Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

EU.V ·

enCore Energy Provides Update on South Texas Uranium Operations

Corporate Updates

enCore Energy Provides Update on South Texas Uranium

Operations

NASDAQ:EU

TSXV:EU

www.encoreuranium.com

DALLAS

,

Jan. 17, 2024

/CNW/ -

enCore Energy Corp.

(NASDAQ: EU) (TSXV: EU) (the "

Company

" or "

enCore"

), a uranium

producer, today provides an update on the Company's

South Texas

operations which are advancing on schedule and providing

exceptional drilling results to support future planned production.

Highlights include:

The Alta Mesa In-Situ Recovery (ISR) Uranium Central Processing Plant (CPP) upgrades and refurbishments are advancing

on schedule for the planned early 2024 resumption of uranium production;

The Alta Mesa Project wellfield drilling is providing increasingly positive high-grade results from the wellfield delineation drill

program;

Uranium production from the Rosita CPP which commenced

November 21, 2023

, continues to meet projected start up

production levels. Additionally, the Grand Opening at the Rosita CPP is scheduled on-site for

February 6, 2024

.

Paul Goranson, enCore Energy's Chief Executive Officer, stated: "Our South Texas operations continue to advance on schedule

due to our successful planning to ensure all necessary supplies and equipment were secured well in advance of installation. With

a full complement of people, materials, and equipment in the field, we are well positioned to make our timelines at our second

production facility, Alta Mesa. Additionally, the wellfield drill results are some of the best grades we have encountered to date.

These results support our plan to accelerate and expand the drill program at the Alta Mesa Uranium Project."

To view the Alta Mesa CPP and Wellfield and Rosita CPP maps please visit:

bit.ly/3fV9fTg

.

Alta Mesa CPP Development Update

At the Alta Mesa CPP, enCore has met most of the key objectives for the refurbishment of the processing circuits necessary for

the planned early 2024 restart. Work remaining includes final inspection of the ion exchange columns, testing the precipitation

tanks, completing tie-in of the scrubber system, and installation and testing of the process circuit instrumentation. The

yellowcake drying circuit upgrades are advancing with the filter press support infrastructure on site. Refurbishment and testing

of the yellowcake drying system is progressing with that work scheduled to be completed just prior to the anticipated production

restart timelines.

Within Production Authorization Area 7 (PAA-7), enCore is installing injection and production wells in the wellfield, has completed

installation of the electrical transmission lines necessary for initial start-up and is continuing to install the pipelines to connect the

wellfield to the Alta Mesa CPP. All necessary equipment for the start-up of production in the PAA-7 wellfield has been received

or has been ordered with a confirmed delivery schedule.

Alta Mesa Wellfield Drilling Update

The wellfield drilling operations, delineating the roll front mineralization within PAA-7, which commenced in

March 2023

, are

advancing rapidly with 78 holes drilled since the previous update (

November 20, 2023

). In total, 445 drill holes have been

completed through

January 4

th

, 2024. There are currently six (6) drill rigs in full operation at the Alta Mesa CPP and Wellfield,

with contracts pending for three (3) additional rigs.

Further refined delineation drilling within the PAA-7 continues to establish the exact pattern of injection and recovery wells from

which to maximize production efficiency. To date, ninety-nine (99) holes have been cased with thirty-six (36) injection and

production wells completed. Two (2) drill rigs are currently casing wells and one (1) drill rig focused on well completion

activities. An additional drill rig will be moving to well completion activities in the coming weeks.

In addition to increasing numbers of drill holes and wells with Grade Thicknesses ("GT") over 1.0 in PAA-7, the Middle C unit,

which was found to overlie PAA-7 in 2023 (NR

May 18, 2023

) continues to exhibit unexpected significant grade, and further

drilling along the Middle C trend is increasing the overall mineralization within PAA-7. Grade Thickness is Grade % U

3

O

8

multiplied by the thickness of the mineralization. ISR recoverable uranium with a Grade Thickness of >0.3 is considered suitable

for inclusion in a wellfield.

