Ero Copper Reports Third Quarter 2022 Operating and Financial Results
November 1, 2022
Ero Copper Reports Third Quarter 2022 Operating and Financial Results
(all amounts in US dollars, unless otherwise noted)
Vancouver, British Columbia – Ero Copper Corp. (TSX: ERO, NYSE: ERO) (“Ero” or the
“Company”) is pleased to announce its operating and financial results for t he three and nine
months e nded September 30, 2022 . Management will host a conference call tomorrow,
Wednesday, November 2, 2022, at 11:30 a.m. Eastern time to discuss the results. Dial-in
details for the call can be found near the end of this press release.
HIGHLIGHTS
• Quarterly copper production of 11,189 tonnes at C1 cash costs(*) of $1.46 per pound of
copper produced;
• Quarterly gold production of 10,965 ounces at C1 cash costs (*) and All-in Sustaining
Costs ("AISC")(*) of $537 and $1,135, respectively, per ounce of gold produced;
• Adjusted EBITDA(*) of $32.1 million and adjusted net income attributable to owners of
the Company(*) of $4.0 million ($0.04 per share on a diluted basis);
• Strong quarterly cash flows from operations of $43.0 million;
• Financial results during the period were impacted by continued metal price weakness,
including the impact of $10.3 million in final settlements on provisionally priced copper
concentrate sales from the first half of 2022, combined with increased unit operating
costs at the Caraíba Operations;
• Capital expenditures accelerated during the quarter as construction activities related to
the Company's growth initiatives continued to progress;
◦ At the Tucumã Project, critical path work packages required ahead of the rainy
season have been completed. These include site access and haul road upgrades,
major drainage infrastructure, and advancing pre-stripping activities; and,
◦ At the Caraíba Operations, the Pilar 3.0 growth initiative continues to progress
with surface infrastructure for the new external shaft well-advanced, critical
equipment orders for the expansion of the mill contracted, and the integration of
Project Honeypot into the life-of-mine production plan completed. The updated
strategic life-of-mine production plan for the Caraíba Operations, inclusive of
Project Honeypot, is expected to be released ahead of the Company's Annual
Operational, Project and Exploration Update on November 8, 2022.
TSX: ERO
NYSE: ERO
1 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
• Available liquidity at quarter-end was $434.8 million, including cash and cash
equivalents of $210.2 million , short-term investments of $149.6 million, and $75.0
million of undrawn availability under the Company's senior revolving credit facility;
• 2022 production, operating cost, and capital expenditure guidance reaffirmed; and,
• The Company will host an Annual Operational, Project and Exploration Update on
November 8, 2022, during which a more detailed overview will be provided on the
Pilar 3.0 growth initiative, including the integration of Project Honeypot, the
Company's advancement of the Tucumã Project, and results from exploration
programs at each of the Company's operations.
*These are non-IFRS measures and do not have a standardized meaning prescribed by IFRS
and might not be comparable to similar financial measures disclosed by other issuers. Please
refer to the Company’s discussion of Non-IFRS measures in its Management’s Discussion and
Analysis for the three and nine months ended September 30, 2022 and the Reconciliation of
Non-IFRS Measures section at the end of this press release.
TSX: ERO
NYSE: ERO
2 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
“Our operations delivered solid third quarter operating performance against a challenging
macroeconomic backdrop that resulted in compressed operating margins during the period,”
said David Strang, Chief Executive Officer. “While near-term global economic conditions
remain dynamic, we are well-positioned with an experienced team, high-quality operations
and a solid balance sheet to continue making progress on our strategic growth initiatives.
"At our Tucumã Project, road upgrades and site drainage are now complete ahead of the rainy
season, and our mining contractor mobilized to site and commenced pre-stripping activities
and waste rock dump construction during the quarter. All activities on site are advancing in-
line with the Feasibility Study schedule. At our Caraíba Operations, shaft civil work, raise-
boring and underground development related to our Pilar 3.0 initiative are progressing well,
and an updated life-of-mine production plan reflecting the integration of Project Honeypot
has also been finalized.
"Despite strong operating performance and successful project execution during the period,
our operating costs remain higher than we had forecasted at the beginning of the year due to
inflationary pressures and the higher allocation of copper sales to international customers
that negate some of the tax benefits we receive when we sell to our domestic customer. As
we look ahead to the fourth quarter, we expect to be in line with our revised full-year
operating cost guidance but acknowledge we are tracking towards the higher end of the
range as a result of these impacts.
"While, like our peers, we continue to navigate challenging near-term market conditions, we
remain focused on advancing our growth strategy in anticipation of an unprecedented outlook
for copper. The timing of our growth initiatives, now well underway at Tucumã and Caraíba,
continues to align well with an expected surge in copper demand that is projected to far
outpace supply in the years ahead."
TSX: ERO
NYSE: ERO
3 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
THIRD QUARTER REVIEW
• Mining & Milling Operations
◦ The Caraíba Operations processed 720,725 tonnes of ore grading 1.68% copper,
producing 11,189 tonnes of copper in concentrate during the quarter after
metallurgical recoveries of 92.2%.
◦ The Xavantina Operations processed 42,747 tonnes of ore grading 8.55 grams per
tonne gold, producing 10,965 ounces of gold after metallurgical recoveries of
93.3% and 7,487 ounces of silver as a by-product.
• Organic Growth Projects
◦ At the Tucumã Project, engineering, contracting efforts and construction activities
continued to progress during the quarter.
– Critical path earthworks, site drainage and road upgrades are finished. Mine
pre-stripping, waste and tailings dump construction, and plant site
earthworks are underway. Total project engineering and construction are
approximately 40% and 8% complete, respectively, on-track with the
Feasibility Study schedule;
– Approximately 30% of planned capital expenditures were under contract as
of quarter-end and within 10% of pre-contingency Feasibility Study
estimates; and,
– Approximately 80% of Feasibility Study capital expenditures have now
been contracted or are in various stages of tendering or negotiation. Based
upon prevailing foreign exchange rates, labour costs and diesel prices, and
subject to final contract negotiations, these expenditures are currently
forecast to be within 12% of pre-contingency Feasibility Study estimates.
◦ The Company continued to advance its Pilar 3.0 initiative, comprised of several
projects that together are expected to enable the creation of a two-mine system at
the Pilar Mine. These projects include (i) Project Honeypot, an engineering initiative
focused on recovering higher-grade material in the upper levels of the Pilar Mine,
(ii) construction of a new external shaft to access the Deepening Extension Zone,
and (iii) an expansion of the Caraíba Mill to 4.2 million tonnes per annum.
– Incorporation of Project Honeypot into the Caraíba strategic life-of-mine
production plan was completed subsequent to quarter-end and is expected
to be released ahead of the Company's Annual Operational, Project and
Exploration Update on November 8, 2022;
– Construction of the new external shaft is progressing well with physical
completion currently at approximately 10% with approximately 30% of
planned capital expenditures under contract as of quarter-end; and,
– Caraíba Mill expansion is advancing as planned with the ball mill
installation contract finalized during the quarter.
TSX: ERO
NYSE: ERO
4 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
Figure 1: Tucumã Project site in April 2022 (left) and August 2022 (right).
Figure 2: Tucumã Project mine access road and completed drainage infrastructure (left) and waste rock dump
with installation of HDPE liner underway in October 2022 (right).
TSX: ERO
NYSE: ERO
5 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
• Exploration Highlights
◦ In early 2022, the Company formed a dedicated nickel exploration team to
accelerate the identification and testing of nickel targets throughout the Curaçá
Valley. This effort resulted in the announced discovery of a new nickel sulphide
system, known as the "Umburana System", located approximately 20 kilometers
from the Caraíba processing facilities. The system, which has an initial strike length
of five kilometers, remains open in all directions and is highlighted by multiple
surface expressions of nickel mineralization. Drilling of additional targets within
the system remains ongoing with four dedicated drill rigs. For additional
information on the Umburana System, including drill results, please see the
Company's press release dated September 29, 2022.
◦ Exploration at the Tucumã Project during the quarter was focused on extensional
drilling of high-grade mineralization to depth in the south and southwestern
portions of the deposit, beneath the designed pit shell.
◦ Exploration activities at the Xavantina Operations during the quarter continued to
focus on testing extensions of the Matinha and Santo Antônio veins. Step-out
drilling continues to confirm thick, high-grade extensions at depth within the Santo
Antônio vein, which remains open.
◦ Highlights from these exploration programs will be announced as part of the
Company's Annual Operational, Project and Exploration Update planned for
November 8, 2022.
