Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

EQX.TO ·

Equinox Gold's Greenstone Project: 96% Complete, Commissioning Underway All dollar amounts shown in United States dollars

Mine Development & Operations

Equinox Gold's Greenstone Project: 96%

Complete, Commissioning Underway

All dollar amounts shown in United States dollars unless otherwise noted

Vancouver, British Columbia--(Newsfile Corp. - November 20, 2023) -

Equinox Gold Corp.

(TSX:

EQX) (NYSE American: EQX) is pleased to provide an update on construction and commissioning

progress at its Greenstone Project in Ontario, Canada. The Greenstone Project is being developed as a

60/40 partnership, respectively, by Equinox Gold and Orion Mine Finance Group, and will be one of the

largest gold mines in Canada, with average annual gold production of more than 400,000 ounces over

the first five years and more than five million ounces of gold produced over its initial 14-year mine life.

Greenstone Project construction progress is documented weekly in a photo gallery on Equinox Gold's

website at

www.equinoxgold.com

and select photos are included in this news release.

Recent Highlights

(at November 10, 2023 unless otherwise noted)

Schedule

- The Greenstone Project is 96% complete. Pre-commissioning

1

activities are ongoing

in most of the main process plant areas, including the crushing and grinding circuits, and wet

commissioning

1

is underway in select areas.

Budget

- The Greenstone Project remains on track for a total spend of $1,225 million. At

September 30, 2023, $1,087 million (89%) of the budget had been spent (100% basis).

Facilities completed

- The realigned 4.7 km of Highway 11 was opened to traffic in August and

the power plant was turned over to the operations team in September, both ahead of plan. The

permanent effluent water treatment plant, truck shop, warehouse, sewage treatment plant, potable

water treatment plant, pit and plant site fuel stations, reagent storage, site mixed emulsion

(explosives) plant and natural gas pipeline to site were previously turned over and are all in

operation.

Construction progress

- All major equipment is now on site and construction is 96% complete.

The focus is on remaining electrical and instrumentation installations in the process plant. In

October, the tailings storage facility ("TSF") was completed to planned elevation. Commissioning

of the TSF is on track for December 2023.

Commissioning

- Pre-commissioning activities are ramping up in coordination with final

construction activities, with systems checks underway at the crusher, ball mills, ore storage dome

and high-pressure grinding rolls ("HPGR") areas. Wet commissioning has commenced at the

leach tanks and in the crusher area.

Pre-production mining

- The third Epiroc Pit Viper 235 drill has been commissioned.

Commissioning of CAT 793F haul trucks 9 and 10 is underway, and haul trucks 11 to 14 and the

LeTourneau 1850 loader will be ready for service in early Q1 2024. More than 15 million tonnes of

material has been moved to date and build-up of the ore stockpile is ahead of plan and on track to

exceed the 800,000 tonnes start-up target.

Operational readiness

- Operational readiness activities and hiring are progressing in-line with

plan. An update on Greenstone 2024 operating costs and production estimates will be reported in

connection with the Company's annual production and cost guidance in Q1 2024.

Greg Smith, President & CEO of Equinox Gold, commented: "With the Greenstone Project 96%

complete and the power plant fully operational, the priority is now on completion and commissioning of

the process plant, commissioning of the TSF and ramp up of mining and operations. The project

continues to advance on budget and on schedule. We look forward to pouring gold in the first half of

2024 and then achieving commercial production."

Greenstone Project Progress

Area

Progress to Date

(at November 10, 2023 unless otherwise noted)

Total Overall Progress

Overall project 96% complete and on schedule to pour gold in the first half of 2024

-

Detailed engineering complete

-

Procurement 92% complete

-

Construction 96% complete

Safety

Continued strong health and safety performance with project-to-date Total Recordable Injury Frequency Rate

2

at October 27, 2023 of 3.72 per million hours worked

5.3 million hours worked with one lost-time injury

Budget

Project remains on budget. At September 30, 2023:

-

89% of total cost spent ($1,087 million)

-

All purchase orders and construction contracts for project completion in place

-

Inflationary pressures have been mitigated through favourable exchange rates and offsetting savings

opportunities, or absorbed through the $177 million contingency included in the construction budget

Process Plant

Process plant construction 96% complete

All major equipment installations including the ball mills, HPGR and conveyors are complete, with final work on

piping and electrical underway

Demobilization of structural and mechanical contractors has commenced

Full process plant commissioning team and plans in place

All electrical rooms are energized

Pre-commissioning activities are ongoing in most of the main process plant areas, including the crushing and

grinding circuits

Wet commissioning of the leach tanks and crushing circuit has commenced

Compressed air and gland water distribution have been commissioned to support commissioning activities in

other areas

Tailings Facility and Water

Management

TSF complete to the planned start-up elevation of 340 metres

Construction of the spillway and pipe corridor extension is nearing completion

Upstream buttress complete, downstream buttress will be complete by year end

All TSF construction required for commissioning is complete and commissioning is on track for December 2023

Site Infrastructure

Truck shop, warehouse, administration office, pit and plant site fuel stations, sewage treatment plant, potable

water treatment plant, site mixed emulsion (explosives) plant, and reagent cold storage building complete and

operational

On-site power plant fully operational and providing power to all site infrastructure

Mobile Equipment and

Mining

Mine pre-production activities operating 24/7 and on plan, with more than 15 million tonnes of material moved

to date

Ten CAT 793F trucks, two Epiroc D65 drills, three Epiroc Pit Viper 235 drills, two Komatsu PC5500 shovels and

four Komatsu D375A-8 bulldozers in service

Mining of ore for the commissioning stockpile is ahead of plan and on track to exceed the 800,000 tonnes

planned for start-up, with 630,000 tonnes stockpiled at November 16

Operational Readiness

Plant operational readiness activities including hiring, procedures development, systems implementation,

procurement activities, and training are on plan

100% of capital spares and operating spares purchased, deliveries in progress

Workforce

All key operations positions are filled

More than 290 operations personnel hired to date, with 30% of personnel self-identified as having Indigenous

ancestry

Demobilization of contractor workforce underway

Infrastructure Repositioning

Highway 11 relocation completed ahead of schedule and opened to traffic in August

Foundation for the Hydro One Geraldton Operating Centre is complete and building erection is underway

Planning for the Hydro One substation relocation in 2024 underway; all long lead equipment has been

purchased, with many items delivered or ready for delivery

Remaining Project Milestones

Remaining milestones to achieve production include:

Tailing storage facility complete and ready for use: December 2023

Process plant hot commissioning

1

: Q1-Q2 2024

Gold pour: H1 2024

Equinox Gold Contacts

Greg Smith, President & CEO

Rhylin Bailie, Vice President, Investor Relations

Tel: +1 604-558-0560

Email:

[email protected]

__________________________

1

Pre-commissioning

is the completion of the construction phase for each equipment and system, including the completion of all inspection test

plans, confirmation of all motors and rotations, and confirmation of all signals from equipment and instruments to the control systems.

Wet

commissioning

includes a dry run of equipment, running motors, vibration and temperature monitoring, loop tests, and testing of safety devices,

interlocks and speed control.

Hot commissioning

follows wet commissioning with the introduction of reagents and ore.

2

Total Recordable Injury Frequency Rate is the total number of injuries excluding those requiring simple first aid treatment.

Construction Photos

Plant site

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/9355/187993_d781aa9974fb0a47_001full.jpg

Pit and plant site

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/9355/187993_d781aa9974fb0a47_002full.jpg

Primary and secondary crushers

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/9355/187993_d781aa9974fb0a47_003full.jpg

High pressure grinding rolls (HPGR) building

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/9355/187993_high_pressure_grindingrollshpgrbuilding.jpg

Ball mills and screens

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/9355/187993_d781aa9974fb0a47_005full.jpg

Pre-leach thickener, process plant and conveyors

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/9355/187993_d781aa9974fb0a47_006full.jpg

Cautionary Notes

This news release contains certain forward-looking information and forward-looking statements within

the meaning of applicable securities legislation. Forward-Looking statements and forward-looking

information in this news release relate to, among other things: the Company's ability to successfully

advance construction and achieve production at Greenstone; the Company's expectations regarding

construction timelines and costs for Greenstone, including its ability to manage inflationary pressures;

and the Company's expectations for the operation of Greenstone, including production capabilities

and future financial or operating performance. Forward-Looking statements or information generally

identified by the use of the words "will", "advance", "progress", "on track", "on schedule", "on budget",

"on plan", "achieve", "remain", "plan", "continue", "expect", and similar expressions and phrases or

statements that certain actions, events or results "could", "would" or "should", or the negative

connotation of such terms, are intended to identify forward-looking statements and information.

Although the Company believes that the expectations reflected in such forward-looking statements

and information are reasonable, undue reliance should not be placed on forward-looking statements

since the Company can give no assurance that such expectations will prove to be correct. The

Company has based these forward-looking statements and information on the Company's current

expectations and projections about future events and these assumptions include: construction and

development at Greenstone being completed and performed in accordance with current expectations,

including estimated capital costs; prices for energy inputs, labour, materials, supplies and services,

and the impact of inflation on the same, remaining as expected; the timely delivery and

commissioning of equipment; availability of funds for the Company's projects and future cash

requirements; capital, decommissioning and reclamation estimates; Greenstone Mineral Reserve

and Mineral Resource estimates and the assumptions on which they are based; the ability to realize

cost savings through leasing of mobile equipment; prices for gold remaining as estimated; no labour-

related disruptions and no unplanned delays or interruptions in scheduled construction, development,

commissioning, and production; all necessary permits, licenses and regulatory approvals are

received in a timely manner; the Company's ability to work effectively with its joint venture partner;

successful relationships between the Company and its Indigenous partners at Greenstone; and the

Company's ability to comply with environmental, health and safety laws. While the Company

considers these assumptions to be reasonable based on information currently available, they may

prove to be incorrect. Accordingly, readers are cautioned not to put undue reliance on the forward-

looking statements or information contained in this news release.

The Company cautions that forward-looking statements and information involve known and unknown

risks, uncertainties and other factors that may cause actual results and developments to differ

materially from those expressed or implied by such forward-looking statements and information

contained in this news release and the Company has made assumptions and estimates based on or

related to many of these factors. Such factors include, without limitation: fluctuations in gold prices;

fluctuations in prices for energy inputs, labour, materials, supplies and services; fluctuations in

currency markets; operational risks and hazards inherent with the business of mining (including

environmental accidents and hazards, industrial accidents, equipment breakdown, unusual or

unexpected geological or structural formations, cave-ins, flooding and severe weather); inadequate

insurance, or inability to obtain insurance to cover these risks and hazards; employee relations;

relationships with, and claims by, local communities and Indigenous partners; the Company's ability

to obtain all necessary permits, licenses and regulatory approvals in a timely manner or at all;

changes in laws, regulations and government practices, including environmental, export and import

laws and regulations; the ability of Equinox Gold to work productively with its joint venture partner and

Indigenous partners at Greenstone; legal restrictions relating to mining; increased competition in the

mining industry; and those factors identified in the section titled "Risks and Uncertainties" in Equinox

Gold's MD&A dated February 21, 2023 for the year ended December 31, 2022 and in the section

titled "Risks Related to the Business" in Equinox Gold's most recently filed Annual Information Form,

both of which are available on SEDAR+ at

www.sedarplus.ca

and on EDGAR at

www.sec.gov/edgar

.

Forward-Looking statements and information are designed to help readers understand management's

views as of that time with respect to future events and speak only as of the date they are made. Except

as required by applicable law, Equinox Gold assumes no obligation to update or to publicly announce

the results of any change to any forward-looking statement or information contained or incorporated by

reference to reflect actual results, future events or developments, changes in assumptions or changes

in other factors affecting the forward-looking statements and information. If Equinox Gold updates any

one or more forward-looking statements, no inference should be drawn that Equinox Gold will make

additional updates with respect to those or other forward-looking statements. All forward-looking

statements and information contained in this news release are expressly qualified in their entirety by

this cautionary statement.

To view the source version of this press release, please visit

https://www.newsfilecorp.com/release/187993