Significant Alta Mesa Wellfield Drilling Results

Drill Hole

Goliad Sandstone Horizon

Depth

(ft)

Grade %

U

3

O

8

Thickness

(feet)

Grade

Thickness

(GT)

Total

Hole GT

166-109

MCU-2

418.0

0.165

2.5

0.412

162-116

MCU-1

411.5

0.167

2.0

0.335

169-106

LCU-2

497.0

0.174

8.5

1.476

164-117

LCU-2

491.0

0.193

5.5

1.062

176-92

LCL-1

517.0

0.167

3.0

0.502

175-911

LCL-1

517.0

0.149

4.0

0.598

175-912

LCU-1

499.0

0.116

4.0

0.463

166-109

MCU-1

413.5

0.160

5.0

0.798

181-951

LCU-1

511.0

0.173

6.0

1.039

169-103

LCL-1

514.0

0.444

3.5

1.554

181-952

LCU-2

514.5

0.310

2.5

0.775

166-112

LCL-1

511.5

0.181

2.5

0.452

183-98

LCU-2

509.5

0.141

5.0

0.706

LCL-1

520.5

0.072

6.0

0.429

1.135

167-113

LCU-2

492.5

0.123

3.0

0.368

172-961

MCU-1

418.0

0.098

3.0

0.294

LCU-1

484.0

0.125

2.0

0.250

LCU-2

504.5

0.267

4.0

1.067

1.611

172-962

LCU-2

503.0

0.143

5.0

0.714

LCL-1

516.0

0.201

2.5

0.503

1.217

172-95

LCU-2

503.5

0.334

5.0

1.672

LCL-1

517.5

0.228

2.0

0.455

2.127

172-97

LCU-2

501.0

0.386

5.5

2.121

181-94

LCU-2

512.0

0.256

10.0

2.563

167-108

MCU-1

410.5

0.233

4.0

0.931

171-99

LCL-1

509.0

0.188

2.5

0.471

-

All intercepts are located in the PAA-7 which hosts mineralization within the Goliad Formation. The Company has identified five saturated (required for ISR), mineralized sandstone horizons within the Goliad Formation lying

approximately 400 to 520 feet below the surface. The water level is located approximately 120 feet below the surface. Grade Thickness is Grade % U

3

O

8

multiplied by the thickness of the mineralization.

ISR recoverable

uranium with a Grade Thickness of >0.3 is considered suitable for inclusion in a wellfield.

Alta Mesa In-Situ Recovery (ISR) Uranium Central Processing Plant ("Alta Mesa CPP") & Wellfield

The Alta Mesa CPP and Wellfield hosts a fully licensed and constructed ISR uranium plant, located on 200,000+ acres of

private land in the state of

Texas

. Alta Mesa will be enCore's second producing location and work continues to complete the

pending joint venture ("JV") transaction with Boss Energy (

December 6, 2023

) whereby Boss Energy will acquire a 30% interest

in the enCore managed JV for consideration of

$60 million USD

and a placement into enCore shares of

$10 million USD

.

Total operating capacity at the Alta Mesa CPP is 1.5 million lbs. U

3

O

8

(uranium) per year. The Alta Mesa CPP historically

produced nearly 5 million lbs. U

3

O

8

between 2005 and 2013, when full production was curtailed as a result of low uranium

prices.

Alta Mesa CPP and Wellfield highlights:

The Alta Mesa CPP is enCore's third fully licensed production facility, along with the Rosita CPP and Kingsville Dome CPP,

all located in the business-friendly state of

Texas

. There are only eleven (11) licensed and constructed uranium production

facilities in all of

the United States

(US);

Alta Mesa CPP's operations are located on private land, with 100% of minerals privately owned, and in a supportive

jurisdiction with primary regulatory authority residing with the

State of Texas

;

The Alta Mesa CPP utilizes well-known ISR technology to extract uranium in a non-invasive process using natural

groundwater and oxygen, coupled with a proven ion exchange process, to recover the uranium.

