Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

EQX.TO ·

Equinox Gold Announces Positive Pre-Feasibility Study for Aurizona Expansion and 73% Increase to Mineral Reserves Peak Annual Production over 160,000 oz of Gold Average Annual Production of 137,000 oz for 11 Years all dollar figures in US dollars

Resource Estimates Economic Studies Production Results

TSX: EQX

NYSE-A: EQX

Suite 1501 - 700 West Pender St., Vancouver, BC Canada V6C 1G8

[email protected] +1 604.558.0560 www.equinoxgold.com

NEWS RELEASE

Equinox Gold Announces Positive Pre-Feasibility Study for Aurizona Expansion

and 73% Increase to Mineral Reserves

Peak Annual Production over 160,000 oz of Gold

Average Annual Production of 137,000 oz for 11 Years

all dollar figures in US dollars, unless otherwise indicated

September 20, 2021 – Vancouver, BC – Equinox Gold Corp. (TSX: EQX, NYSE American: EQX) (“Equinox Gold” or

the “Company”) is pleased to announce the results of a Pre-Feasibility Study (“PFS”) for an expansion at the

Company’s 100%-owned Aurizona Gold Mine (“ Aurizona”) located in Brazil. By mining the underground and

satellite open -pit deposits concurrently with the existing Piaba open -pit, the expansion would extend the

Aurizona mine life to 11 years with average annual production of 137,000 ounces (“oz”) of gold per year and

total life-of-mine (“LOM”) production of 1.5 million oz of gold. Peak production in years 2026 to 2029 averages

more than 160,000 oz of gold per year.

Updated Mineral Reserve and Resource estimates for Aurizona, incorporating the new underground and open-

pit deposits and offsetting 18 months of mining depletion , show a 73% increase over the December 31, 2019

estimate with 1.7 million oz of Proven & Probable Mineral Reserves grading 1.6 0 grams per tonne (“g/t”) gold

plus 868,000 oz of Measured & Indicated Mineral Resources (exclusive of Reserves) grading 1.49 g/t gold.

AURIZONA EXPANSION HIGHLIGHTS

• After-tax NPV5% of $314 million at $1,500/oz gold and $600 million at $1,800/oz gold

• $464 million after-tax LOM cumulative net cash flow at $1,500/oz gold and $830 million at $1,800/oz gold

• $803/oz average LOM cash costs

• $944/oz average AISC from 2024 onward and $1,058/oz average AISC LOM

• 1.5 million oz LOM gold production at an average recovery of 90.5%

- More than 160,000 oz peak average annual gold production from 2026 to 2029

- 137,000 oz average annual gold production (LOM)

• 1.7 million oz Proven & Probable Mineral Reserves grading 1.60 g/t gold

• $154 million underground mine initial capital costs, including $20 million contingency

• 11-year mine life with additional expansion potential from further exploration success

Christian Milau, CEO of Equinox Gold, stated: “Incorporating the Aurizona underground and satellite deposits

into our mine plan will nearly double the Aurizona mine life, increase annual production and generate almost

$1 billion of net cash flow at current gold prices. I am incredibly proud of what our team has accomplished at

Aurizona. The expansion will create additional economic and social opportunities for our community partners

and substantial value for our shareholders , with significant potenti al for further growth as we continue to

explore what could eventually be a multi-decade mine.”

Scott Heffernan, EVP Exploration of Equinox Gold, stated: “Exploration continues to unlock the potential at

Aurizona. We have successfully replaced reserves from nearly three years of mining and provided an additional

70% growth of both mineral reserves and mineral resources. We expect to demonstrate additional growth at

- 2 -

Aurizona with on going exploration focused on mine life extension through infill drilling and conversion of

resources to reserves, plus significant near-mine, underground and regional exploration to further develop this

mining district as a cornerstone asset for Equinox Gold.”

OVERVIEW

Equinox Gold achieved commercial production at Aurizona in July 2019 after constructing a new mill and

upgrading existing infrastructure. With an initial capital spend of only $160 million, Aurizona has produced more

than 260,000 oz of gold and generated more than $190 million in free cash flow since commencing production.

The Piaba gold deposit contains gold mineralization in a vein system that extends at least four kilometres (“km”)

along strike with smaller satellite deposits to the east and west of the main Piaba deposit . Recent drilling has

shown that gold mineralization also extends below the ultimate open pit to depths greater than 1,000 metres

(“m”) from surface. In 2020, a total of 65 diam ond drillholes totaling nearly 26,000 m were drilled in the

underground deposit to support the PFS and underground resource estimate. Year to date, 30 drillholes totaling

nearly 11,000 m have been drilled in the Piaba underground, Tatajuba and satellite deposits, the results of which

will be incorporated into the next reserve and resource update.

Aurizona Overall Site Plan

The current operation consists of the Piaba open-pit mine and a conventional crushing and grinding circuit with

an 8,000 tonnes-per-day (“t/d”) carbon-in-leach (“CIL”) plant. The expansion will incorporate ore from the

existing Piaba open-pit deposit along with the Piaba underground deposit and the Tatajuba, Boa Esperança, and

Genipapo open -pit deposits. While the expanded m ine will continue to use the existing mill and surface

infrastructure, the existing powerline will need to be upgraded and the mine will require additional tailings and

waste rock storage. Mining and processing underground ore concurrently with open -pit ore will increase the

average mill feed grade, increase annual gold production and extend the mine life to 11 years.

- 3 -

MINING

The PFS considers the addition of an underground mine beneath the existing Piaba pit as well as the inclusion of

two satellite open-pit areas: Tatajuba and Genipapo.

Underground Mining

The underground mine will be developed along a total strike length of 2.3 km beneath the Piaba pit. Access to

the mine will be via a ramp collared in hard rock within the pit. The currently defined seven separate mining

areas will be accessed by a 2-km main haulage decline with separate internal ramps. The first 800 m of the main

haulage will be developed as a single heading to the location of the primary ventilation raise, which also provides

emergency egress. From that point onwards the ramp will be de veloped as a double ramp arrangement, with

the second ramp used for ventilation purposes during production. All underground mine development is in

stable rock units located on the hanging wall side of the mineralized body.

The proposed underground mining method is long-hole stoping due to good ground conditions and the steep

dip of the deposit. The PFS contemplates owner mining of stopes and underground development. Most of the

stopes will include permanent rib pillars and be backfilled with rockfill from underground development or open-

pit waste. The addition of cement to rockfill is confined to higher -grade areas where mining recovery can be

maximized by eliminating rib pillars and above sill pillars.

Ore release will occur early in underground development, and Equinox Gold is reviewing additional opportunities

to access higher-grade zones earlier in the underground mining schedule to enhance economics. First ore is

released after approximately two years with steady state production exceeding 3,300 t/d achieved by year four.

This production level is maintained until the middle of year seven and then reduces until underground mining is

complete at the end of year 10. The Crown Pillar between the Piaba open-pit and underground will be recovered

when underground mining is complete. In the PFS mine plan, the underground deposit provides 6.5 million

tonnes (“Mt”) of ore grading 2.77 g/t gold of fresh rock.

Aurizona Underground Development Plan (Isometric View Looking South)

- 4 -

Open-pit Mining

Open-pit mining is currently undertaken by a contractor using conventional drill and blast, load and haul methods.

Piaba and Piaba East are currently in production providing feed to the Aurizona mill. Piaba East is a single-phase

pit that is expected to be depleted by the end of 2024. Piaba will continue until 2032, mining the remaining four

phases in the design and also the crown pillar in the floor when underground mining is complete. In the PFS mine

plan, Piaba provides 18.9 Mt grading 1.3 g/t gold with 83% of the feed material being fresh rock. Piaba East

provides 1.2 Mt grading 1.46 g/t gold of primarily saprolite mill feed.

The Boa Esperan ça pit is scheduled to be mined and completed in 2021 , providing a total of 0.9 Mt grading

0.81 g/t gold of saprolite mill feed and creating a freshwater storage facility for plant operations.

The Tatajuba deposit, located 4 km to the west of the Piaba pit, is a two-phase pit design scheduled to commence

production in the fourth quarter of 2023. Mining would continue in 2024 then pause until 2027, when the second

phase would be complete. In the PFS mine plan, Tatajuba provides 2.0 Mt grading 1.39 g/t gold with 70% of the

material being saprolite and transition material and the remainder fresh rock.

The Genipapo area is located 3 km by road to the east of the Aurizona plant. This area is separated into two

small areas called Genipapo North and Genipapo South that will share a common waste storage facility. Mining

of Genipapo South would start in 2024 and then move to Genipapo North, which is completed in 2028. Combined,

the two Genipapo pits are expected to provide 0.67 Mt grading 0.82 g/t gold of saprolite and laterite feed.

The Crown Pillar removal is expected to provide 1.9 Mt of fresh rock grading 1.36 g/t gold in 2031 and 2032 ,

after underground mining is complete.

Aurizona Mine Plant Feed (LOM)

Note: Plant feed of 3.35 Mt for calendar year 2021 is shown for clarity only. The PFS accounts for 1.72 Mt of plant feed commencing in H2 2021.

CAPITAL AND OPERATING COSTS

The PFS contemplates a three-year capital development and construction timeline for the underground mine.

Total initial capital costs during this period are estimated at $154 million. Underground capital costs assume the

mining fleet is purchased. Leasing the mining fleet would reduce capital costs by $25 million.

-

0.5

1.0

1.5

2.0

2.5

3.0

3.5

-

500,000

1,000,000

1,500,000

2,000,000

2,500,000

3,000,000

3,500,000

4,000,000

2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032

Feed Grade (g/t gold)

Feed Tonnage (t)

Open Pit Feed Underground Feed

Open Pit Feed Grade (gpt) Underground Feed Grade (gpt)

Plant Feed Grade (gpt)

- 5 -

Sustaining capital costs of $ 383 million include $60 million for the underground mine, largely for continued

capital development and equipment replacements and rebuilds, $79 million for o pen-pit capitalized stripping

and $178 million for infrastructure. Infrastructure includes $98 million for the construction of additional tailings

facilities, $22 million for powerline upgrades and a new substation , $ 26 million for building improvements,

equipment, and automation, and $25 million for exploration.

Aurizona LOM Capital Costs

Item Initial

($M)

Sustaining

($M)

Total

($M)

Open-pit Mining 79 79

Underground Mining 134 60 194

Processing 14 14

Infrastructure 178 178

Environmental 10 10

Contingency 20 43 63

Total Capital 154 383 537

Aurizona Underground Capital Costs

Item Initial

($M)

Sustaining

($M)

Total

($M)

Underground Mine Capital Development 46 26 72

Underground Mining Equipment 34 24 58

Underground Mine Infrastructure 41 10 51

EPCM and Pre-production Costs 13 1 14

Contingency 20 9 29

Total Underground Mine Capital 154 69 224

Operating costs are estimated at $33.14 per tonne of ore processed, as summarized below. LOM average cash

costs are estimated at $ 803/oz with LOM AISC estimated at $ 1,058/oz of gold sold. Following completion of

significant sustaining capital expenditures, AISC from 2024 onward averages $944/oz.

Aurizona Operating Costs

Total Operating Costs Total LOM ($M) $/tonne $/oz

Open-pit Mining ($/t mined) 2.25

Open-pit Mining ($/t ore mined) 10.79

Underground Mining ($/t ore mined) 32.78

Mining 490 15.15 326

Open-pit 276 8.53 184

Underground 214 6.62 142

Processing 373 11.52 248

G&A 209 6.47 139

Total 1,072 $33.14 713

ECONOMIC SENSITIVITIES

Using the base case gold price of $1,500/oz and incorporating only Proven & Probable Mineral Reserves, the

Aurizona expansion has an after-tax NPV5% of $314 million and after-tax cumulative net cash flow of $464 million.

Project economics are most sensitive to operating costs and changes in the gold price.

- 6 -

Aurizona Sensitivity to Gold Price

Gold price ($/oz) $1,350 $1,500 $1,800

Net Cashflow (pre tax) ($M) $295 $510 $941

Net Cashflow (after tax) ($M) $249 $464 $829

NPV5% (pre tax) ($M) $186 $354 $689

NPV5% (after tax) ($M) $146 $314 $600

MINERAL RESERVES & RESOURCES

The expansion mine plan is based on Proven & Probable Mineral Reserves of 32.3 Mt grading 1.60 g/t gold for

1,660,000 contained oz of gold, an increase of 73% compared to the previously stated Mineral Reserves from

December 31, 2019 . Measured & Indicated Mineral Resources (exclusive of Mineral Reserves ) are 18.1 Mt

grading 1.49 g/t gold for 868,000 contained oz of gold , with additional Inferred Resources of 12 .7 Mt grading

2.19 g/t gold for 895,000 contained oz of gold.

Aurizona Mineral Reserve Estimate

Effective Date June 30, 2021

Category Location Tonnes

(kt)

Gold Grade

(g/t)

Contained Gold

(koz)

Proven Piaba Open Pit 14,475 1.37 638

Piaba East Open Pit 828 1.59 42

Boa Esperança Open Pit 168 0.63 4

Piaba Underground 223 2.42 17

Crown Pillar 638 1.54 32

Stockpile 249 0.92 7

Total Proven 16,581 1.39 740

Probable Piaba Open Pit 4,423 1.17 167

Piaba East Open Pit 414 1.22 16

Boa Esperança Open Pit 713 0.85 20

Tatajuba Open Pit 1,974 1.39 87

Genipapo Open Pit 673 0.81 18

Piaba Underground 6,305 2.77 562

Crown Pillar 1,246 1.27 51

Total Probable 15,749 1.82 920

Total Proven & Probable 32,330 1.60 1,660

Notes: CIM Definition Standards (2014) were followed for calculating Mineral Reserves : This mineral reserve estimate is as of June 30, 2021 and is based on the

mineral resource estimates for Piaba, Boa Esperança, Tatajuba, and Genipapo all dated June 30, 2021 by Equi ty Exploration. The mineral reserve calculation was

completed under the supervision of Gordon Zurowski, P.Eng. of AGP., who is a Qualified Person as defined under NI 43 -101. Mineral reserves are stated within

the final design pits based on a $1,350/oz gold price. The gold cut-off grades used were: Piaba Open Pit – 0.35 g/t (laterite, saprolite, transition), 0.41 g/t (rock);

Boa Esperança Open Pit – 0.36 g/t (laterite, saprolite); Tatajuba Open Pit – 0.43 g/t (laterite, saprolite, transition), 0.47 g/t (rock ); Genipapo Open Pit – 0.36 g/t

(laterite, saprolite); Piaba Underground – 1.80 g/t (rock) ; Open pit mining costs varied by area but averaged $2.25/t mined and included an extra $2/t for ore

haulage to the process plant from Tatajuba. Underground Mining co sts averaged $32.78/t ore mined. Processing costs averaged $11.52/t ore based on variable

costs by material type of $7.84/t for laterite/saprolite, $8.08/t for transition and $12.63/t for fresh rock. G&A was $6.47/t ore processed. LOM average gold

recovery is 90.5%. Numbers may not sum due to rounding.

- 7 -

Aurizona Mineral Resource Estimate (exclusive of Reserves)

Effective Date June 30, 2021

Category Location Tonnes

(kt)

Gold Grade

(g/t)

Contained Gold

(koz)

Measured Piaba Open Pit 2,439 1.21 95

Boa Esperança Open Pit 66 0.60 1

Piaba Underground 1,000 2.10 67

Total Measured 3,505 1.44 163

Indicated Piaba Open Pit 3,114 1.19 121

Boa Esperança Open Pit 427 1.03 14

Tatajuba Open Pit 181 1.39 8

Genipapo Open Pit 249 0.84 7

Touro Open Pit 2,965 0.78 75

Piaba Underground 7,212 1.96 454

Tatajuba Underground 464 1.73 26

Total Indicated 14,612 1.50 705

Total Measured & Indicated 18,117 1.49 868

Inferred 12,689 2.19 895

Notes: Mineral Resource statement has been prepared in accordance with NI43 -101 Standards of Disclosure for Mineral Projects (May 2016) and the CIM

Definition Standards for Mineral Resources and Mineral Reserves (May 2014) . Mineral Resources are reported exclusive of reserves. Mineral Resources are

reported using a cut-off grade of 0.30 g/t gold for open pit resources and 1.00 g/t gold for underground resources. The Open Pit Mineral Resource is constrained

using an optimized pit that has been generated using Lerchs -Grossman pit optimisation algorithm. The Underground Mineral Resources are constrained using a

1.00 g/t Au grade shell occurring the lower of 20m below the transition -fresh rock contact, or 20 m below the Reserve pit. Mineral Resources are based on the

Mineral Resource statements for each respect ive deposit and area, and have been prepared by Trevor Rabb, P.Geo who is a qualified person as defined by

National Instrument 43-101. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. Totals may not sum due to rounding.

PRODUCTION SCHEDULE

The Aurizona production schedule shows average annual production of 137,000 oz of gold during the 11-year

mine life (from July 2021 to June 2032) with average LOM AISC of $1,058/oz of gold sold. Total LOM production

is estimated at 1,503,000 oz of gold with peak production in Years 2026 to 2029 averaging more than 160,000

oz per year at AISC of $970/oz of gold sold.

Aurizona Annual Gold Production and AISC

Note: Production of 59,120 oz for the first half of 2021 is shown for clarity only. The PFS considers production commencing in H2 2021.

-

200

400

600

800

1,000

1,200

1,400

1,600

1,800

-

20,000

40,000

60,000

80,000

100,000

120,000

140,000

160,000

180,000

2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032

AISC ($/oz)

Recovered Gold (oz)

Open Pit - PFS Underground Open Pit - 2021 H1 Actual AISC

- 8 -

METALLURGY AND PROCESSING

The Aurizona process plant treats ore via a conventional cyanidation process. Run -of-mine (ROM) ore is

processed using a conventional primary crush and SAG-Ball mill comminution circuit followed by a gravity circuit,

CIL process and associated gold recovery and carbon handling circuits to produce gold doré. Combined recovery

from gravity concentration and CIL is expected to average 90.5%. Recent metallurgical testwork on samples from

Piaba underground and Tatajuba confirm a similar metallurgical response using the existing processing circuit.

No flowsheet changes or plant modifications will be required to treat ore from future mining areas.

POWER

Currently the mine is serviced by a 69 kV powerline maintained by the regional utility CEMAR, with a substation

at site. The current operation typically draws 10-11 MW of power from the grid. A total of 7 MW of additional

power is required at peak running load for the underground mine expansion. A powerline upgrade is included in

the PFS as well as a new surface substation. Diesel generators are also included for back-up emergency electrical

power underground.

PERMITTING

The Economic Exploitation Plan (PAE) for Piaba, which was ratified in 2019, will be updated to include the Piaba

underground mine operation before submission for approval from the Brazil National Mining Agency (ANM).

Equinox Gold received the Preliminary License (LP) for Tatajuba in August 2021 and anticipates receiving the

Installation License (LI) in H1 2022, which will allow for the commencement of mine and infrastructure

development.

Genipapo has an exploration permit under assessment by ANM. Upon ANM’s approval, Equinox Gold will submit

a PAE requesting the Genipapo mining concession. Boa Esperança is fully permitted under the existing Piaba

Operating License (LO).

ADDITIONAL OPPORTUNITIES & NEXT STEPS

An extensive exploration program is ongoing at Aurizona to further expand Mineral Resources, convert

Resources to Mineral Reserves, and continue exploration along strike and at depth at a number of near-mine

targets. There is potential to expand both the Piaba East and Boa Esperança open-pits, and the Piaba

underground deposit remains open at depth and along strike. Numerous other near -mine targets including

Micote, Mestre Chico, S ão Lo urenço, Conce ição and Ferradura all require further testing. In addition, gold

mineralization at Tatajuba is yet to be fully defined and t here is good potential that the Tatajuba deposit

continues along strike and at depth, representing another opportunity for mine life extension with exploration

success.

Equinox Gold plans to commence permitting of the exploration decline in late 2021, which will allow for targeted

drilling of the ore body from underground and would also serve as the ramp for future underground mining.

TECHNICAL REPORT PREPARATION

Equinox Gold retained independent consultants to complete the PFS and prepare a technical report in

compliance with National Instrument 43 -101 (“NI 43 -101”). Key aspects of the PFS include an updated

underground mine design, revised Piaba pit design, inclusion of satellite Reserves and an update to the Mineral

Resource a nd Mineral Reserve estimates , updated mine schedule, infrastructure development , and the

supporting cost development with financial model . The findings and conclusions are based on information