Ero Copper Reports Fourth Quarter and Full Year 2022 Operating and Financial Results
March 7, 2023
Ero Copper Reports Fourth Quarter and Full Year 2022 Operating and Financial Results
(all amounts in US dollars, unless otherwise noted)
Vancouver, British Columbia – Ero Copper Corp. (TSX: ERO, NYSE: ERO) (“Ero” or the
“Company”) is pleased to announce its operating and financial results for t he three and
twelve months e nded December 31, 2022 . Management will host a conference call
tomorrow, Wednesday, March 8, 2023, at 11:30 a.m. Eastern time to discuss the results. Dial-
in details for the call can be found near the end of this press release.
HIGHLIGHTS
• Record full-year copper production of 46,371 tonnes, including 12,664 tonnes
produced in the fourth quarter, surpassed the Company's 2022 production guidance
range of 43,000 to 46,000 tonnes
• Copper C1 cash costs (*) for the fourth quarter and full-year were $1.41 and $1.36,
respectively, per pound of copper produced
• Gold production also marked a record 42,669 ounces in 2022, including 11,786 ounces
produced in the fourth quarter, and exceeded the full-year guidance range of 39,000 to
42,000 ounces
• Gold C1 cash costs (*) for the fourth quarter and full-year were $445 and $560,
respectively, per ounce of gold produced. All-in Sustaining Costs ("AISC") (*) for the
same periods were $1,096 and $1,124, respectively, per ounce of gold produced
• Fourth quarter and full-year cash flows from operations were $34.0 million and
$143.4 million, respectively
• Fourth quarter and full-year adjusted EBITDA(*) were $58.2 million and $208.6 million,
respectively
• Fourth quarter and full-year adjusted net income attributable to owners of the
Company(*) were $22.2 million ($0.24 per share on a diluted basis) and $83.5 million
($0.91 per share on a diluted basis), respectively
• Capital expenditures were nearly $90 million in the fourth quarter as construction
activity related to the Company's strategic growth initiatives ramped up. Full-year
capital expenditures, including deposits on contracts, were just under $300 million,
below 2022 capital expenditure guidance of $308 million to $354 million, primarily
TSX: ERO
NYSE: ERO
1 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
due to the success of Project Honeypot and subsequent deferral of the delivery date
for the new external shaft of Pilar Mine
• Available liquidity at year-end was $392.4 million, including cash and cash equivalents
of $177.7 million , short-term investments of $139.7 million, and $75.0 million of
undrawn availability under the Company's senior secured revolving credit facility.
Subsequent to year-end, the Company extended the maturity and increased the size of
its senior secured revolving credit facility to $150.0 million, resulting in pro forma year-
end liquidity of $467.4 million
• 2023 production, operating cost, and capital expenditure guidance reaffirmed
*These are non-IFRS measures and do not have a standardized meaning prescribed by IFRS
and might not be comparable to similar financial measures disclosed by other issuers. Please
refer to the Company’s discussion of Non-IFRS measures in its Management’s Discussion and
Analysis for the year ended December 31, 2022 and the Reconciliation of Non-IFRS Measures
section at the end of this press release.
TSX: ERO
NYSE: ERO
2 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
“Our 2022 financial results showcase record production levels amidst a backdrop of
inflationary pressures experienced across the global mining industry over the past year ,” said
David Strang, Chief Executive Officer. “Despite encountering some unique obstacles related
to our domestic smelter that necessitated a higher allocation of copper concentrate sales to
the export market, resulting in reduced tax benefits during the year, we resumed domestic
sales on a limited basis subsequent to year-end. With the added benefit of higher metal
prices, we are witnessing stronger-than-expected operating margins as we enter 2023 and
are well-positioned to execute on our growth strategy.
"At our Tucumã Project, road upgrade and drainage infrastructure completed at the end of the
third quarter allowed us to build momentum during the rainy season with minimal down-
time. As of year-end, we reached just over 20% physical completion and are ahead of
schedule on pre-stripping activities. As a result of these efforts, we were able to commence
concrete pours for the plant foundation subsequent to year-end.
"At the Pilar Mine, we revised our timeline for the new external shaft following the success of
Project Honeypot and updates to Caraíba's Strategic Life-of-Mine Plan. The Project Honeypot
stopes added to our production plan have allowed us to maintain high margins while
smoothing our capital profile during construction of the shaft, for which the delivery date has
been deferred by approximately nine months.
