Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

EQX.TO ·

Equinox Gold Provides 2020 Guidance More Than Triples Annualized Gold Production in 2020

Mergers & Acquisitions

TSX: EQX

NYSE-A: EQX

Suite 1501 - 700 West Pender St., Vancouver, BC Canada V6C 1G8

[email protected] +1 604.558.0560 www.equinoxgold.com

NEWS RELEASE

Equinox Gold Provides 2020 Guidance

More Than Triples Annualized Gold Production in 2020

All dollar amounts are expressed in US$

March 31, 2020 – Vancouver, BC – Equinox Gold Corp. (TSX: EQX, NYSE American: EQX) (“Equinox Gold” or the

“Company”) today announces 2020 production and cost guidance of 540,000 to 600,000 ounces (“oz”) of gold

at all-in-sustaining costs1 (“AISC”) of $1,000 to $1,060 per oz. Guidance for the Los Filos, Fazenda, RDM and Pilar

mines reflects production expectations from March 10, 2020, the closing date of the merger with Leagold Mining

Corporation (“Leagold”), to December 31, 2020 . Total consolidated 2020 production, including gold produced

by Leagold in 2020 before completion of the merger, is estimated at 615,000 to 680,000 oz of gold.

“Equinox Gold had another year of tremendous growth in 2019. The Company advanced its Aurizona mine to

production, commenced construction at its Castle Mountain mine and ended 2019 with the announcement of a

merger with Leagold to create a premier gold producer with exceptional growth potential,” said Christian Milau,

CEO of Equinox Gold. “With the merger complete, Equinox Gold expects to more than triple its annualized gold

production in 2020 and is fully funded to increase production over the next two years to more than one million

ounces of gold annually. We also recognize the challenges presented by the COVID-19 pandemic and its potential

effect on our operations and our guidance for this year. If necessary, w e will adjust our expectations as the

situation evolves.”

2020 Guidance and Outlook

Guidance for Los Filos, Fazenda, RDM, Pilar and Santa Luz reflects expectations for the period commencing

March 10, 2020, the closing date of the merger with Leagold, and ending December 31, 2020. The Company may

revise guidance during the year to reflect changes to expected results , including from effects related to the

COVID-19 pandemic.

Production

(oz)

AISC1,2

($/oz)

Sustaining

Capital1

Non-Sustaining

Capital1

Los Filos3 170,000 - 190,000 $1,000 - $1,050 $24 M $51 M

Aurizona 115,000 - 125,000 $1,100 - $1,150 $40 M $11 M

Mesquite 120,000 - 130,000 $975 - $1,025 $8 M $8 M

Fazenda3 55,000 - 60,000 $900 - $950 $7 M $3 M

RDM3 50,000 - 55,000 $1,000 - $1,050 $5 M $17 M

Pilar3 25,000 - 30,000 $1,200 - $1,300 $4 M $2 M

Castle Mountain 5,000 - 10,000 $750 - $800 - $45 M

Santa Luz3 - - - $6 M

Total – Mines 540,000 - 600,000 $1,000 - $1,060 $88 M $143 M

1 AISC per oz sold and sustaining and non-sustaining capital are non-IFRS measures. See Non-IFRS Measures and AISC per Ounce Sold in

Cautionary Notes.

2 Exchange rates used to forecast 2020 AISC include a rate of BRL 4.0 to USD 1 and MXN 19.5 to USD 1.

3 Production costs and capital attributable to Equinox Gold post-merger completion on March 10, 2020.

- 2 -

Consolidated gold production is expected to increase quarter over quarter during the year, with the fourth

quarter benefiting from the addition of gold production from Castle Mountain and the processing of higher -

grade ore at Los Filos.

Los Filos Gold Mine

The Los Filos gold mine in Guerrero State, Mexico began commercial production in 2008 and currently comprises

two open pits (Los Filos and Bermejal) and one underground mine (Los Filos). Ore from all three deposits is

processed using heap leach recovery. Los Filos produced a total of 200,856 oz of gold during 2019 . Los Filos

production for 2020 attributable to Equinox Gold post-merger is estimated at 170,000 to 190,000 oz of gold at

AISC of $ 1,000 to $1,050 per oz of gold sold , with production weighted heavily toward the second half of the

year as the Company accesses ore from the new Bermejal underground mine and new Guadalupe open pit.