TSX: ERO
NYSE: ERO
6 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
OPERATING AND FINANCIAL HIGHLIGHTS
3 months
ended
Sep. 30, 2022
3 months
ended
June 30, 2022
3 months
ended
Sep. 30, 2021
9 months
ended
Sep. 30, 2022
9 months
ended
Sep. 30, 2021
Operating Highlights
Copper (Caraíba Operations)
Ore Processed (tonnes) 720,725 801,425 572,666 2,118,380 1,724,252
Grade (% Cu) 1.68 1.74 1.90 1.73 2.11
Cu Production (tonnes) 11,189 12,734 10,057 33,707 33,593
Cu Production (000 lbs) 24,669 28,073 22,170 74,312 74,059
Cu Sold in Concentrate (tonnes) 10,522 12,948 10,762 33,515 33,324
Cu Sold in Concentrate (000 lbs) 23,197 28,546 23,727 73,888 73,468
C1 cash cost of Cu produced (per lb)(1) $ 1.46 $ 1.24 $ 0.94 $ 1.34 $ 0.70
Gold (Xavantina Operations)
Au Production (oz) 10,965 11,122 9,426 30,883 29,254
C1 cash cost of Au Produced (per oz)(1) $ 537 $ 643 $ 538 $ 604 $ 508
AISC of Au produced (per oz)(1) $ 1,135 $ 1,169 $ 741 $ 1,135 $ 681
Financial Highlights ($ in millions, except per share amounts)
Revenues $ 85.9 $ 114.9 $ 111.8 $ 309.7 $ 355.0
Gross profit 22.8 50.7 68.0 134.5 234.5
EBITDA(1) 27.9 53.9 48.5 159.9 215.7
Adjusted EBITDA(1) 32.1 55.8 72.9 150.3 245.1
Cash flow from operations 43.0 22.4 150.7 109.4 297.9
Net income 4.0 24.1 26.4 80.6 142.4
Net income attributable to owners of the Company 3.7 23.8 26.1 79.7 141.2
Per share (basic) 0.04 0.26 0.29 0.88 1.60
Per share (diluted) 0.04 0.26 0.28 0.87 1.52
Adjusted net income attributable to owners of the
Company(1) 4.0 24.4 41.2 61.3 154.4
Per share (basic) 0.04 0.27 0.47 0.68 1.75
Per share (diluted) 0.04 0.27 0.44 0.67 1.66
Cash, cash equivalents, and short-term investments 359.8 429.9 119.1 359.8 119.1
Working capital(1) 343.2 417.7 81.4 343.2 81.4
Net (cash) debt(1) 51.5 (10.2) (63.7) 51.5 (63.7)
(1) EBITDA, Adjusted EBITDA, Adjusted net income (loss) attributable to owners of the Company, Adjusted net
income (loss) per share attributable to owners of the Company, Net (Cash) Debt, Working Capital, C1 cash
cost of copper produced (per lb), C1 cash cost of gold produced (per ounce) and AISC of gold produced (per
ounce) are non-IFRS measures. These measures do not have a standardized meaning prescribed by IFRS and
might not be comparable to similar financial measures disclosed by other issuers. Please refer to the
Company’s discussion of Non-IFRS measures in its Management’s Discussion and Analysis for the three and
nine months ended September 30, 2022 and the Reconciliation of Non-IFRS Measures section at the end of
this press release.
TSX: ERO
NYSE: ERO
7 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
2022 GUIDANCE(*)
The Company is reaffirming its full-year production guidance as well as its revised 2022
operating cost and capital expenditure guidance. At the Caraíba Operations, copper
production in Q4 2022 is expected to be similar to Q3 2022 production levels. At the
Xavantina Operations, the Company also expects to achieve similar Q4 2022 gold production
levels relative to Q3 2022, resulting from higher anticipated gold grades and lower expected
tonnes processed.
Due primarily to a higher allocation of concentrate sales to the international market and the
continued influence of inflation on the cost of key consumables, C1 cash costs at the Caraíba
Operations are trending towards the high-end of the guidance range of $1.20 to $1.35 per
pound of copper produced. At the Xavantina Operations, costs are trending towards the low-
end of the full-year C1 cash cost guidance range of $600 to $700 per ounce of gold produced
and the high-end of the 2022 AISC range of $1,000 to $1,100 per ounce of gold produced.
2022 PRODUCTION AND COST GUIDANCE(*)
The Company's cost guidance for 2022 assumes a USD:BRL foreign exchange rate of 5.30, a
gold price of $1,725 per ounce and a silver price of $20.00 per ounce for Q4 2022.
2022 Guidance
Caraíba Operations
Copper Production (tonnes) 43,000 - 46,000
C1 Cash Cost Guidance (US$/lb)(1)
$1.20 - $1.35
Xavantina Operations
Gold Production (ounces) 39,000 - 42,000
C1 Cash Cost Guidance (US$/oz)(1)
$600 - $700
All-in Sustaining Cost (AISC) Guidance (US$/oz)(1)
$1,000 - $1,100
(1) These are non-IFRS measures and do not have a standardized meaning prescribed by IFRS and might not be
comparable to similar financial measures disclosed by other issuers. See the Reconciliation of Non-IFRS
Measures section at the end of this press release for additional information.
TSX: ERO
NYSE: ERO
8 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada