Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

EQX.TO ·

NEWS RE LEASE Equinox Gold Energizes Crusher at Aurizona Gold Mine, Commences Commissioning

Mine Development & Operations

TSX-V: EQX

OTC: EQXFF

Suite 730 – 800 West Pender St., Vancouver, BC Canada V6C 2V6

[email protected] +1 604.558.0560 www.equinoxgold.com

NEWS RE LEASE

Equinox Gold Energizes Crusher at Aurizona Gold Mine, Commences Commissioning

December 20, 2018 – Vancouver, BC – Equinox Gold Corp. (TSX-V: EQX, OTC: EQXFF) (“E quinox Gold” or the

“Company”) is pleased to report that the new crusher at its Aurizona Gold Mine in Brazil (“Aurizona”) has been

energized and dry tested with the expectation of putting first ore through the system in early January 2019.

The project is nearly complete and on schedule to achieve commercial production around the end of Q1-2019.

• C

rusher circuit including vibrating feeder has been energized and dry tested

• Commissioning team ramping up and training programs are underway

• Engineering and procurement activities are complete

• Tailings storage facility is complete

• Powerline sub-station upgrades are complete and awaiting final verification by the state utility

• Ancillary buildings and facilities are complete

• At the end of November, processing plant construction was 90% complete

- Concrete work is complete

- S

tructural steel erection is 96% complete

- Equipment and plate work installation is 86% complete

- Piping is 76% complete

- E lectrical and instrumentation is 50% complete

• Pre-production mining is nearing completion

- More than 6.4 million tonnes of material moved

- 730,000 tonnes of ore stockpiled and ready for commissioning

The construction team is focused on piping, electrical and instrumentation. T he main transmission line is ready to

provide full energization to all equipment, and site-wide distribution circuits to local electrical rooms are being

commissioned to enable testing of individual equipment components.

Equinox Gold commenced full -scale construction at Aurizona in January 2018 and pre -production mining in April

2018. Approximately US$116 million was spent at the end of November 30, 2018 , including fiscal 2017 spending

related to construction activities . The project remains fully funded . In addition to existing cash reserves, the

Company has US$10 million remaining to draw against its US$85 million construction credit facility.

Construction progress at Aurizona is documented in a photo gallery on Equinox Gold’s website at

www.equinoxgold.com and a number of photos are included at the end of this news release.

On Behalf of the Board of Equinox Gold Corp.

“Christian Milau”

CEO & Director

Equinox Gold Contacts

Christian Milau, CEO & Director

Rhylin Bailie, Vice President Investor Relations

Tel: +1 604-558-0560

Email: [email protected]

- 2 -

Aerial view of Aurizona Plant (foreground) and ore stockpile (background)

Crusher

CIP Tanks

Thickener

Process Water

Ore Stockpile

CN Destruct

Crusher

Piaba Open Pit

Surge Bin

SAG and

Ball Mills

Leach Tanks

Electrical

Substation

Reagents

- 3 -

SAG and ball mills

Crusher (left), surge bin (centre), thickener (right), SAG and ball mill (top)

- 4 -

Mining fleet

About Equinox Gold

Equinox Gold is a Canadian mining company with a multi-million-ounce gold reserve base, gold production from its

Mesquite Gold Mine in California, and near- term production growth from two past -producing mines in Brazil and

California. Construction is well advanced at the Company’s Aurizona Gold Mine in Brazil with the objective of

achieving commercial production around the end of Q1 -2019, and the Company is advancing its Castle Mountain

Gold Mine in California with the objective of ram ping-up Phase 1 operations in early 2020. Further information

about Equinox Gold’s portfolio of assets and long-term growth strategy is available at www.equinoxgold.com or by

email at [email protected].

Cautionary Notes and Forward-Looking Statements

Neither the TSX Venture Exchange nor its Regulation Services Provider (as such term is defined in the policies of the TSX Venture

Exchange) accepts responsibility for the adequacy or accuracy of this release.

This document contains certain forward-looking information and forward-looking statements within the meaning of applicable

securities legislation (collectively “forward -looking statements”). A ll statements other than statements of historical fact are

forward-looking statements. The use of the words “expect ation”, “on track ”, “ around the end”, “underway”, “awaiting”,

“nearing”, “ ready”, “enable”, “objective”, “advancing” and similar expressions are intended to identify forward- looking

statements. Forward-looking statements contained in this news release include, but are not limited to, statements regarding

construction activities underway at Aurizona, anticipated production from the Aurizona Gold Mine and Castle Mountain Gold

Mine and the growth potential of the Company. Although the Company believes that the expectations reflected in such forward-

looking statements and/or information are reasonable, undue reliance should not be placed on forward- looking statements

since the Company can give no assurance that such expectations will prove to be correct. These statements involve known and

unknown risks, uncertainties and other factors that may cause actual results or events to differ materially from those anticipated

in such forward -looking statements, including the risks, uncertainties and other factors identified in the Company ’s periodic

filings with Canadian securities regulators, and as sumptions made with regard to the Company’s ability to complete

construction at Aurizona and achieve production, and the timing to achieve production; the Company’s ability to advance Castle

Mountain and achieve production, and the timing to achieve production; the Company ’s ability to successfully operate

Mesquite; and the Company’s ability to achieve its expected growth and production potential. Furthermore, the forward-looking

statements contained in this news release are made as at the date of this news release and the Company does not undertake

any obligations to publicly update and/or revise any of the included forward- looking statements, whether as a result of

additional information, future events and/or otherwise, except as may be required by applicable securities laws.