Equinox Gold's Greenstone Project: On Schedule, On Budget All dollar amounts shown in United States dollars

Corporate Updates

Equinox Gold's Greenstone Project: On

Schedule, On Budget

All dollar amounts shown in United States dollars unless otherwise noted

Vancouver, British Columbia--(Newsfile Corp. - August 1, 2023) -

Equinox Gold Corp.

(TSX: EQX)

(NYSE American: EQX) is pleased to provide an update on construction progress at its Greenstone

Project in Ontario, Canada. The Greenstone Project is being developed as a 60/40 partnership,

respectively, by Equinox Gold and Orion Mine Finance Group and will be one of the largest gold mines in

Canada, with average annual gold production of more than 400,000 ounces over the first five years and

more than five million ounces of gold over its initial 14-year mine life.

Greenstone Project construction progress is documented weekly in a photo gallery on Equinox Gold's

website at

www.equinoxgold.com

and select photos are included in this news release.

Recent Highlights

(at July 21, 2023 unless otherwise noted)

Schedule

- The Greenstone Project is 85% complete. A third independent quantitative risk

assessment completed in Q2 2023 concluded that the Greenstone Project remains on schedule to

pour gold in the first half of 2024.

Budget

- The Greenstone Project remains on track for a total spend of $1.23 billion. At June 30,

2023, $937 million (76%) of the budget had been spent (100% basis) with approximately $170

million remaining for Equinox Gold's share to fund through to project completion.

Facilities completed

- With construction of the following facilities completed, the operations team

has assumed responsibility for the permanent effluent water treatment plant, truck shop,

warehouse, sewage treatment plant, potable water treatment plant, pit and plant site fuel stations,

reagent storage, and site mixed emulsion (explosives) plant. The new Ministry of Transportation

patrol yard was turned over to the Ministry and dismantling of the old patrol yard is complete. The

natural gas pipeline to site has been commissioned and is operational.

Construction progress

- All major equipment is now on site. Mechanical installations are 75%

complete and electrical and piping installations are both 67% complete. Power plant construction

is complete and pre-commissioning commenced in Q2 2023. The Highway 11 relocation is

substantially complete and ahead of schedule, with handover planned for Q3 2023. With all

auxiliary facilities now handed over to operations, the remaining construction effort is focused on

completion of the process plant and tailings storage facility.

Pre-production mining

- The first two Epiroc Pit Viper 235 drill rigs and the eighth CAT 793F

haul truck were commissioned during the quarter. Mine pre-production activities have been

operating 24/7 since Q4 2022, with more than 10.6 million tonnes of material moved to date. The

current priority for mined material continues to be supplying waste rock for the tailings storage

facility and other construction activities. Mining of ore for the commissioning stockpile is expected

to commence in Q4 2023.

Commissioning and operational readiness

- The commissioning team and commissioning

plans are in place and operational readiness activities are underway.

Greg Smith, President & CEO of Equinox Gold, commented: "The Greenstone Project continues to

advance on budget and on schedule. With most ancillary facilities complete and transferred to the

operations team and construction activities 83% complete, our focus is shifting toward commissioning

and operational readiness as we advance to construction completion and first gold pour in the first half of

2024, and then achieving commercial production."

Results of Independent Quantitative Risk Assessment

Valency Inc., a global provider of construction project assurance solutions and quantitative risk

assessments, completed the Greenstone Project's second quantitative risk assessment ("QRA") during

Q2 2023. The QRA concluded that the schedule and budget remain achievable, and the Greenstone

Project remains on track to pour gold in the first half of 2024.

An update on Greenstone 2024 operating costs and production estimates will be reported in connection

with the Company's annual production and cost guidance in Q1 2024.

Greenstone Project Progress

Area

Progress to Date

(at July 21, 2023 unless otherwise noted)

Total Overall Progress

Overall project 85% complete and on schedule to pour gold in the first half of 2024

Detailed engineering complete

Procurement 87% complete

Construction 83% complete

Plant site earthworks 97% complete, concrete 93% complete, structural steel 89% complete, mechanical

installations 75% complete, piping installations 67% complete, electrical installations 67% complete

Safety

Strong health and safety performance with project-to-date Total Recordable Injury Frequency Rate

1

at June 30,

2023 of 3.19 per million hours worked

Budget

Project remains on budget. At June 30, 2023:

76% of total cost spent ($937 M)

All purchase order and construction contracts for project completion in place

Inflationary pressures have been mitigated through favourable exchange rates and offsetting savings

opportunities, or absorbed through the $177 million contingency included in the construction budget

Process Plant

Process plant construction 75% complete

All major equipment delivered to site

Installation of various crushing and grinding equipment is advanced, including work on the ball mills and high

pressure grinding rolls (HPGR). Crusher retaining wall complete

Four of the six conveyors erected with the other two in process

Structures completed in the gravity tower, acid wash, elution and carbon regeneration areas. Gold room

concrete block walls completed with most electrical and mechanical equipment in place

A significant number of subsystems in the process plant will be mechanically complete by the end of Q3 2023

Tailings Facility and Water

Management

Tailings storage facility 80% complete with dams in the East and Southeast areas at the target elevation of

337.0 metres

Tailings and reclaim piping and pipeline corridor installation underway

Power Plant and Electrical

Pre-commissioning activities underway; on track to be commissioned in Q3 2023

Natural gas pipeline to site complete and operational

Site Infrastructure

Truck shop, warehouse, administration office, pit and plant site fuel stations, sewage treatment plant, potable

water treatment plant, site mixed emulsion (explosives) plant, and reagent cold storage buildings complete and

operational

Mobile Equipment and

Mining

Mine pre-production activities operating 24/7 and in line with plan, with more than 10.6 million tonnes of

material moved to date

Eight CAT 793F trucks, two Epiroc D65 drills, two Epiroc Pit Viper 235 drill, one Komatsu PC5500 shovel and

two Komatsu D375A-8 bulldozers on site

Infrastructure Repositioning

Highway 11 relocation ahead of schedule and near complete

Earthworks underway for the new Hydro One Geraldton Operating Centre; completion targeted for Q1 2024.

Planning for the Substation relocation in 2024 underway

Commissioning and

Operational Readiness

Commissioning team in place; managing power plant commissioning and preparing for process plant

commissioning activities to begin in Q4 2023

Plant operational readiness activities are focused on hiring, procedures, systems implementation, procurement

activities to support start up, and training

Recruitment on track with over 200 operations personnel hired to date

Capital spares purchases complete, ordering of operating spares well advanced

1

Total Recordable Injury Frequency Rate is the total number of injuries excluding those requiring simple first aid treatment.

Remaining Project Milestones

Important construction milestones include:

Process plant steel erection underway: June 2022

Administration building complete: July 2022

Delivery and assembly of pre-production fleet of four trucks and excavators: Q2-Q3 2022

Permanent water effluent treatment plant ready for use: Q3 2022

Commence installation of gensets in power plant, power building enclosed: Q3 2022

Start of pre-production mining: Q3 2022

All main buildings enclosed: Q1 2023

Leach tanks installed: Q4 2022

Ball mills received and installed: Q1-Q3 2023

Highway 11 realignment complete: August 2023

Crushers installed: Q3 2023

Commence pre-commissioning of crushing circuit: Q4 2023

Power plant operational: Q4 2023

Tailing storage facility complete and ready for use: Q4 2023

Commissioning: Q1-Q2 2024

Gold pour: H1 2024

Equinox Gold Contacts

Greg Smith, President & CEO

Rhylin Bailie, Vice President, Investor Relations

Tel: +1 604-558-0560

Email:

[email protected]

Construction Photos

Project overview - July 21

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/9355/175576_9d7fdfc8e4169a64_001full.jpg

Plant site overview - July 21

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/9355/175576_9d7fdfc8e4169a64_002full.jpg

Crushers and crusher area retaining wall

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/9355/175576_9d7fdfc8e4169a64_003full.jpg

Conveyors between crusher and HPGR buildings

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/9355/175576_9d7fdfc8e4169a64_004full.jpg

East end - ball mills

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/9355/175576_9d7fdfc8e4169a64_005full.jpg

High pressure grinding rolls (HPGR) installation

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/9355/175576_9d7fdfc8e4169a64_006full.jpg

Pre-leach thickener

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/9355/175576_9d7fdfc8e4169a64_007full.jpg

Cable pulls on leach tanks

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/9355/175576_9d7fdfc8e4169a64_008full.jpg

West end - carbon in pulp area

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/9355/175576_9d7fdfc8e4169a64_009full.jpg

Power plant

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/9355/175576_9d7fdfc8e4169a64_010full.jpg

Cautionary Notes

This news release contains certain forward-looking information and forward-looking statements within

the meaning of applicable securities legislation. Forward-looking statements and forward-looking

information in this news release relate to, among other things: the Company's ability to successfully

advance construction and achieve production at Greenstone; the Company's expectations regarding

construction timelines and costs for Greenstone, including its ability to manage inflationary pressures;

and the Company's expectations for the operation of Greenstone, including production capabilities

and future financial or operating performance. Forward-looking statements or information generally

identified by the use of the words "will", "advance", "progress", "on track", "on schedule", "on budget",

"remain", "plan", "continue", "expect", and similar expressions and phrases or statements that certain

actions, events or results "could", "would" or "should", or the negative connotation of such terms, are

intended to identify forward-looking statements and information. Although the Company believes that

the expectations reflected in such forward-looking statements and information are reasonable, undue

reliance should not be placed on forward-looking statements since the Company can give no

assurance that such expectations will prove to be correct. The Company has based these forward-

looking statements and information on the Company's current expectations and projections about

future events and these assumptions include: construction and development at Greenstone being

completed and performed in accordance with current expectations, including estimated capital costs;

prices for energy inputs, labour, materials, supplies and services, and the impact of inflation on the

same, remaining as expected; the timely delivery and commissioning of equipment; availability of

funds for the Company's projects and future cash requirements; capital, decommissioning and

reclamation estimates; Greenstone Mineral Reserve and Mineral Resource estimates and the