Equinox Gold Commences Processing Ore at Greenstone Project: First Gold Pour on Track for Q2 2024

Production Results Mine Development & Operations

Equinox Gold Commences Processing Ore at

Greenstone Project: First Gold Pour on Track

for Q2 2024

Vancouver, British Columbia--(Newsfile Corp. - April 9, 2024) -

Equinox Gold Corp.

(TSX: EQX)

(NYSE American: EQX) is pleased to provide an update on commissioning progress at its Greenstone

Project in Ontario, Canada. The Greenstone Project is being developed as a 60/40 partnership,

respectively, by Equinox Gold and Orion Mine Finance Group and will be one of the largest gold mines in

Canada, producing approximately 400,000 ounces of gold annually for the first five years and more than

five million ounces of gold over its initial 14-year mine life.

Ore was introduced into the grinding circuit on April 6, with first gold pour expected in May. More than 1.5

million tonnes of ore have been stockpiled and 70,000 tonnes of low-grade ore has been pre-crushed to

use for early commissioning feed. Progressively higher-grade ore will be fed into the mill as production

ramps up toward planned throughput of 27,000 tonnes per day, with commercial production targeted for

Q3 2024.

Greg Smith, President & CEO of Equinox Gold, commented: "Following 2.5 years of construction,

Greenstone is on schedule to commence gold production in the first half of the year, as planned. This is a

significant achievement and a testament to the experience of the Greenstone team. Greenstone is a

world-class asset, and reaching production will be a pivotal milestone for Equinox Gold. Once operating

at full capacity, Greenstone will be our largest and lowest cost-mine. We look forward to first gold in May

and continuing to advance the project to commercial production."

Commissioning of the plant began earlier this year, initially with the crushing circuit and ore storage

dome, followed by the high-pressure grinding rolls (HPGR), ball mill #1, and thickener and leach tanks.

Flocculant and lime were loaded into the system during the last week of March and the full system was

water tested during the first week of April. The equipment is working as expected and ball mill #2 will be

brought online in the coming weeks as throughput is progressively increased. Hiring is on track with

more than 400 positions filled, and all senior plant operators are on board.

Greenstone has worked 6.4 million hours project to date with one lost-time injury. Progress has been

documented since construction began in a photo gallery on Equinox Gold's website at

www.equinoxgold.com

, and select photos are included in this news release.

Equinox Gold Contacts

Greg Smith, President & CEO

Rhylin Bailie, Vice President, Investor Relations

Tel: +1 604-558-0560

Email:

[email protected]

About Equinox Gold

Equinox Gold is a growth-focused Canadian mining company with seven operating gold mines,

commissioning underway at a new mine, and a plan to achieve more than one million ounces of annual

gold production by advancing a pipeline of expansion projects. Equinox Gold's common shares are

listed on the TSX and the NYSE American under the trading symbol EQX. Further information about

Equinox Gold's portfolio of assets and long-term growth strategy is available at

www.equinoxgold.com

or

by email at

[email protected]

.

Greenstone Photos

Site overview.

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/9355/204785_site.jpg

Haul truck at crusher.

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/9355/204785_2eba2cf044c2f8d6_010full.jpg

First ore to mill.

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/9355/204785_2eba2cf044c2f8d6_011full.jpg

Conveyor with ore feed to secondary crusher.

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/9355/204785_2eba2cf044c2f8d6_012full.jpg

Crushed ore storage dome.

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/9355/204785_2eba2cf044c2f8d6_013full.jpg

Cautionary Notes

This news release contains certain forward-looking information and forward-looking statements within

the meaning of applicable securities legislation. Forward-looking statements and forward-looking

information in this news release relate to, among other things: the Company's ability to successfully

complete commissioning and achieve production at Greenstone; the Company's expectations

regarding the timing of first gold pour and achieving commercial production; the Company's

expectations for the operation of Greenstone, including production capabilities and future financial or

operating performance; the Company's ability to work effectively with its joint venture partner at

Greenstone; the strategic vision for the Company and expectations regarding exploration potential,

production capabilities and future financial or operating performance; and the Company's ability to

successfully advance its growth and development projects. Forward-looking statements or information

generally identified by the use of the words "will", "advance", "plan", "expect", "achieve", "on track",

"on schedule", "target", "continue", and similar expressions and phrases or statements that certain

actions, events or results "could", "would" or "should", or the negative connotation of such terms, are

intended to identify forward-looking statements and information. Although the Company believes that

the expectations reflected in such forward-looking statements and information are reasonable, undue

reliance should not be placed on forward-looking statements since the Company can give no

assurance that such expectations will prove to be correct. The Company has based these forward-

looking statements and information on the Company's current expectations and projections about

future events and these assumptions include: commissioning at Greenstone being completed and

performed in accordance with current expectations, including estimated capital costs remaining as

expected; availability of funds for the Company's projects and future cash requirements; Greenstone

Mineral Reserve and Mineral Resource estimates and the assumptions on which they are based;

Equinox Gold's ability to achieve the production, cost and development expectations for its respective

operations and projects; prices for gold remaining as estimated; currency exchange rates remaining

as estimated; no labour-related disruptions and no unplanned delays or interruptions in scheduled

commissioning, construction, development and production, including by blockade; the expansion

projects at Los Filos, Castle Mountain and Aurizona being completed and performed in accordance

with current expectations; tonnage of ore to be mined and processed; ore grades and recoveries

remaining consistent with mine plans; all necessary permits, licenses and regulatory approvals are

received in a timely manner; successful relationships between the Company and its joint venture

partner and between the Company and its Indigenous partners at Greenstone; and the Company's

ability to comply with environmental, health and safety laws. While the Company considers these

assumptions to be reasonable based on information currently available, they may prove to be

incorrect. Accordingly, readers are cautioned not to put undue reliance on the forward-looking

statements or information contained in this news release.

The Company cautions that forward-looking statements and information involve known and unknown

risks, uncertainties and other factors that may cause actual results and developments to differ

materially from those expressed or implied by such forward-looking statements and information

contained in this news release and the Company has made assumptions and estimates based on or

related to many of these factors. Such factors include, without limitation: fluctuations in gold prices;

fluctuations in prices for energy inputs, labour, materials, supplies and services; fluctuations in

currency markets; operational risks and hazards inherent with the business of mining (including

environmental risks, geotechnical failures, industrial accidents, equipment breakdown, unusual or

unexpected geological or structural formations, cave-ins, flooding and severe weather); inadequate

insurance, or inability to obtain insurance to cover these risks and hazards; employee relations;

relationships with, and claims by, local communities and Indigenous partners; the Company's ability

to obtain all necessary permits, licenses and regulatory approvals in a timely manner or at all;

changes in laws, regulations and government practices, including environmental, export and import

laws and regulations; legal restrictions relating to mining; increased competition in the mining

industry; and those factors identified in the section titled "Risks and Uncertainties" in Equinox Gold's

MD&A dated February 21, 2024 for the year ended December 31, 2022, and in the section titled

"Risks Related to the Business" in Equinox Gold's most recently filed Annual Information Form, both

of which are available on SEDAR+ at

www.sedarplus.ca

and on EDGAR at www.sec.gov/edgar.

Forward-looking statements and information are designed to help readers understand management's

views as of that time with respect to future events and speak only as of the date they are made. Except

as required by applicable law, Equinox Gold assumes no obligation to update or to publicly announce

the results of any change to any forward-looking statement or information contained or incorporated by

reference to reflect actual results, future events or developments, changes in assumptions or changes

in other factors affecting the forward-looking statements and information. If Equinox Gold updates any

one or more forward-looking statements, no inference should be drawn that Equinox Gold will make

additional updates with respect to those or other forward-looking statements. All forward-looking

statements and information contained in this news release are expressly qualified in their entirety by

this cautionary statement.

To view the source version of this press release, please visit

https://www.newsfilecorp.com/release/204785