E3 Lithium Outlines 2024 Corporate Guidance
and its Plans to Advance the Clearwater Project
Highlights:
• E3 Lithium is looking forward to another significant year of growth in 2024 as it advances its
Clearwater Project towards commercial operations and revenue generation
• With the commercial viability of Direct Lithium Extraction Technology and E3 Lithium’s brines-to-
battery flow sheet demonstrated in 2023, achieving the milestones set for 2024 marks a
fundamental shift in E3 Lithium’s business and sets it on a clear and demonstrated pathway to
commercial operations
• E3 Lithium looks forward to discussing its 2024 guidance during its February 22 webinar at 10 a.m.
MST / 12 p.m. EST – details to join are provided below
CALGARY, ALBERTA, February 21, 2024 – E3 LITHIUM LTD. (TSXV: ETL) (FSE: OW3) (OTCQX: EEMMF), “E3
Lithium” or the “Company,” a leader in Canadian lithium, is pleased to share its plans for the upcoming year.
The Company made significant progress in 2023 on the path for producing commercial lithium in Alberta.
Looking ahead into 2024, E3 Lithium’s primary focus remains on advancing the Clearwater Project to
commercial operations. The milestones it will achieve in 2024 will establish its project as one of the few
advanced stage lithium developments in Canada and North America. In addition to the Clearwater Project,
the magnitude of E3 Lithium’s resources enables the Company to unlock the potential of the significant land
package throughout 2024 across its permit areas.
Going into 2024, E3 Lithium maintains a strong financial position. In the current market conditions, E3
Lithium has positioned itself to continue accelerating a path forward to producing first commercial lithium
from its significant resources in South-Central Alberta.
“E3 Lithium had a very successful 2023 by progressing all core aspects of our business, putting us in
position to deliver ambitious targets in 2024 moving us closer to first commercial lithium,” said Chris
Doornbos, President and CEO of E3 Lithium. “The achievement of this year’s goals will mark a fundamental
shift in our business, one that sees us move from a technology and resource developer to a
commercialization company on a clear and demonstrated pathway to operations.”
E3 Lithium is focusing on the following goals in 2024.
Progressing the Clearwater Project Towards Commercial Operations
E3 Lithium’s Clearwater Project is the Company’s primary focus for its first commercial lithium facility,
located in South-Central Alberta. The milestones the Company will achieve in advancing its development
this year, including progressing engineering studies and commercial permitting, will establish the
Clearwater Project as one of the few advanced stage lithium projects in Canada and North America. The
PFS for the Clearwater Project represents a monumental milestone for Canadian lithium brines as it results
in the booking of reserves.
Suite 1520 – 300 5th Ave SW
Calgary, AB T2P 3C4
Tel: +1 (587) 324-2775
Email: [email protected]
Website: e3lithium.ca
Image 1: E3 Lithium’s Alberta assets
To move towards commercial operations in the Clearwater Project, the Company looks forward to
completing the PFS and releasing the NI 43-101 report, aiming for late Q2 2024. E3 Lithium is working
diligently to deliver the PFS report in Q2; the critical path to be able to do so is receiving engineering
packages from external vendors. If delivery is delayed, the public report may be delayed as well. The
Company will update the market on its progress and delivery times as they become firm.
The PFS is designed to a level of detail that will enable the Company to move directly into Feasibility Study
(FS) and includes the full design of the first commercial facility, along with an updated cost estimate and
development schedule. With the publication of the PFS NI 43-101 report, E3 Lithium will book Canada’s first
lithium-in-brine reserves in the Clearwater Project area, a significant milestone for the Canadian lithium
brine industry. E3 Lithium has initiated the permitting process for the commercial facility and will look to
advance this throughout 2024. The milestones E3 Lithium looks forward to completing include publishing
the PFS NI 43-101 report, selecting the EPC for and kicking off the FS, completing environmental and
wildlife surveys and public consultation for its commercial facility, and preparing regulatory applications for
approval.
While the PFS will outline details of the first commercial facility, the Clearwater area is likely to be able to
support further production expansion. Based on the sheer size and consistency of E3 Lithium’s resources in
Alberta, demonstrating a successful development in the Clearwater area supports the value of the
remaining land in the Exshaw (northern Bashaw) and Rocky areas. E3 Lithium believes it has enough brines
to produce approximately 150,000 tonnes of battery grade lithium per year once fully operational across
multiple commercial facilities, which is enough lithium for approximately 2.2M EVs1 annually.
Developing E3 Lithium’s Other Significant Resource Areas
In addition to its Clearwater area in Alberta, E3
Lithium’s significant land package includes the
Exshaw and Rocky areas and its Saskatchewan
property. While E3 Lithium’s focus remains firmly
on the Clearwater Project, the team is evaluating
and progressing additional projects across its
resource base.
Exshaw Area
In the Northern part of the Bashaw District lies
the Exshaw area. The brine composition in the
Exshaw area is very similar to the Clearwater
Project, and the development of this area is
expected to be similar to the Clearwater area.
This area is larger by total brine volume than the
Clearwater. E3 plans to begin the evaluation of
how to develop the Exshaw area once the
Clearwater PFS is complete.
1 Based on a typical 68 kg EV battery.
Suite 1520 – 300 5th Ave SW
Calgary, AB T2P 3C4
Tel: +1 (587) 324-2775
Email: [email protected]
Website: e3lithium.ca
Image 2: E3 Lithium’s Saskatchewan assets
Rocky Area
In the Western trend of the Leduc Aquifer lies the Rocky area. This portion of the aquifer is largely
disconnected from the Bashaw District and hosts a significant volume of lithium enriched brine. The
Company plans to update the resource to include the full aquifer trend in 2024. Once complete, the
Company will evaluate how this area fits into its larger development plans.
Nisku Aquifer across E3 Lithium’s Alberta Resource Areas
Recent sampling results indicate that the Nisku Aquifer, located above the Leduc Aquifer, has similar
concentrations of lithium to the Leduc. This aquifer is coincident with the Leduc in the Bashaw Area,
making it a candidate for co-production. As the Company’s production wells will go through the Nisku to
reach the Leduc, it offers the potential to add more production to the plant in a commercial setting by co-
producing both the Leduc and the Nisku. If successful, the benefit would be an increase to the lifespan of
each well and therefore, a reduction in the well capital required over the life of the plant.
Saskatchewan
E3 Lithium holds a strategic land position in
the heart of the Estevan lithium belt in
Saskatchewan. Resource holders that
surround E3 Lithium have recently
completed resource updates and economic
studies that look to advance Saskatchewan
into a commercially producing region for
lithium. E3 Lithium plans to complete an
inaugural resource in Saskatchewan in
2024. As this area does not form the core of
E3 Lithium’s focus, the Company is
evaluating the best options for creating
value from the land for its shareholders.
Advancing Commercial Development and Offtake
E3 Lithium has been developing strong relationships with potential customers that include companies in the
automotive, cell and cathode manufacturing sectors. The completion of the PFS is a major milestone for
these discussions to mature towards sale contracts. E3 Lithium has been working to grow its commercial
team to support this effort and will continue to prioritize identifying mutually beneficial arrangements with
offtakers.
E3 Lithium’s Strengths G oing into 2024
Balance sheet strength supports ability to execute 2024 plans: E3 Lithium raised more than $30M
CAD via capital raises and grant funding in 2023 and has more than $20M remaining to draw down
on from the Strategic Innovation Fund. The Company is in a strong financial position to execute on
Suite 1520 – 300 5th Ave SW
Calgary, AB T2P 3C4
Tel: +1 (587) 324-2775
Email: [email protected]
Website: e3lithium.ca
its goals in 2024. E3 Lithium continues to actively seek, identify and pursue all sources of non-
dilutive funding to meet the Company’s ongoing needs for capital.
Long-term outlook for EV uptake and lithium demand: The long-term outlook for EV uptake and
demand remains strong, with North American policy objectives in full alignment with a
comprehensive shift to EVs into the 2030s. According to Benchmark Mineral Intelligence, entering
2024, North America is expected to grow lithium production to approximately 40,000 tonnes per
annum (tpa) of battery-grade lithium, while demand is expected to be more than 150,000 tpa. By
2030 global demand could exceed 3M tpa, growing at over 15% per year.
Commercial production to coincide with rising demand: E3 Lithium’s initial commercial production
is likely to be timed in to coincide with the increase in demand for and shortfall of supply of lithium,
which may create favourable pricing environments for E3 Lithium’s offtake.
Lithium offtake sold in long-term contracts: Most lithium today is sold in long-term offtake
arrangements that contain negotiated sales prices. The best gauge for these prices is long term
price forecasts provided by reputable research firms, which are outlining prices much higher than
current spot prices. The price forecasts provided by reputable research firms will be relied upon for
the PFS.
Efficient and well-known permitting regime: Alberta is home to one of the world’s most efficient
and well known regulatory and permitting processes for energy project development, led by the
Government of Alberta and the Alberta Energy Regulator. Recently E3 Lithium’s permits to its
significant land position in Alberta were converted to the province’s new Brine-Hosted Mineral
Licences, reaffirming E3 Lithium’s ownership of ‘surface to basement’ mineral rights to saline
aquifers throughout its operating areas and underscoring the province’s commitment to providing
regulatory certainty and growing the lithium industry. The requirements for E3 Lithium’s commercial
permits are well understood and the Company looks forward to progressing its regulatory work in
2024.
Join us at our Upcoming Webinar
E3 Lithium will be hosting a webinar for investors and other interested parties to share more information
about its 2024 Corporate Guidance and the progress made to-date. Details for this virtual webinar are below
and questions can be submitted in advance to [email protected].
• Date: Thursday, February 22, 2024
• Time: 10 a.m. MST / 12 p.m. EST / 9 a.m. PST
• Log in details: Zoom (click here to log in at the time of the webinar; no need to register in advance)
ON BEHALF OF THE BOARD OF DIRECTORS
Chris Doornbos, President & CEO
E3 Lithium Ltd.
Suite 1520 – 300 5th Ave SW
Calgary, AB T2P 3C4
Tel: +1 (587) 324-2775
Email: [email protected]
Website: e3lithium.ca
E3 Lithium - Investor and Media Relations
Robin Boschman
Director, Investor Relations and Corporate Communications
587-324-2775
About E3 Lithium
E3 Lithium is a development company with a total of 16.0 million tonnes of lithium carbonate equivalent
(LCE) Measured and Indicated and 0.9 million tonnes LCE Inferred mineral resources1 in Alberta. As
outlined in E3’s Preliminary Economic Assessment, the Clearwater Lithium Project has an NPV8% of USD
1.1 Billion with a 32% IRR pre-tax and USD 820 Million with a 27% IRR after-tax1. E3 Lithium’s goal is to
produce high purity, battery grade lithium products to power the growing electrical revolution. With a
significant lithium resource and innovative technology solutions, E3 Lithium has the potential to deliver
lithium to market from one of the best jurisdictions in the world.
1: The Preliminary Economic Assessment (PEA) for the Clearwater Lithium Project NI 43-101 technical
report is amended Sept 17, 2021. Gordon MacMillan, P.Geol, QP, Fluid Domains Inc. and Grahame Binks,
MAusIMM, QP (Metallurgy), formerly of Sedgman Canada Limited (Report Date: June 15, 2018, Effective
Date: June 4, 2018 Amended Date: September 17, 2021). The mineral resource NI 43-101 Technical Report
for the North Rocky Property, effective October 27, 2017, identified 0.9Mt LCE (inferred). The mineral
resource NI 43-101 Technical Report for the Bashaw District Project, effective March 21, 2023, identified
16.0Mt LCE (measured & indicated). All reports are available on the E3 Lithium’s website
(e3lithium.ca/technical-reports) and SEDAR+ (www.sedarplus.ca).
Forward-Looking and Cautionary Statements
This news release includes certain forward-looking statements as well as management’s objectives,
strategies, beliefs and intentions. Forward looking statements are frequently identified by such words as
“may”, “will”, “plan”, “expect”, “anticipate”, “estimate”, “intend” and similar words referring to future events
and results. Forward-looking statements are based on the current opinions and expectations of
management. All forward-looking information is inherently uncertain and subject to a variety of
assumptions, risks and uncertainties, including the speculative nature of mineral exploration and
development, fluctuating commodity prices, the effectiveness and feasibility of emerging lithium extraction
technologies which have not yet been tested or proven on a commercial scale or on the Company’s brine,
competitive risks and the availability of financing, as described in more detail in our recent securities filings
available at www.sedarplus.ca. Actual events or results may differ materially from those projected in the
forward-looking statements and we caution against placing undue reliance thereon. We assume no
obligation to revise or update these forward-looking statements except as required by applicable law.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.