Alta Mesa & Mesteña Grande Mineral

Resource Summary (0.30 GT cut-off)

1,2

Tons

Avg. Grade

(% U

3

O

8

)

Pounds

Total Measured Mineral Resource

1

54,000

0.152

164,000

Alta Mesa Indicated Mineral Resource

1,397,000

0.106

2,959,000

Mesteña Grande Indicated Mineral Resource

119,000

0.120

287,000

Total Measured & Indicated Resources

1,570,000

0.109

3,410,000

Alta Mesa Inferred Mineral Resource

1,263,000

0.126

3,192,000

Mesteña Grande Inferred Mineral Resource

5,733,000

0.119

13,601,000

Total Inferred Resources

6,996,000

0.120

16,793,000

1,2

Represents that portion of the in-place mineral resource that are estimated to be recoverable within existing wellfields. Wellfield recovery factors have not been applied to indicated and inferred mineral resources. As

reported in the

NI-43-101 Technical Report Summary for the Alta Mesa Uranium Project, Brooks and Jim Hogg Counties, Texas, USA completed by Doug Beahm, PE, PG, of BRS Engineering. (Effective January 19, 2023)

The Company advises that it is not basing its production decisions at Alta Mesa CPP or Rosita CPP on a feasibility study of

mineral reserves demonstrating economic and technical viability. The production decision is based on known past In-Situ

Recovery (ISR) and processing operations at these two production facilities and surrounding lands. However, the Company

understands that there is increased uncertainty, and consequently a higher risk of failure, when production is undertaken in

advance of a feasibility study. The Company has determined to proceed with a production decision based on past operations at

the Alta Mesa CPP and Rosita CPP, including past ISR operations in the known mineral resource areas.

John M. Seeley

, Ph.D., P.G., C.P.G., enCore's Manager of Geology and Exploration, and a Qualified Person under NI 43-101,

has reviewed and approved the technical disclosure in this news release on behalf of the Company.

About enCore Energy Corp.

enCore Energy Corp., America's Clean Energy Company™, is committed to providing clean, reliable, and affordable domestic

nuclear energy as the newest uranium producer in

the United States

. Uranium production commenced at enCore's licensed and

past-producing South Texas Rosita Central Processing Plant ("CPP") in

November 2023

with work underway for a planned 2024

restart of uranium production at its licensed and past-producing South Texas Alta Mesa CPP. The enCore team is led by

industry experts with extensive knowledge and experience in all aspects of ISR uranium operations and the nuclear fuel cycle.

enCore solely utilizes In-Situ Recovery ("ISR") for uranium extraction, a well-known and proven technology co-developed by the

leaders at enCore Energy. In-Situ Recovery extracts uranium in a non-invasive process using natural groundwater and oxygen,

coupled with a proven ion exchange process, to recover the uranium.

Future projects in enCore's production pipeline include the Dewey-Burdock project in

South Dakota

and the Gas Hills project in

Wyoming

, along with significant uranium resource endowments in

New Mexico

providing long term opportunities. enCore

diligently works to realize value from other owned assets, including our proprietary uranium database that includes technical

information from many past producing companies, from our various non-core assets, and by leveraging our ISR expertise in

researching opportunities that support the use of this technology as applied to other metals. enCore is also committed to

working with local communities and indigenous governments to create positive impact from corporate developments.

www.encoreuranium.com

Cautionary Note Regarding Forward Looking Statements:

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture

Exchange) accepts responsibility for the adequacy or accuracy of this release.

