EMP METALS COMPLETES CONSTRUCTION OF PROJECT AURORA

DEMONSTRATION PLANT AND ADVANCES COMMISSIONING TOWARD

Q3 START-UP

Vancouver, British Columbia, August 5, 2026 – EMP Metals Corp. (CSE: EMPS) (OTCQB: EMPPF)

(FSE: 9ST) ("EMP Metals" or the "Company") is pleased to announce that construction of its

Project Aurora Demonstration Plant located within the Company's Viewfield Project Area in

Saskatchewan has been successfully completed.

The fully integrated demonstration facility is now directly connected to both the production well

and waste brine disposal well, allowing continuous wellhead brine delivery to the facility process

while returning spent brine to the targeted disposal interval. This integrated configuration

enables full commissioning of the demonstration plant under real operating conditions and is

among the first Lithium Brine facilities in Canada to achieve this level of integration.

Commissioning activities continue to progress according to plan and are now approximately 50%

complete. Live production brine is currently being processed through multiple operating systems

as commissioning advances toward full plant start -up. The Company remains on schedule to

commence demonstration operations during the third quarter of 2026.

Figure 1 – Project Aurora direct wellhead connected piping for production and disposal brine

Tel: 604-689-7422 204 – 252 Esplanade West, North Vancouver, BC V7M 0E9

The demonstration plant has now achieved several key milestones, including:

• Construction and field infrastructure 100% complete.

• Direct wellhead connection established to both production and disposal wells.

• Raw brine delivery from the production well into the process facility and advancing

towards continuous flow, steady state operations.

• Waste brine disposal system fully operational with injection into the targeted disposal

formation.

• Approximately 50% of the overall commissioning schedule completed.

• Commissioning advancing across all major processing systems.

• Start-up in Q3 2026 remains on schedule.

"Completing construction of Project Aurora marks a major milestone for EMP as we transition

from building the facility to operating it," said Karl Kottmeier, CEO of EMP Metals. "Having the

demonstration plant fully connected directly to both the production well and disposal well allows

us to commission the facility under true field operating conditions. Fresh production brine is now

flowing through the process as we continue integrating each system, and with commissioning

approximately halfway complete, we remain on schedule for Q3 start-up."

Project Aurora is EMP's integrated, continuous -flow lithium refining demonstration system

designed to process ten (10) m³/day of raw brine from wellhead to lithium chemicals. The facility

is intended to validate process performance, optimize operating para meters, and generate

engineering and economic data to support future commercial-scale development.

The demonstration program represents a key step toward commercializing EMP's lithium brine

resource in Saskatchewan. Operational data generated throughout the demonstration campaign

will support engineering design, process optimization, and economic evalua tion for a future

modular commercial facility capable of producing more than 3,000 tonnes per year of lithium

products.

EMP's Saskatchewan lithium resource continues to benefit from favourable brine chemistry free

of hydrogen sulfide (H₂S) and oil -derived organics, shallow low -cost drilling, established

infrastructure, and a supportive critical minerals regulatory environme nt, positioning the

Company to pursue initial commercial modules targeting 1,500 to 3,000 annually, expandable

thereafter.

About EMP Metals

EMP is a Canadian-based lithium exploration and development company focused on large -scale

resources using direct lithium extraction (DLE). EMP currently holds over 205,000 net acres

(83,000 hectares) of Subsurface Dispositions and strategic wellbores in Southern Saskatchewan.

Tel: 604-689-7422 204 – 252 Esplanade West, North Vancouver, BC V7M 0E9

For more information, please go to the Company’s website at www.empmetals.com or contact:

Karl Kottmeier, CEO

[email protected]

Phone: 1-604-689-7422

Paul Schubach, COO

[email protected]

Phone: 1-306-519-8341

Forward-Looking Statements

Information set forth in this news release contains forward-looking statements that are based on

assumptions as of the date of this news release. These statements reflect management's current

estimates, beliefs, intentions and expectations. They are not guarantees of future performance.

EMP Metals cautions that all forward-looking statements are inherently uncertain, and that

actual performance may be affected by a number of material factors, many of which are beyond

EMP Metals’ control. Such factors include, among other things: risks and uncertainties relating

to EMP Metals' limited operating history, ability to obtain sufficient financing to carry out its

exploration and development objectives on its mineral properties, obtaining the necessary

permits to carry out its activities and the need to comply with environmental and governmental

regulations. Accordingly, actual and future events, conditions and results may differ materially

from the estimates, beliefs, intentions and expectations expressed or implied in the forward-

looking information. Except as required under applicable securities legislation, EMP Metals

undertakes no obligation to publicly update or revise forward-looking information.

The Canadian Securities Exchange has neither approved nor disapproved the information

contained herein and does not accept responsibility for the adequacy or accuracy of this news

release.