The Company is advancing an expansion of the Los Filos mine complex including enlarging the Los Filos open pit,

developing a second underground mine (Bermejal), adding a new open pit (Guadalupe) and constructing a new

carbon in leach (“CIL”) plant to process higher-grade ore. Leagold commenced the expansion project in Q3-2019,

completing an access road to allow the start of stripping from the Guadalupe open pit and commencing work

for additional ventilation for Bermejal underground development. Equinox Gold is evaluating the benefits of

constructing a larger CIL plant than the currently contemplated 4,000 tonnes per day (“t/d”) plant, which would

have an impact on the current feasibility estimate for construction capital of $115 million. Trade-off studies will

be completed in mid-2020 after which the Company will provide an update on the size of and costs to construct

the CIL plant. Construction is currently targeted to commence in H2-2020.

Equinox Gold has budgeted a total capital spend of $ 75 million at Los Filos during 2020. Non -sustaining capital

of $ 51 million relates primarily to the expansion project and includes $20 million for pre -stripping of the

Guadalupe open pit and $23 million allocated to Bermejal underground development. In addition, $3.5 million

is allocated for regional and Guadalupe exploration and $2 million is budgeted for underground step-out drilling.

Of the $24 million budgeted for sustaining capital, $8 million is for major overhauls and rebuilds of the existing

fleet to support Guadalupe stripping, $6 million is allocated for development at the Los Filos underground mine,

$3 million is for processing equipment and $3 million is budgeted for heap leach expansion.

Aurizona Gold Mine

Aurizona is an open-pit gold mine in Maranhão State, Brazil. The Company completed construction in Q2 -2019

and announced commercial production effective July 1, 2019 , producing a total of 75,282 oz during 2019

including pre-commercial production ounces. Aurizona production for 2020 is estimated at 115,000 to 125,000

oz of gold at AISC of $1,100 to $1,150 per oz of gold sold. The increase in AISC compared to 2019 is largely due

to: mine plan scheduling, with ore feed in 2020 slightly below reserve grade ; a waste stripping program in the

open pit; and increased sustaining capital associated with the third tailings facility lift.

Equinox Gold has budgeted a total capital spend of $ 51 million at Aurizona during 2020. Sustaining capital of

$40 million relates primarily to completion of the third tailings facility lift ($13 million) and capitalized stripping

in the open pit ($19 million). Non-sustaining capital of $11 million includes $8 million allocated to exploration.

Mesquite Gold Mine

Mesquite is an open -pit heap leach gold mine in California, USA that Equinox Gold acquired during Q4 -2018.

Mesquite produced a total of 125,736 oz during 2019 at AISC of $933 per oz sold. Mesquite production for 2020

is estimated at 120,000 to 130,000 oz of gold at AISC of $975 to $1,025 per oz of gold sold.

Equinox Gold has budgeted a total capital spend of $ 16 million at Mesquite during 2020. Sustaining capital of

$8 million relates primarily to increasing solution handling infrastructure. Non-sustaining capital of $8 million is

- 3 -

allocated for exploring new targets a nd drilling mineralized dumps to identify economic material that can b e

classified as ore and stacked on the operating leach pads.

Fazenda Gold Mine

Fazenda is an underground mine located in Bahia State, Brazil. Fazenda has been in operation for more than 30

years and produced a total of 73,228 oz of gold during 2019. Fazenda production for 2020 attributable to Equinox

Gold post-merger is estimated at 55,000 to 60,000 oz of gold at AISC of $900 to $950 per oz of gold sold.

Equinox Gold has budgeted a total capital spend of $ 10 million at Fazenda during 2020 . Of the $7 million

allocated to sustaining capital, $4 million is for underground development and $2 million relates to the scheduled

tailings facility raise. The $3 million allocated to non-sustaining capital is primarily for underground development

to allow for exploration drilling with the objective of converting resources to reserves.

RDM Gold Mine

RDM is a conventional open -pit mine located in Minas Gerais State, Brazil. RDM commenced commercial

production in early 2014 and produced a total of 62,634 oz during 2019. RDM production for 2020 attributable

to Equinox Gold post-merger is estimated at 5 0,000 to 55,000 oz of gold at AISC of $1,000 to $1,050 per oz of

gold sold.

Equinox Gold has budgeted a total capital spend of $ 22 million at RDM during 2020. Sustaining capital of

$5 million relates primarily to the scheduled tailings facility raise . Non-sustaining capital of $ 17 million relates

almost entirely to open-pit expansion and capitalized stripping. Permits required to commence the pit expansion

are expected to be received in Q2-2020.