"Given the scarcity of new copper development projects and extraordinary demand
anticipated from global decarbonization efforts, the timing of our near-term growth plans is
highly favorable. With these unprecedented market conditions as well as nearly $470 million
in balance sheet liquidity as of February 2023, we remain focused on delivering peer-leading
growth."
TSX: ERO
NYSE: ERO
3 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
FOURTH QUARTER & FULL-YEAR REVIEW
• Mining & Milling Operations
◦ The Caraíba Operations achieved record full-year production of 46,371 tonnes of
copper in concentrate, following strong year-end operating performance driven by
the addition of high-grade Project Honeypot stopes to the fourth quarter
production plan
– Higher mined and process copper grades during the fourth quarter resulted
in copper production of 12,664 tonnes in concentrate, representing an
increase of approximately 13% compared to the third quarter
– Full-year copper production exceeded 2022 copper production guidance
range of 43,000 to 46,000 tonnes and reflect a year-on-year increase to
mill throughput of nearly 500,000 tonnes of ore
◦ The Xavantina Operations delivered record quarterly and full-year gold production
of 11,786 and 42,669 ounces, respectively
– Fourth quarter gold production benefited from higher processed gold
grades of 10.17 grams per tonne ("gpt"), representing an increase in grade
of nearly 20% compared to the prior quarter
– Full-year gold production, which surpassed 2022 gold production guidance
range of 39,000 to 42,000 ounces, increased approximately 13% year-on-
year due to higher mill throughput as well as higher mined and processed
gold grades
• Organic Growth Projects
◦ The Company continued to progress the construction of the Tucumã Project, which
is advancing on schedule with over 20% physical completion achieved as of year-
end
– Mine pre-stripping accelerated during Q4 2022 with approximately 1.6
million tonnes of pre-stripping completed as of year-end, or approximately
12% of total. Waste dump construction is progressing on schedule with
completion expected in Q3 2023
– Completion of the on-site concrete batch plant and mobilization of the civil
works contractor occurred subsequent to year-end with first foundations
poured in February 2023
– Approximately 55% of planned capital expenditures were under contract as
of year-end, up from approximately 30% at the end of Q3 2022. An
additional 25% of Feasibility Study capital expenditures remain in various
stages of tendering or negotiation. Consistent with Q3 2022 project capital
forecasts, total planned capital expenditures remain within 12% of pre-
contingency Feasibility Study as of year-end
TSX: ERO
NYSE: ERO
4 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
– In partnership with The National Service for Industrial Training, a Brazilian
non-profit organization focused on improving the competitiveness of Brazil's
manufacturing sector through technical and vocational education, the
Company commenced comprehensive training programs within the city of
Tucumã and surrounding communities to further develop skills within the
local community that are expected to support the development and
operation of the Tucumã Project
◦ During the quarter, the Company's Pilar 3.0 initiative was significantly bolstered by
the success of Project Honeypot as reflected in the Caraíba Operations' 2022
Strategic Life-of-Mine ("LOM") Plan (please refer to press release dated November
7, 2022). Project Honeypot, an engineering initiative focused on recovering higher-
grade material in the upper levels of the Pilar Mine, is one of three projects that
together are expected to enable the creation of a two-mine system at the Pilar
Mine. The other two components of Pilar 3.0 include (i) construction of a new
external shaft to access the Deepening Extension Zone and (ii) an expansion of the
Caraíba mill to 4.2 million tonnes per annum
– The addition of Project Honeypot into the LOM Plan drove a significant
increase to the Caraíba Operations' estimated mineral resources, mineral
reserves and mine life, allowing the Company to defer the delivery date of
the new external shaft by approximately nine months without impacting
expected copper production
– Construction of the new external shaft continued to advance well against
the revised timeline with physical completion at approximately 20% as of
year-end and approximately 35% of planned capital expenditures under
contract or in the final stages of negotiation. Based upon current capital
expenditure forecasts which reflect additional supplier and contractor
quotes, construction of the new external shaft remains on budget
– The Caraíba mill expansion remains on schedule with completion expected
in Q4 2023
TSX: ERO
NYSE: ERO
5 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
Figure 1: Tucumã Project pre-stripping progress (February 2023).
Figure 2: Aerial view of future Tucumã Project processing areas, including (A) primary crushing, (B) secondary
and tertiary crushing, and (C) plant and administrative buildings.
TSX: ERO
NYSE: ERO
6 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
• Subsequent Events
◦ In January 2023, the Company entered into a zero-cost collar program on 3,000
tonnes of copper per month for February through December of 2023. The collars
establish a floor price at $3.50 per pound of copper on total hedged volumes of
33,000 tonnes of copper, representing approximately 75% of full-year production
volumes. The program protects a meaningful portion of the Company's revenue at
the Company's 2023 budget copper price which was used for capital, cash flow
and liquidity planning purposes, while providing upside to increases in the copper
price up to a cap of $4.76 per pound - within 5% of the all-time high copper price.
The hedge contracts are financially settled on a monthly basis.
◦ Subsequent to year-end, the Company also closed its amended senior secured
revolving credit facility (the "Amended Senior Credit Facility"), increasing its
capacity from $75.0 million to $150.0 million and extending the maturity from
March 2025 to December 2026. The Company also achieved improved terms on
the Amended Credit Facility, including a 25 basis point reduction to the applicable
margin on drawn funds and reduced standby fees on undrawn commitments.
TSX: ERO
NYSE: ERO
7 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada
OPERATING AND FINANCIAL HIGHLIGHTS
3 months
ended
Dec. 31, 2022
3 months
ended
Sep. 30, 2022
3 months
ended
Dec. 31, 2021
12 months
ended
Dec. 31, 2022
12 months
ended
Dec. 31, 2021
Operating Highlights
Copper (Caraíba Operations)
Ore Processed (tonnes) 745,850 720,725 646,319 2,864,230 2,370,571
Grade (% Cu) 1.84 1.68 2.01 1.76 2.08
Cu Production (tonnes) 12,664 11,189 11,918 46,371 45,511
Cu Production (000 lbs) 27,918 24,669 26,275 102,230 100,333
Cu Sold in Concentrate (tonnes) 13,301 10,522 12,393 46,816 45,717
Cu Sold in Concentrate (000 lbs) 29,323 23,197 27,321 103,211 100,788
C1 cash cost of Cu produced (per lb)(1) $ 1.41 $ 1.46 $ 0.96 $ 1.36 $ 0.77
Gold (Xavantina Operations)
Au Production (oz) 11,786 10,965 8,544 42,669 37,798
C1 cash cost of Au Produced (per oz)(1) $ 445 $ 537 $ 582 $ 560 $ 525
AISC of Au produced (per oz)(1) $ 1,096 $ 1,135 $ 910 $ 1,124 $ 732
Financial Highlights ($ in millions, except per share amounts)
Revenues $ 116.7 $ 85.9 $ 134.9 $ 426.4 $ 489.9
Gross profit 52.7 22.8 84.4 187.2 318.9
EBITDA(1) 58.7 27.9 80.7 218.6 296.4
Adjusted EBITDA(1) 58.2 32.1 86.8 208.6 331.9
Cash flow from operations 34.0 43.0 66.7 143.4 364.6
Net income 22.5 4.0 60.2 103.1 202.6
Net income attributable to owners of the Company 22.2 3.7 59.8 101.8 201.1
Per share (basic) 0.24 0.04 0.67 1.12 2.27
Per share (diluted) 0.24 0.04 0.65 1.10 2.21
Adjusted net income attributable to owners of the
Company(1) 22.2 4.0 59.7 83.5 215.4
Per share (basic) 0.24 0.04 0.67 0.92 2.43
Per share (diluted) 0.24 0.04 0.65 0.91 2.37
Cash, cash equivalents, and short-term investments 317.4 359.8 130.1 317.4 130.1
Working capital(1) 263.3 343.2 86.0 263.3 86.0
Net (cash) debt(1) 100.7 51.5 (70.9) 100.7 (70.9)
(1) EBITDA, Adjusted EBITDA, Adjusted net income (loss) attributable to owners of the Company, Adjusted net
income (loss) per share attributable to owners of the Company, Net (Cash) Debt, Working Capital, C1 cash
cost of copper produced (per lb), C1 cash cost of gold produced (per ounce) and AISC of gold produced (per
ounce) are non-IFRS measures. These measures do not have a standardized meaning prescribed by IFRS and
might not be comparable to similar financial measures disclosed by other issuers. Please refer to the
Company’s discussion of Non-IFRS measures in its Management’s Discussion and Analysis for the year ended
December 31, 2022 and the Reconciliation of Non-IFRS Measures section at the end of this press release.
TSX: ERO
NYSE: ERO
8 Ero Copper Corp
625 Howe Street | Suite 1050 | Vancouver | BC | V6C 2T6 | Canada