Ero Copper Reports Second Quarter 2022 Operating and Financial Results Including Record Quarterly Copper and Gold Production
August 2, 2022
Ero Copper Reports Second Quarter 2022 Operating and Financial Results
Including Record Quarterly Copper and Gold Production
(all amounts in US dollars, unless otherwise noted)
Vancouver, British Columbia – Ero Copper Corp. (TSX: ERO, NYSE: ERO) (“Ero” or the
“Company”) is pleased to announce its operating and financial results for t he three and six
months e nded June 30, 2022 . Management will host a conference call tomorrow,
Wednesday, August 3, 2022, at 11:30 a.m. Eastern time to discuss the results. Dial-in details
for the call can be found near the end of this press release.
HIGHLIGHTS
• Record quarterly copper production of 12,734 tonnes at C1 cash costs (*) of $1.24 per
pound of copper produced;
• Record quarterly gold production of 11,122 ounces at C1 cash costs (*) and All-in
Sustaining Costs ("AISC") (*) of $643 and $1,169, respectively, per ounce of gold
produced;
• Adjusted EBITDA(*) of $55.8 million and adjusted net income attributable to owners of
the Company(*) of $24.4 million ($0.27 per share on a diluted basis);
• Financial results during the period were impacted by operational challenges at the
Company's primary domestic customer that resulted in a higher allocation of sales to
the international market. The timing of sales to, and longer quotational periods with,
international customers, combined with a weakening copper price just prior to quarter-
end, resulted in a reduction to revenue of approximately $13.0 million (see "Second
Quarter Review" for more information);
• Quarterly cash flows from operations of $22.4 million also reflect an increase in
accounts receivable of $18.9 million due to the timing of concentrate shipments and
longer payment terms with international customers. Absent this increase in accounts
receivable, cash flows from operations during the quarter would have been over $40.0
million;
• Available liquidity at quarter-end was $504.9 million, including cash and cash
equivalents of $329.3 million , short-term investments of $100.6 million, and $75.0
million of undrawn availability under the Company's senior revolving credit facility;
TSX: ERO
NYSE: ERO
1 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
• Key organic growth projects advancing on schedule and on budget:
◦ At the Tucumã Project (formerly referred to as the Boa Esperança Project),
approximately 22% of planned capital expenditures were under contract as of
August 1, 2022, with another 8% in the final phases of contracting. Capital
commitments contracted and in the final phases of negotiation are within 6% of
Feasibility Study estimates;
◦ At the Caraíba Operations (formerly referred to as the MCSA Mining Complex),
equipment packages and supply contracts totaling approximately 25% of planned
capital expenditures for the new external shaft have been finalized as of August 1,
2022 at 10% below project capital estimates. The shaft sinking contract, the
largest contributor to the project's total capital spend, is in the final negotiation
phase. Upon execution of the sinking contract, capital secured under contract for
the project is expected to be approximately 70% and align with the total project
capital estimate; and,
◦ In addition to ongoing construction activities, the Company is developing a
sustainability strategy for the Tucumã Project and surrounding community. To
date, approximately $1.0 million has been earmarked for projects designed to
mitigate the environmental impact of project development and provide support for
the local community.
• Reaffirming full-year production guidance, lowering consolidated 2022 capital
expenditure guidance, and raising operating cost guidance for the year:
◦ Full-year copper production expected to be at the high-end of the 43,000 to
46,000 tonne guidance range;
◦ Full-year gold production guidance range of 39,000 to 42,000 ounces reaffirmed;
◦ Full-year consolidated capital expenditure guidance lowered by over $20 million,
from $330-$375 million to $308-$354 million, as a result of capital replanning
efforts resulting in deferrals at the Company's Caraíba Operations. The deferral of
this capital spend is not expected to impact timelines for key growth projects;
◦ Full-year C1 cash cost guidance has been increased for the Caraíba Operations to
$1.20 to $1.35 (previously $1.05 to $1.15) per pound of copper produced to
reflect elevated international concentrate sales , which are expected to continue
through the remainder of the year, as well as the impact of inflation in the cost of
key consumables and a strong BRL versus the US dollar in H1 2022; and,
◦ Full-year cost guidance ranges for the Xavantina Operations (formerly referred to
as the NX Gold Mine) have be updated to reflect the aforementioned impact of
inflation and BRL strength in H1 2022:
– C1 cash cost guidance revised to $600 to $700 (previously $500 to $600)
per ounce of gold produced; and,
– AISC guidance revised to $1,000 to $1,100 (previously $925 to $1,025) per
ounce of gold produced.
TSX: ERO
NYSE: ERO
2 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
“Our second quarter delivered record operational performance across our assets and saw the
successful execution of important milestones critical to our growth strategy,” said David
Strang, Chief Executive Officer. “Underpinning our record quarterly production results were
new monthly records set for production rates, development rates, asset efficiency and
availability, among others. Following a challenging first quarter operating environment, I
want to congratulate our on-site teams for setting new high watermarks that showcase the
capabilities of our assets and people.
“Across our key growth projects, construction and development activities are progressing on
schedule and well within contingency levels at this time. Our team's adherence to the original
capital expenditure estimates for major equipment line items and work packages that have
been secured on these projects to date is remarkable given the significant inflationary
headwinds that the mining industry has faced since the beginning of 2022.
“Despite our record operating performance and outstanding project execution during the
quarter, our financial results were impacted by operational challenges at our primary
domestic smelting customer, which resulted in changes to our copper concentrate sales
channels that are expected to continue through the balance of the year."
“Primarily as a result of higher allocation of sales to international customers and elevated
input costs in the first half of the year across our business units, we have adjusted our full-
year operating cost guidance ranges. Offsetting these increases, proactive capital
management reviews with our team during the quarter identified over $20 million of capital
deferrals that will not impact our business strategy yet will support continued balance sheet
strength during this period of elevated market and copper price volatility.”
*These are non-IFRS measures and do not have a standardized meaning prescribed by IFRS
and might not be comparable to similar financial measures disclosed by other issuers. Please
refer to the Company’s discussion of Non-IFRS measures in its Management’s Discussion and
Analysis for the three and six months ended June 30, 2022 and the Reconciliation of Non-
GAAP Measures section at the end of this press release.
TSX: ERO
NYSE: ERO
3 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
SECOND QUARTER REVIEW
• Mining & Milling Operations
◦ The Caraíba Operations processed 801,425 tonnes of ore grading 1.74% copper,
producing a record 12,734 tonnes of copper in concentrate during the quarter after
metallurgical recoveries of 91.2%.
◦ The Xavantina Operations processed 57,291 tonnes grading 6.59 grams per tonne,
producing a record 11,122 ounces of gold after metallurgical recoveries of 91.6%
and 7,306 ounces of silver as a by-product.
• Organic Growth Projects
◦ At the Tucumã Project, the Company continued to advance critical-path
workstreams during the period and subsequent to quarter-end. Highlights include:
– Approximately 22% of planned capital expenditures under contract as of
August 1, 2022, with another 8% in the final phases of contracting;
– Capital commitments contracted and in the final phases of negotiation
within 6% of Feasibility Study estimates;
– Significant advances made on all road upgrades, including pit access and
completion of community bypass road infrastructure;
– Completion of approximately 75% of planned pre-production vegetation
suppression required for pre-stripping activities to commence;
– Purchase of the ball mill for the Project;
– Site earth works initiated subsequent to quarter-end; and,
– Installation of site drainage expected to be completed by end of October
2022, ahead of the rainy season.
◦ At the Caraíba Operations, the Company made meaningful progress on its "Pilar
3.0" initiative, which encompasses various projects that jointly are designed to
create a two-mine system at the Pilar Mine targeting higher sustained production
levels. These projects include (i) construction of a new external shaft to access the
Deepening Extension Zone, (ii) Project Honeypot, which is expected to support
higher production volumes from the upper levels of the Pilar Mine, (iii) an
expansion of the Caraíba Mill to 4.2 million tonnes per annum, and (iv) the recently
completed Cooling Project. Select highlights include:
– Equipment packages and supply contracts totaling approximately 25% of
planned capital expenditures for the new external shaft finalized as of
August 1, 2022 at 10% below budget;
– Shaft sinking contract, which will bring estimated shaft capital secured
under contract to approximately 70%, in the final negotiation phase. Upon
execution, capital commitments under contract expected to align with
original estimates;
– Engineering and procurement related to shaft sinking were completed
during the quarter with the shaft sinking contract anticipated to be finalized
during the third quarter;
TSX: ERO
NYSE: ERO
4 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
– Completed construction of the concrete batch plant during the period and
commenced commissioning activities subsequent to quarter-end;
– Engineering and design work related to the expansion of the Caraíba Mill
continued during the second quarter with the ball mill installation contract
finalized subsequent to quarter-end;
– Aggressively advanced drilling efforts within the Project Honeypot area, the
results of which are expected to be included in the Company's year-end
mineral reserve and resource estimates; and,
– Completed the Cooling Project's second and final phase, with hand-over to
operations occurring in April 2022 at better-than-design performance.
• Impact of Increased Sales of Copper Concentrate to International Market
◦ Historically, the Company has had limited exposure to movements in copper prices
on provisional invoices due to its majority allocation of concentrate sales to
domestic customers with which the Company has favorable payment terms.
However, during the second quarter, operational challenges at the Company's
primary domestic customer resulted in a higher allocation of sales to the
international market. Longer quotational periods with international customers,
combined with a weakening copper price just prior to quarter-end, resulted in a
reduction to revenue of approximately $13.0 million during the period.
◦ Quarterly cash flows from operations of $22.4 million were also impacted by an
increase in accounts receivable of $18.9 million due to the timing of concentrate
shipments and longer payment terms with international customers.
◦ These concentrate sales changes, including related impacts on payment terms, are
expected to continue through the end of 2022. Allocation of concentrate sales
between domestic and international customers is expected to revert to historical
levels in 2023 assuming competitive pricing terms.
TSX: ERO
NYSE: ERO
5 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
OPERATING AND FINANCIAL HIGHLIGHTS
3 months
ended
June 30, 2022
3 months
ended
Mar. 31, 2022
3 months
ended
June 30, 2021
6 months
ended
June 30, 2022
6 months
ended
June 30, 2021
Operating Highlights
Copper (Caraíba Operations)
Ore Processed (tonnes) 801,425 596,230 553,992 1,397,655 1,151,586
Grade (% Cu) 1.74 1.78 2.13 1.76 2.22
Cu Production (tonnes) 12,734 9,784 10,898 22,518 23,536
Cu Production (000 lbs) 28,073 21,570 24,026 49,643 51,889
Cu Sold in Concentrate (tonnes) 12,948 10,045 10,094 22,993 22,562
Cu Sold in Concentrate (000 lbs) 28,546 22,145 22,253 50,691 22,253
C1 cash cost of Cu produced (per lb)(1) $ 1.24 $ 1.31 $ 0.72 $ 0.63 $ 0.49
Gold (Xavantina Operations)
Au Production (oz) 11,122 8,796 10,377 19,918 19,828
C1 cash cost of Au Produced (per oz)(1) $ 643 $ 638 $ 499 $ 641 $ 494
AISC of Au produced (per oz)(1) $ 1,169 $ 1,092 $ 660 $ 1,135 $ 652
Financial Highlights ($ in millions, except per share amounts)
Revenues $ 114.9 $ 108.9 $ 120.7 $ 223.8 $ 243.2
Gross profit 50.7 61.0 83.7 111.7 166.5
EBITDA(1) 53.9 78.1 112.0 132.0 167.2
Adjusted EBITDA(1) 55.8 62.4 85.5 118.2 172.2
Cash flow from operations 22.4 44.0 85.1 66.4 147.2
Net income 24.1 52.5 84.0 76.6 116.0
Net income attributable to owners of the Company 23.8 52.1 83.4 75.9 115.2
Per share (basic) 0.26 0.58 0.95 0.84 1.31
Per share (diluted) 0.26 0.57 0.89 0.83 1.24
Adjusted net income attributable to owners of the
Company(1) 24.4 33.0 53.5 57.3 109.8
Per share (basic) 0.27 0.37 0.61 0.63 1.25
Per share (diluted) 0.27 0.36 0.57 0.62 1.18
Cash, cash equivalents, and short-term investments 429.9 365.5 137.7 429.9 137.7
Working capital(1) 417.7 443.7 118.9 417.7 118.9
Net (cash) debt(1) (10.2) (54.4) 19.2 (10.2) 19.2
(1) EBITDA, Adjusted EBITDA, Adjusted net income (loss) attributable to owners of the Company, Adjusted net
income (loss) per share attributable to owners of the Company, Net (Cash) Debt, Working Capital, C1 cash
cost of copper produced (per lb), C1 cash cost of gold produced (per ounce) and AISC of gold produced (per
ounce) are non-IFRS measures. These measures do not have a standardized meaning prescribed by IFRS and
might not be comparable to similar financial measures disclosed by other issuers. Please refer to the
Company’s discussion of Non-IFRS measures in its Management’s Discussion and Analysis for the three and
six months ended June 30, 2022 and the Reconciliation of Non-GAAP Measures section at the end of this
press release.
