of its joint venture partnership model; the ability of ExGen and its

partners to raise future equity financing, if needed, at prices acceptable to ExGen or its partners; ExGen's current and initial

understanding and analysis of the Empire Mine Project; the ability of ExGen or third parties to discover viable exploration targets

and the results of exploration on the Empire Mine Project; the ability of Phoenix to explore and develop the Empire Mine Project;

the cost of exploration, including sampling, drilling and assaying, on the Empire Mine Project, the costs of developing the Empire

Mine Project and the costs and the ability of Phoenix to produce a feasibility study in compliance with NI 43 -101; and ExGen's

general and administrative costs remaining sustainable. While, ExGen considers these assumptions to be reasonable, these

assumptions are inherently subject to significant uncertainties and contingencies. Additionally, there are known and unknown risk

factors which could cause ExGen's observations, actual results, performance or achievements to be materially different from a ny

future results, performance or achievements expressed or implied by the forward -looking information contained herein. Known

risk factors include, among others: the possibility that the analytical results from future core sampling does not return sig nificant

grades of copper, gold, silver, zinc, lead or any other molybdenum by -products; uncertainties relating to interpretation of drill

results and the geology; continuity and grade of mineralization; there is no certainty that the ongoing work programs will result in

significant or successful exploration of the Empire Mine Project or development of the Empire Mine Project into a producing mine;

uncertainty as to the actual results of exploration and development or operational activities; uncertainty as to the avail ability and

terms of future financing; uncertainty as to timely availability of permits and other governmental approvals; ExGen may not b e

able to comply with its ongoing obligations regarding its properties; the early stage development of ExGen and its projects, and in

particular, the Empire Mine Project; general business, economic, competitive, political and social uncertainties; capital mar ket

conditions and market prices for securities, junior market securities and mining exploration company securities; commodity prices,

in particular copper, gold, silver, and zinc prices; competition; changes in project parameters as plans continue to be refin ed;

accidents and other risks inherent in the mining industry; lack of insurance; delay or failure to receive board or regulatory approvals;

changes in legislation, including environmental legislation, affecting ExGen; conclusions of economic evaluations; and lack o f

qualified, skilled labour or loss of key individuals. A description of additional assumptions and ri sk factors used to develop such

forward-looking information that may cause actual results to differ materially from forward -looking information can be found in

ExGen's disclosure documents on the SEDAR website at www.sedar.com. Although ExGen has attempted to identify important

factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other

factors that cause results not to be as anticipated, estimated or intended. Accordingly, readers sho uld not place undue reliance on

forward-looking information. ExGen does not undertake to update any forward -looking information except in accordance with

applicable securities laws.