Oyu Tolgoi Underground Development Update – Mongolia
The Oyu Tolgoi project in Mongolia includes two separate land holdings: the Oyu Tolgoi mining licence,
which is held by Entrée’s joint venture partner Oyu Tolgoi LLC (“OTLLC”) and the Entrée/Oyu Tolgoi JV
Property, which is a partnership between Entrée and OTLLC. On October 15, 2020, OTLLC’s 66%
shareholder Turquoise Hill Resources Ltd. (“Turquoise Hill”) provided an update on underground
development:
Work on the Oyu Tolgoi underground project has continued to progress despite COVID‐19
controls and ongoing international travel restrictions issued by the Government of Mongolia. 40
of OTLLC’s expatriates were able to return to Mongolia in July. Further flights are planned in order
to return the required specialists to site.
Care and maintenance activities continue at Shafts 3 and 4 but some commissioning activities
have advanced in preparation for shaft sinking, including rope installation and no‐load testing of
the Shaft 4 hoisting system. Further substantial progress will require the remobilisation of
international shaft‐sinking specialists, and subject to local border restrictions, preparation is
underway by OTLLC to mobilise these contractors before the end of the fourth quarter 2020.
Shafts 3 and 4 will provide ventilation to support the ongoing development associated with
production ramp up for Panels 1 and 2. OTLLC and Rio Tinto International Holdings Ltd. (“Rio
Tinto”) continue to review the impacts of the Shaft 3 and 4 delays.
Overall, underground development on the Oyu Tolgoi mining licence has now reached 48,604
equivalent metres.
All surface infrastructure required for first sustainable production from Panel 0 on the Oyu Tolgoi
mining licence is complete and OTLLC is focused on the safe and efficient delivery of the critical
underground Material Handling System 1 (“MHS1”). The balance of project infrastructure to be
delivered after the completion of MHS1 is not needed for first sustainable production from Panel
0. However, it is needed to support the production ramp‐up profile and the life of mine material
handling infrastructure capacity.
On July 2, 2020, Turquoise Hill announced the completion of an updated Oyu Tolgoi Feasibility
Study (“OTFS20”) that incorporates the new mine design for the first lift (“Lift 1”) of Hugo North
Panel 0 announced by Turquoise Hill on May 13, 2020. The Lift 1 mine plan incorporates the
development of three panels and in order to reach the full sustainable production rate of 95,000
tonnes per day from the underground operations, all three panels need to be in production. On
August 28, 2020, Turquoise Hill announced that it had filed an updated technical report for the
‐ 2 ‐
Oyu Tolgoi project (“2020 OTTR”). OTFS20 and the 2020 OTTR do not reflect the impacts of the
COVID‐19 pandemic, which continue to be assessed by OTLLC, Rio Tinto and Turquoise Hill.
OTFS20 and the 2020 OTTR incorporate an update to the first sustainable production schedule
and capital cost estimates for the underground mine development based on the new block cave
mine design for Panel 0. The new design anticipates a base case development capital cost of $6.8
billion, with a range of $6.6 billion to $7.1 billion, and a target to first sustainable production from
the Oyu Tolgoi mining licence of February 2023, with a target range between October 2022 and
June 2023, inclusive of an allowance for schedule contingency. The mine design for Panel 0 is now
undergoing detailed study, design, engineering and optimization work to support the definitive
estimate cost and schedule update for Panel 0 (the “Definitive Estimate”), expected to be
completed by OTLLC, Rio Tinto and Turquoise Hill in the fourth quarter of 2020. Turquoise Hill has
been advised that preliminary indications from the Definitive Estimate process are that first
sustainable production is trending towards the earlier months of the target range, and that the
forecast development capital cost remains within the range of $6.6 billion to $7.1 billion.
Entrée/Oyu Tolgoi JV Property
Entrée’s 2018 Technical Report completed on its interest in the Entrée/Oyu Tolgoi JV Property
discusses two development scenarios, a reserve case (the “2018 Reserve Case”) and a Life‐of‐
Mine Preliminary Economic Assessment (the “2018 PEA”). The 2018 Reserve Case is based only
on mineral reserves attributable to the Entrée/Oyu Tolgoi joint venture (the “Entrée/Oyu Tolgoi
JV”) from Lift 1 of the Hugo North Extension underground block cave located at the northern
portion of Panel 1. Both the 2018 Reserve Case and the 2018 PEA are based on information
reported within the 2016 Oyu Tolgoi Feasibility Study.
The Company has not yet been provided with OTFS20 or any of the data or assumptions
underlying OTFS20, the block cave designs in OTFS20 or Turquoise Hill’s updated mineral
resources and reserves and the Company is therefore unable to verify such data or the scientific
and technical disclosures made by Turquoise Hill at this time. For information on the Company’s
interest in Entrée/Oyu Tolgoi JV Property, see the 2018 Technical Report available on SEDAR at
www.sedar.com.
Once the Definitive Estimate and the ongoing Panel 1 optimization studies have been completed
and delivered to Entrée with OTFS20, the Company expects to be able to assess the potential
impact on Entrée/Oyu Tolgoi JV Property resources and reserves as well as production and
financial assumptions and outputs from the two alternative cases, the 2018 Reserve Case and the
2018 PEA. Entrée will continue to evaluate any information made available to it by Rio Tinto or
OTLLC and will update the market accordingly.
Corporate
On September 14, 2020, the Company closed a non‐brokered private placement of 10,278,000
units of the Company at a price of C$0.43 per unit for gross proceeds of approximately C$4.4
million. Each unit consists of one common share and one‐half of one transferable common share
purchase warrant (each whole warrant, a “Warrant”). Each Warrant entitles the holder to
purchase one additional common share of the Company at a price of C$0.60 per share for a period
of three years following the date of issuance.
Q3 2020 operating loss was $0.4 million and was consistent with the comparative quarter of Q3
2019.
‐ 3 ‐
Q3 2020 operating cash outflow after working capital was $0.3 million and was consistent with
the $0.3 million operating cash outflow in Q3 2019.
As at September 30, 2020, the cash balance was $7.4 million and the working capital balance was
$7.5 million. The Company holds the majority of its cash in Canadian currency.
The Company recognises the unprecedented situation surrounding the ongoing COVID‐19
pandemic and is closely monitoring the effect of the COVID‐19 pandemic on its business and
operations and will continue to update the market on the impacts to the Company’s business and
operations in relation to these extraordinary circumstances.
OUTLOOK AND STRATEGY
The Company’s primary objective for the 2020 year continues to be to work with other Oyu Tolgoi
stakeholders to advance potential amendments to the joint venture agreement (the “Entrée/Oyu Tolgoi
JVA”) that currently governs the relationship between Entrée and OTLLC and upon finalization, transfer
the Shivee Tolgoi and Javhlant mining licences to OTLLC as manager of the Entrée/Oyu Tolgoi JV. The form
of Entrée/Oyu Tolgoi JVA was agreed between the parties in 2004, prior to the execution of the Oyu Tolgoi
Investment Agreement and commencement of underground development. The Company currently is
registered in Mongolia as the 100% ultimate holder of the Shivee Tolgoi and Javhlant mining licences.
The Company believes that amendments that align the interests of all stakeholders as they are now
understood, would be in the best interests of all stakeholders, provided there is no net erosion of value
to Entrée. No agreements have been finalized and there are no assurances agreements may be finalized
in the future.
The Company continues to expect 2020 full year expenditures, which include Mongolian site management
and compliance costs, to be between $1.5 million and $1.7 million.
The Company’s interim financial statements and Management’s Discussion and Analysis (“MD&A”) for
the third quarter ended September 30, 2020 are available on the Company’s website at
www.EntreeResourcesLtd.com, on SEDAR at www.sedar.com and on EDGAR at www.sec.gov.
QUALIFIED PERSON
Robert Cinits, P.Geo., consultant to Entrée and the Company’s former Vice President, Corporate
Development, and a Qualified Person as defined by NI 43‐101, has approved the technical information in
this release. For further information on the Entrée/Oyu Tolgoi JV Property, see the Company’s Technical
Report (the “2018 Technical Report”), titled “Entrée/Oyu Tolgoi Joint Venture Project, Mongolia, NI 43‐
101 Technical Report”, with an effective date of January 15, 2018, available on SEDAR at www.sedar.com.
ABOUT ENTRÉE RESOURCES LTD.
Entrée Resources Ltd. is a Canadian mining company with a unique carried joint venture interest on a
significant portion of one of the world’s largest copper‐gold projects – the Oyu Tolgoi project in Mongolia.
Entrée has a 20% or 30% carried participating interest in the Entrée/Oyu Tolgoi JV, depending on the
depth of mineralization. Sandstorm Gold Ltd., Rio Tinto and Turquoise Hill are major shareholders of
Entrée, holding approximately 21%, 9% and 8% of the shares of the Company, respectively. More
information about Entrée can be found at www.EntreeResourcesLtd.com.
‐ 4 ‐
FURTHER INFORMATION
David Jan
Investor Relations
Entrée Resources Ltd.
Tel: 604‐687‐4777 | Toll Free: 1‐866‐368‐7330
E‐mail: [email protected]
This News Release contains forward‐looking statements within the meaning of the United States Private Securities Litigation Reform Act of 1995
and forward‐looking information within the meaning of applicable Canadian securities laws with respect to corporate strategies and plans; uses
of funds and projected expenditures; the expectations set out in OTFS20; timing and status of Oyu Tolgoi underground development; the mine
design for Hugo North Lift 1 Panel 0 and the related cost and production schedule implications; the re‐design studies for Panels 1 and 2 of Hugo
North (including Hugo North Extension) Lift 1 and the possible outcomes, content and timing thereof; timing of completion of the Definitive
Estimate and the scope thereof; timing and amount of production from Lift 1 of the Entrée/Oyu Tolgoi JV Property, potential production delays
and the impact of any delays on the Company’s cash flows, expected copper and gold grades, liquidity, funding requirements and planning; the
potential impact of COVID‐19 (coronavirus) on Oyu Tolgoi underground development and the business, operations and financial condition of the
parties to the Entrée/Oyu Tolgoi JV; the estimation of mineral reserves and resources; estimates of capital and operating costs, mill throughput,
cash flows and mine life; capital, financing and project development risk; mining dilution; discussions with the Government of Mongolia, Rio Tinto,
OTLLC and Turquoise Hill on a range of issues including Entrée’s interest in the Entrée/Oyu Tolgoi JV Property, the Shivee Tolgoi and Javhlant
mining licences and certain material agreements; permitting time lines; anticipated business activities; and future financial performance.
In certain cases, forward‐looking statements and information can be identified by words such as "plans", "expects" or "does not expect", "is
expected", "budgeted", "scheduled", "estimates", "forecasts", "intends", "anticipates", or "does not anticipate" or "believes" or variations of such
words and phrases or statements that certain actions, events or results "may", "could", "would", "might", "will be taken", "occur" or "be achieved".
While the Company has based these forward‐looking statements on its expectations about future events as at the date that such statements were
prepared, the statements are not a guarantee of Entrée’s future performance and are based on numerous assumptions regarding present and
future business strategies; the correct interpretation of agreements, laws and regulations; local and global economic conditions and negotiations
and the environment in which Entrée will operate in the future, including commodity prices, projected grades, projected dilution, anticipated
capital and operating costs, anticipated future production and cash flows; the anticipated location of certain infrastructure and sequence of mining
within and across panel boundaries; the construction and continued development of the Oyu Tolgoi underground mine; and the status of Entrée’s
relationship and interaction with the Government of Mongolia, OTLLC, Rio Tinto and Turquoise Hill. With respect to the construction and continued
development of the Oyu Tolgoi underground mine, important risks, uncertainties and factors which could cause actual results to differ materially
from future results expressed or implied by such forward‐looking statements and information include, amongst others, the timing and cost of the
construction and expansion of mining and processing facilities; the timing and availability of a long term domestic power source for Oyu Tolgoi
(or the availability of financing for OTLLC or the Government of Mongolia to construct such a source); the potential impact of COVID‐19; the ability
of OTLLC to secure and draw down on the supplemental debt under the Oyu Tolgoi project finance facility and the availability of additional
financing on terms reasonably acceptable to OTLLC, Turquoise Hill and Rio Tinto to further develop Oyu Tolgoi; the impact of changes in, changes
in interpretation to or changes in enforcement of, laws, regulations and government practises in Mongolia; delays, and the costs which would
result from delays, in the development of the underground mine; the status of the relationship and interaction between OTLLC, Rio Tinto, Turquoise
Hill and the Government of Mongolia on the continued operation and development of Oyu Tolgoi, future funding plans and requirements and
OTLLC internal governance; the anticipated location of certain infrastructure and sequence of mining within and across panel boundaries;
projected copper, gold and silver prices and their market demand; and production estimates and the anticipated yearly production of copper, gold
and silver at the Oyu Tolgoi underground mine.
Other risks, uncertainties and factors which could cause actual results, performance or achievements of Entrée to differ materially from future
results, performance or achievements expressed or implied by forward‐looking statements and information include, amongst others,
unanticipated costs, expenses or liabilities; discrepancies between actual and estimated production, mineral reserves and resources and
metallurgical recoveries; development plans for processing resources; the outcome of the Definitive Estimate; matters relating to proposed
exploration or expansion; mining operational and development risks, including geotechnical risks and ground conditions; regulatory restrictions
(including environmental regulatory restrictions and liability); risks related to international operations, including legal and political risk in
Mongolia; risks associated with changes in the attitudes of governments to foreign investment; risks associated with the conduct of joint ventures;
risks related to the potential impact of global or national health concerns, including the COVID‐19 (coronavirus) pandemic; inability to upgrade
Inferred mineral resources to Indicated or Measured mineral resources; inability to convert mineral resources to mineral reserves; conclusions of
economic evaluations; fluctuations in commodity prices and demand; changing foreign exchange rates; the speculative nature of mineral
exploration; the global economic climate; dilution; share price volatility; activities, actions or assessments by Rio Tinto, Turquoise Hill or OTLLC
and by government authorities including the Government of Mongolia; the availability of funding on reasonable terms; the impact of changes in
interpretation to or changes in enforcement of laws, regulations and government practices, including laws, regulations and government practices
with respect to mining, foreign investment, royalties and taxation; the terms and timing of obtaining necessary environmental and other
government approvals, consents and permits; the availability and cost of necessary items such as water, skilled labour, transportation and
appropriate smelting and refining arrangements; unanticipated reclamation expenses; changes to assumptions as to the availability of electrical
power, and the power rates used in operating cost estimates and financial analyses; changes to assumptions as to salvage values; ability to
maintain the social licence to operate; accidents, labour disputes and other risks of the mining industry; global climate change; title disputes;
limitations on insurance coverage; competition; loss of key employees; cyber security incidents; misjudgements in the course of preparing forward‐
looking statements; as well as those factors discussed in the Company’s most recently filed MD&A and in the Company’s Annual Information Form
for the financial year ended December 31, 2019, dated March 13, 2020 filed with the Canadian Securities Administrators and available at
www.sedar.com. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ
‐ 5 ‐
materially from those described in forward‐looking statements, there may be other factors that cause actions, events or results not to be as
anticipated, estimated or intended. There can be no assurance that forward‐looking statements will prove to be accurate, as actual results and
future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward‐
looking statements. The Company is under no obligation to update or alter any forward‐looking statements except as required under applicable
securities laws.