Pilar Gold Mine

Pilar in Goiás State, Brazil consists of two underground mines. Pilar commenced commercial production in

October 2014 and produced a total of 37,739 oz of gold during 2019. Pilar production for 2020 attributable to

Equinox Gold post-merger is estimated at 25,000 to 30,000 oz of gold at AISC of $1,200 to $1,300 per oz of gold

sold.

Equinox Gold has budgeted a total capital spend of $ 6 million at Pilar during 2020. Of the $4 million s ustaining

capital budget, $2 million is allocated for the scheduled tailings facility raise with $1 million budgeted for

underground development. Non-sustaining capital of $2 million is related to permitting and land access for the

Três Buracos deposit, which is scheduled f or permitting in 2020 and subsequent open -pit mining in 2021 to

complement the existing underground mines.

Castle Mountain Gold Project

Castle Mountain is a past-producing open-pit heap leach gold mine in California, USA. A July 2018 prefeasibility

study for the project contemplated a two -phase development plan, with production estimated at 45,000 oz of

gold per year during Phase 1 and more than 200,000 oz of gold per year during Phase 2.

The Company commenced full -scale construction of Phase 1 on October 30, 2019. Construction is more than

50% complete with first gold pour targeted for Q3-2020. Total production for 2020 is estimated at 5,000 to

10,000 oz of gold at AISC of $750 to $800 per oz of gold sold.

Phase 1 will consist of a run-of-mine heap leach operation processing primarily 12,000 t/d of stockpiled ore from

previous operations. The Phase 2 expansion i s estimated to increase production to 200,000 oz per year and

throughput to 41,000 t/d of ore, of which 2,340 t/d of higher-grade ore will be processed through a mill and

- 4 -

carbon-in-leach circuit with the remainder going to the heap leach. The detailed feas ibility study for Phase 2 is

targeted for completion in H2-2020.

Equinox Gold has budgeted $ 45 million of non -sustaining capital at Castle Mountain during 2020 , with

$40 million related to construction and commissioning and $5 million allocated to completion of the Phase 2

feasibility study.

Santa Luz Gold Project

The Santa Luz project in Bahia State, Brazil is a past -producing mine that commenced operations in mid -2013

and was placed on care and maintenance in September 2014 due in part to lower than planned gold recovery.

Leagold completed an updated feasibility study for Santa L uz in October 2018 incorporating resin -in-leach

processing to increase gold recovery with total construction costs estimated at $82 million.

Equinox Gold is reviewing Santa Luz costs and engineering with the expectation of commencing construction in

late 2020 or early 2021. A total of $6 million has been budgeted for Santa Luz care and maintenance and early

construction activities in 2020. Updated capital guidance will be provided when a final construction decision is

made in 2020.

Mineral Reserves and Resources

Equinox Gold will provide an updated mineral reserve and mineral resource estimate in mid-2020.

Qualified Persons

Adriaan (Attie) Roux, Pr.Sci.Nat., Equinox Gold’s COO, Doug Reddy, P.Geo ., Equinox Gold’s E VP Technical

Services, and Scott Heffernan, MSc, P.Geo., Equinox Gold’s E VP Exploration, are the Qualified Persons under

National Instrument 43-101 for Equinox Gold and have reviewed, approved and verified the technical content

of this news release.

About Equinox Gold

Equinox Gold is a Canadian mining company with six producing gold mines, a multi- million-ounce gold reserve

base and a strong growth profile from two development projects and two expansion projects. Equinox Gold

operates entirely in the Americas, with two properties in the United States, one in Mexico and five in Brazil .

Equinox Gold’s common shares are listed on the TSX and the NYSE American under the trading symbol EQX .

Further information about Equinox Gold ’s portfolio of assets and long -term growth strategy is available at

www.equinoxgold.com or by email at [email protected].

Equinox Gold Contacts

Christian Milau, Chief Executive Officer

Rhylin Bailie, Vice President, Investor Relations

Tel: +1 604-558-0560

Email: [email protected]

Cautionary Notes and Forward-looking Statements

Non-IFRS Measures

This news release refers to all -in sustaining costs (“AISC”), AISC per ounce sold and sustaining and non- sustaining capital expenditures

that are measures with no standardized meaning under International Financial Reporting Standards (“IFRS”), i.e. they ar e non -IFRS

measures, and may not be comparable to similar measures presented by other companies. Their measurement and presentation is

intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance

prepared in accordance with IFRS.

- 5 -

AISC per Ounce Sold

AISC per gold oz sold is a non -IFRS measure based on guidance announced by the World Gold Council (“WGC”) in September 2013 and

updated in November 2018. The WGC is a non- profit association of the world’s leading gold mining companies established in 1987 to

promote the use of gold to industry, consumers and investors. The WGC is not a regulatory body and does not have the authorit y to

develop accounting standards or disclosure requirements. The WGC has worked with its member companies to develop a measure that

expands on IFRS measures such as operating expenses and non- IFRS measures to provide visibility into the economics of a gold mining

Company. Current IFRS measures used in the gold industry, such as operating expenses, do not capture all of the expenditures incurred to

discover, develop and sustain gold production. The Company believes the AISC measure provides further transparency into costs associated

with producing gold and will assist analysts, investors and other stakeholders of the Company in assessing its operating performance, its

ability to generate free cash flow from current operations and its overall value. Combined AISC does not include corporate G&A.

Forward-looking Statements

This news release includes certain statements that constitute “forward -looking statements”, and “forward- looking information” within

the meaning of applicable securities laws collectively “forward -looking statements”. These include statements r egarding the growth

potential of the Company. When used in this news release, words such as “will”, “monitoring”, “review”, “adjust”, “adapt”, “growth”,

“guidance”, “plan”, “budget”, “expected”, and similar expressions are intended to identify these forwar d-looking statements as well as

phrases or statements that certain actions, events or results “may”, “could”, “would”, “should”, “occur” or “be achieved” or the negative

connotation of such terms. As well, forward -looking statements may relate to future outlook and anticipated events, such as the

Company’s ability to achieve the 2020 production and cost estimates at its properties , the funding available to the Company, the timing

and likelihood of project development, construction and expansion, the timing and amount of expected future production, the costs of

future production, construction and expenditures, budgets and allocation of budgets, access, drilling and permitting, processing of higher

grade ore, timing and completion of feasibility studies, feasi bility estimates and trade -off studies, timing and completion of updated

reserve and resource estimates, the value of AISC per gold oz, the Company’s plans and protocols with regard to managing potential

impacts related to the COVID-19 pandemic, the Company’s strategy to help keep its workforce and local communities safe, the Company’s

business continuity protocols and the potential impact on operations related to COVID -19, the Company’s ability to maintain activities

and productivity at its operating mines, the Company’s ability to successfully resume operations at mines at which operations have been

restricted or suspended, and the Company’s ability to advance its development and expansion projects and achieve its growth objectives.

These forward-looking statements involve assumptions, numerous risks and uncertainties, certain of which are beyond the Company’s

control including risks associated with or related to the volatility of metal prices and the Company’s shares, there being no significant

disruptions affecting the Company’s operations or projects, risks related to the COVID-19 pandemic including government and health

authority responses and increased regulations and restrictions regarding the flow of labour, materials and impact on the Company’s

business, projects and operations, as well as the risk factors identified in Equinox Gold’s year-end MD&A dated February 28, 2020, which

is available on SEDAR at www.sedar.com and EDGAR at www.sec.gov. Forward-looking statements are based on information available at

the time those statements are made and/or management’s good faith belief as of that time with respect to future events and are subject

to risks and uncertainties that could cause actual performance or results to differ materially from those express ed in or suggested by the

forward-looking statements. Forward-looking statements speak only as of the date those statements are made. The COVID -19 situation

is changing rapidly and Equinox Gold will continue to review and adapt its response protocols as the situation unfolds, applying guidelines

outlined by the World Health Organization and governments of countries within which the Company operates. The extent to which COVID-

19 (or any other disease, epidemic or pandemic) impacts business activity, operatio ns or financial results, and the duration of any such

impact, will depend on future developments that are highly uncertain and cannot be predicted, including new information that may

emerge concerning COVID-19 and the actions required to contain or treat its impact, among others. Except as required by applicable law,

Equinox Gold assumes no obligation to update or to publicly announce the results of any change to any forward- looking statement

contained or incorporated by reference herein to reflect actual results, future events or developments, changes in assumptions or changes

in other factors affecting the forward- looking statements. If Equinox Gold updates any one or more forward- looking statements, no

inference should be drawn that the company will make additional updates with respect to those or other forward-looking statements. All

forward-looking statements contained in this news release are expressly qualified in their entirety by this cautionary statement.