TSX: ERO
NYSE: ERO
6 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
2022 GUIDANCE(*)
The Company is reaffirming its full-year production guidance, lowering consolidated 2022
capital expenditure guidance, and raising operating cost guidance for the year.
At its Caraíba Operations, the Company continues to guide to the high-end of its reaffirmed
2022 copper production guidance range of 43,000 to 46,000 tonnes. As previously noted,
copper production is expected to be roughly equally weighted between the first and second
halves of the year with mining of the initial Project Honeypot stope (RC03) at the Pilar Mine
expected to support a continuation of strong mined and processed copper grades into Q3
2022. At the Xavantina Operations, higher gold grades are expected to drive modestly higher
gold production during the second half of the year.
The Company is lowering its consolidated 2022 capital expenditure guidance by over $20
million, from $330-$375 million to $308-$354 million, as a result of capital replanning
efforts and deferrals at the Caraíba Operations. The deferral of this capital spend is not
expected to impact timelines of the Company's key growth projects.
The Company is raising its full-year operating cost guidance ranges due to the impact of
inflation in the cost of key consumables and a stronger BRL versus the US dollar during H1
2022 as well as an expected continuation of elevated copper concentrate sales to
international markets in H2 2022. The Company's revised 2022 copper C1 cash cost
guidance range is $1.20 to $1.35 (originally $1.05 to $1.15) per pound of copper produced.
The Company is also increasing its 2022 gold C1 cash costs and AISC guidance ranges to
$600 to $700 (previously $500 to $600) and $1,000 to $1,100 (previously $925 to $1,025),
respectively, per ounce of gold produced for its Xavantina Operations.
2022 PRODUCTION AND COST GUIDANCE(*)
The Company's cost guidance for 2022 assumes a USD:BRL foreign exchange rate of 5.30, a
gold price of $1,725 per ounce and a silver price of $20.00 per ounce for H2 2022.
Original Revised
Caraíba Operations
Copper Production (tonnes) 43,000 - 46,000 Unchanged
C1 Cash Cost Guidance (US$/lb)(1)
$1.05 - $1.15 $1.20 - $1.35
Xavantina Operations
Gold Production (ounces) 39,000 - 42,000 Unchanged
C1 Cash Cost Guidance (US$/oz)(1)
$500 - $600 $600 - $700
All-in Sustaining Cost (AISC) Guidance (US$/oz)(1)
$925 - $1,025 $1,000 - $1,100
(1) These are non-IFRS measures and do not have a standardized meaning prescribed by IFRS and might not be
comparable to similar financial measures disclosed by other issuers.
TSX: ERO
NYSE: ERO
7 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
2022 CAPITAL EXPENDITURE GUIDANCE(*)
The Company's capital expenditure guidance for 2022 assumes a USD:BRL foreign exchange
rate of 5.30 for H2 2022 and has been presented below in USD millions.
Original Revised
Caraíba Operations
Growth $125 - $140 $95 - $110
Sustaining $80 - $90 $85 - $95
Exploration $25 - $30 Unchanged
Total, Caraíba Operations $230 - $260 $180 - $205
Tucumã Project
Growth $70 - $80 Unchanged
Exploration $5 - $6 Unchanged
Total, Tucumã Project $75 - $86 Unchanged
Xavantina Operations
Growth $0 - $1 $2 - $4
Sustaining $16 - $18 Unchanged
Exploration $9 - $10 $10 - $11
Total, Xavantina Operations $25 - $29 $28 - $33
Company Total
Growth $195 - $221 $167 - $194
Sustaining $96 - $108 $101 - $113
Exploration $39 - $46 $40 - $47
Total, Company $330 - $375 $308 - $354
(*) Guidance is based on certain estimates and assumptions, including but not limited to, mineral reserve
estimates, grade and continuity of interpreted geological formations and metallurgical performance. Please
refer to the Company’s SEDAR and EDGAR filings, including the Company's most recent Annual Information
Form ("AIF"), for complete risk factors.
TSX: ERO
NYSE: ERO
8 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada