Ero Copper Reports Third Quarter 2023 Operating and Financial Results
November 2, 2023
Ero Copper Reports Third Quarter 2023 Operating and Financial Results
(all amounts in US dollars, unless otherwise noted)
Vancouver, British Columbia – Ero Copper Corp. (TSX: ERO, NYSE: ERO) (“Ero” or the
“Company”) is pleased to announce its operating and financial results for t he three and nine
months e nded September 30, 2023 . Management will host a conference call tomorrow,
Friday, November 3, 2023 , at 8:30 a.m. eastern time to discuss the results. Dial-in details for
the call can be found near the end of this press release.
HIGHLIGHTS
• Copper production of 10,766 tonnes at C1 cash costs (*) of $1.82 per pound of copper
produced
• Gold production of 17,579 ounces at C1 cash costs (*) and All-in Sustaining Costs
("AISC")(*) of $371 and $844, respectively, per ounce of gold produced
• Record gold production and operating margins at the Xavantina Operations partially
offset lower copper production at the Caraíba Operations as well as the impact of a
stronger Brazilian Real ("BRL") relative to the U.S. dollar ("USD")
◦ Net income attributable to the owners of the Company of $2.5 million ( $0.03
per share on a diluted basis)
◦ Adjusted net income attributable to the owners of the Company (*) of $17.3
million ($0.18 per share on a diluted basis)
◦ Adjusted EBITDA(*) of $42.9 million
• Reaffirming full-year copper production guidance and providing updates to other 2023
guidance ranges to reflect YTD performance, including record operating results at the
Xavantina Operations
• Important milestones achieved in the execution of strategic growth initiatives during
the quarter
◦ Construction of the Tucumã Project reached over 70% physical completion as of
quarter-end. Total project capital estimate remains unchanged at approximately
$305 million
◦ At the Caraíba Operations, construction of the Pilar Mine's new external shaft
continued to progress on schedule. Planned capital expenditures under contract
or in the final stages of negotiation remain at approximately 80% with current
estimates within 5% of budget
TSX: ERO
NYSE: ERO
1 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
◦ Production from the new Matinha vein commenced at the Xavantina Operations,
contributing to a quarter-on-quarter increase of over 40% to both processed
gold grades and gold production as well as record-low unit operating costs
• Available liquidity at quarter-end of $237.6 million included cash and cash equivalents
of $44.8 million , short-term investments of $42.8 million, and $150.0 million of
undrawn availability under the Company's senior secured revolving credit facility
• Immediately prior to quarter-end and continuing into Q4 2023, the Company
opportunistically expanded its foreign exchange hedge program
◦ Of the $437 million foreign exchange derivative position as of October 2023,
$145 million is designated for major project capital expenditures with a
weighted average floor and ceiling of 5.10 and 5.23 BRL per USD, respectively
• Subsequent to quarter-end, the Company entered into a binding term sheet ("Term
Sheet") with Vale Base Metals ("VBM") to earn a 60% interest in the Furnas copper
project (the "Project") upon completion of several exploration, engineering and
development milestones over a period of five years from the execution of a definitive
earn-in agreement
◦ Offers opportunity to expand long-term growth pipeline within the Carajás
Mineral Province, home to the Company's Tucumã Project in Para State, Brazil
◦ Partnership expected to leverage the Company and VBM's collective strengths
while advancing Brazil's position as a leader in the global energy transition
◦ For more information on the Project and Term Sheet, please see the Company's
press release dated October 30, 2023
*These are non-IFRS measures and do not have a standardized meaning prescribed by IFRS
and might not be comparable to similar financial measures disclosed by other issuers. Please
refer to the Company’s discussion of Non-IFRS measures in its Management’s Discussion and
Analysis for the three and nine months ended September 30, 2023 and the Reconciliation of
Non-IFRS Measures section at the end of this press release.
TSX: ERO
NYSE: ERO
2 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
“2023 continues to be a pivotal year for Ero Copper as our near-term growth projects reach
critical milestones and we continue to define and broaden our long-term growth pipeline,”
said David Strang, Chief Executive Officer. “This strategic execution was evident at the
Xavantina Operations, where we successfully initiated production from the Matinha vein
during the quarter, resulting in record gold production and operating margins. We also made
substantial progress at our Tucumã Project, as announced earlier this month, and advanced
our Pilar 3.0 initiative at the Caraíba Operations, where we are nearing completion of the mill
expansion project and preparing to commence main sinking of the new external shaft."
"In parallel, we continue to advance on our medium- and longer-term growth pipeline
through ongoing regional copper and nickel exploration programs at the Caraíba Operations
and, more recently, the execution of a binding term sheet to earn a 60% in VBM's Furnas
copper project."
"Despite these important strategic advancements as well as solid operating performance at
our Caraíba Operations during the quarter, our financial results were impacted by broader
economic conditions that drove weaker metal prices and a stronger BRL against the U.S.
dollar. In response, and in addition to the protection provided by the copper price hedges we
established earlier this year, we elected to opportunistically expand our foreign exchange rate
hedge program to cover a significant portion of projected operating costs and capital
expenditures through the end of 2024."
"While we continue to navigate near-term economic and market uncertainty, we remain
optimistic about the long-term demand outlook for copper and are committed to the
execution of our strategy as we position Ero Copper to create sustainable, long-term value for
all stakeholders."
TSX: ERO
NYSE: ERO
3 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
THIRD QUARTER REVIEW
• Mining & Milling Operations
◦ The Caraíba Operations processed 806,096 tonnes of ore grading 1.46% copper,
producing 10,766 tonnes of copper in concentrate during the quarter after
metallurgical recoveries of 91.6%
– Lower mill throughput volumes, as well as lower mined and processed
copper grades due to mine sequencing, resulted in decreased copper
production quarter-on-quarter
◦ The Xavantina Operations processed 31,446 tonnes of ore grading 18.72 grams
per tonne, producing 17,579 ounces of gold production after metallurgical
recoveries of 92.9%
– Initial production from the new Matinha vein contributed to a quarter-on-
quarter increase of over 40% in both processed gold grades and gold
production
• Organic Growth Projects
◦ The Company made significant progress on the construction of its Tucumã Project,
which reached over 70% physical completion at quarter-end, up from
approximately 45% at the end of Q2 2023. The first phase of plant commissioning
is expected to commence by year-end 2023. First production remains on track to
begin in H2 2024
– Significant advancement in mine pre-stripping, with first sulphide ore on
track to be reached in early November
– All earthworks are now completed, including the water storage reservoir,
site drainage and run-of-mine stockpiles
– Over 15,000 cubic meters of concrete have been poured (over 65%
complete), concluding all major foundation requirements
– Steel structure pre-assembly and erection are tracking ahead of schedule
with approximately 1,000 tonnes of steel already in place
– Key pieces of processing equipment are on site with installations either
concluded or ongoing, including the primary crusher, ball mill, secondary
and tertiary crushers, vibrating screen decks and flotation cells
– Main electrical substation installed on site with construction of power line
tracking ahead of schedule; tie-in to national power grid scheduled for Q4
2023
– Project capital estimate remains unchanged at approximately $305 million
– For additional information on the Tucumã Project, including recent images of
construction progress, please see the Company's press release dated
October 19, 2023
TSX: ERO
NYSE: ERO
4 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
◦ At the Caraíba Operations, the Company is focused on advancing its Pilar 3.0
initiative, designed to support sustained annual ore production levels of 3.0 million
tonnes. The components of Pilar 3.0 include (i) Project Honeypot, an engineering
initiative focused on recovering higher-grade material in the upper levels of the
Pilar Mine, (ii) an expansion of the Caraíba mill from 3.0 to 4.2 million tonnes of
annual throughput capacity, and (iii) construction of a new external shaft to enable
the creation of a two-mine system at the Pilar Mine
– Construction of the new external shaft remains on schedule. Headframe
erection, stage winder installation and several key underground
infrastructure installations were completed during the quarter. Main shaft
sinking remains on track to commence prior to year-end. Planned capital
expenditures under contract or in the final stages of negotiation remain at
approximately 80% with current estimates within 5% of budget
– At the Caraíba mill, installation of the new ball mill, Jameson cell and
associated electrical installations were nearly completed during the period.
The mill expansion project remains on schedule for physical completion
prior to year-end
– Greenfield exploration of regional nickel targets continued during the
quarter; the identification of new copper targets within the Vermelhos
district warrants further investigation during the coming year
◦ Please see recent images from construction on the Caraíba Operations' new
external shaft below
TSX: ERO
NYSE: ERO
5 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
Figure 1: October 2023 aerial view of the Caraíba Operations shaft project, including (A) the permanent rock
and personnel winders, (B) the completed shaft headframe, (C) the stage winder foundation, and (D)
engineering and administrative buildings.
TSX: ERO
NYSE: ERO
6 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
Figure 2: Progress on erection of the permanent rock and personnel winder building (October 2023).
TSX: ERO
NYSE: ERO
7 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
Figure 3: Progress on erection of the stage winder building (October 2023).