The Company advises that it is not basing its production decisions at Alta Mesa CPP or Rosita CPP on a feasibility study of

mineral reserves demonstrating economic and technical viability. The production decision is based on known past ISR and

processing operations at these two production facilities and surrounding lands. However, the Company understands that there

is increased uncertainty, and consequently a higher risk of failure, when production is undertaken in advance of a feasibility

study. The Company has determined to proceed with a production decision based on past operations at the Alta Mesa CPP

and Rosita CPP, including past ISR operations in the known mineral resource areas.

Note on forward looking information:

Certain information contained in this news release, including: any information relating to

the Company being a leading uranium company, statements regarding future or potential production, and any other

statements regarding future expectations, beliefs, goals or prospects; may constitute "forward-looking information" and

"forward-looking statements" within the meaning of applicable Canadian and

United States

securities laws and regulations

(collectively, "forward-looking statements"). All statements in this news release that are not statements of historical fact

(including statements containing the words "expects", "is expected", "does not expect", "plans", "anticipates", "does not

anticipate", "believes", "intends", "estimates", "projects", "potential", "scheduled", "forecast", "budget" and similar expressions

or variations (including negative variations) of such words and phrases, or statements that certain actions, events or results

"may", "could", "would", "might" or "will" be taken) should be considered forward-looking statements. Such forward-looking

statements include statements regarding our planned extraction and production operations. All such forward-looking

statements are subject to important risk factors and uncertainties, many of which are beyond the company's ability to control

or predict. Forward-looking statements necessarily involve known and unknown risks, including, without limitation, risks

associated with general economic conditions; adverse industry events; future legislative and regulatory developments; the

ability of enCore to implement its business strategies; including commencement of production at Alta Mesa in the planned

time frames or at all; the expansion of operations to satellite locations; and other risks. A number of important factors could

cause actual results or events to differ materially from those indicated or implied by such forward-looking statements,

including without limitation access to capital risks, exploration and development risks, changes in commodity prices, access to

skilled mining personnel, the results of exploration and development activities; production risks; uninsured risks; regulatory

risks; defects in title; the availability of materials and equipment, timeliness of government approvals and unanticipated

environmental impacts on operations; litigation risks; risks posed by the economic and political environments in which the

Company operates and intends to operate; increased competition; assumptions regarding market trends and the expected

demand and desires for the Company's products and proposed products; reliance on industry equipment manufacturers,

suppliers and others; the failure to adequately protect intellectual property; the failure to adequately manage future growth;

adverse market conditions, the failure to satisfy ongoing regulatory requirements and factors relating to forward looking

statements listed above which include risks as disclosed in the Company's annual information form filings. Should one or

more of these risks materialize, or should assumptions underlying the forward-looking statements prove incorrect, actual

results may vary materially from those described herein as intended, planned, anticipated, believed, estimated or expected.

The Company assumes no obligation to update the information in this communication, except as required by law. Additional

information identifying risks and uncertainties is contained in filings by the Company with the various securities commissions

which are available online at

www.sec.gov

and

www.sedar.com

. Forward-looking statements are provided for the purpose of

providing information about the current expectations, beliefs and plans of management. Such statements may not be

appropriate for other purposes and readers should not place undue reliance on these forward-looking statements, that speak

only as of the date hereof, as there can be no assurance that the plans, intentions or expectations upon which they are based

will occur. Such information, although considered reasonable by management at the time of preparation, may prove to be

incorrect and actual results may differ materially from those anticipated. Forward-looking statements contained in this news

release are expressly qualified by this cautionary statement.

View original content to download multimedia:

https://www.prnewswire.com/news-releases/encore-energy-provides-update-on-south-texas-uranium-operations-302036875.html

SOURCE

enCore Energy Corp.

View original content to download multimedia:

http://www.newswire.ca/en/releases/archive/January2024/17/c8472.html

%SEDAR: 00029787E

For further information:

please contact: William M. Sheriff, Executive Chairman, 972-333-2214, [email protected]

CO: enCore Energy Corp.

CNW 07:00e 17-JAN-24