Empress Royalty Receives First Silver from Tahuehueto MINE
WWW.EMPRESSROYALTY.COM PAGE 1
NEWS RELEASE | JU LY 18, 2022 | VANCOUVER , BC
EMPRESS ROYALTY RECEIVES FIRST SILVER FROM
TAHUEHUETO MINE
Empress Royalty Corp. (TSXV:EMPR | OTCQB:EMPYF) (“ Empress” or the “ Company”) is pleased
to announce the Company has received the first payable silver ounce s from the silver stream
agreement on the Tahuehueto Mine (“Tahuehueto” or the “Mine”). Tahuehueto Mine is located
in Durango, Mexico, 100% owned and operated by Altaley Mining Corporation (“Altaley”).
“I am excited to announce Empre ss has received its first payment of silver ounces from th e
Tahuehueto mine. It’s only been 12 months since the Tahuehueto silver stream was completed
and this is a major milestone to see a development asset move forward to generate revenue for
the Company”, stated Alexandra Woodyer Sherron, CEO and President of Empress. “Tahuehueto
is an exceptional asset which is expected to generate significant revenue for Empress . It gives
Empress direct exposure to silver and combined with our low G&A provides an effective hedge
against inflation pressures as seen in other industries . Empress continues to build a strong
portfolio of revenue generating gold and silver royalties and streams and Tahuehueto
demonstrates our ability to deliver value to our shareholders.”
Figures 1 to 3. Tahuehueto Mine
WWW.EMPRESSROYALTY.COM PAGE 2
THE INVESTMENT
On April 16, 2021, Empress executed the US$5M silver stream agreement (“Stream”) with Altaley
to purchase 100% of the payable silver production from Tahuehueto for the first 1,2 50,000
payable silver ounces . Ther eafter, the percentage will step down to 20% of the payable silver
production up to a maximum of 10 years. Empress will purchase the silver at 20% of spot price.
PROJECT UPDATE
Tahuehueto is located in Durango, Mexico. It is a typical epithermal polymetallic mineral deposit
in this part of Mexico, with metals consist ing of gold, silver, zinc, copper and lead. The Mine is
fully permitted, has all social and environmental licenses to operate, and has offtake agreements
in place.
On April 26 , 2022, Altaley filed an updated technical report, including a Preliminary Feasibility
Study (“PFS”) for Tahuehueto. With the filing of the PFS report, Altaley updated the March 7,
2022, disclosure with a significant increase of approximately 30% to the overall economic s of
the project. Altaley expects to produce 2,166 oz/month of gold and 37,829 oz/month of silver,
of which 100% of the silver is subject to the above terms of the S tream. Please see Altaley’s
website ( www.altaleymining.com) for further details on the PFS. Highlights from the Altaley
press release include the following:
• 2022 Preliminary Feasibility Study improves 2017 PFS increasing throughput to 1,000
tonnes per day (“tpd”) returning a post-tax NPV of US$161.3M, at a discount rate of
5%, (US$141.8M and US$131.8M at discount rate of 8% and 10% respectively).
• IRR of 65% with a two year payback period with a 5% discount rate.
• Total Life of Mine Capital Cost estimate of US$56.9M with project construction over
95% complete.
• Life of Mine All in Sustaining Costs (“AISC”) estimated at US$844 per gold equivalent
ounce at US$1,647.52/ounce Au, US$21.64/ounce Ag, US$0.92/pound Pb,
US$1.14/pound Zn and US$3.60/pound Cu).
• Proven & Probable Reserves of 3.58 million tonnes grading 2.55g/t gold, 50.06 g/t
silver, 1.92% zinc, 1.11% lead, 0.26% copper.
• 9-year Life of Mine (“ LOM”) utilizing mostly low -cost bulk underground Sub-level
Open Stoping mining method with average annual production of 25,987 oz of gold,
453,952 oz of silver, 827 tonnes of copper, 3,155 tonnes of lead and 6,123 k -lbs of
zinc.
WWW.EMPRESSROYALTY.COM PAGE 3
• Significant opportunities exist to expand the Projects Mineral Resources and Reserves
base with near mine and regional exploration. Altaley plans to aggressively pursue
exploration as soon as free cash flows allow or alternative funding is secured.
On May 16, 2022, Altaley announced Tahuehueto initiated pre-production mining and milling
commissioning operations and construction efforts at the Mine were advanced to allow the start-
up and commission of one ball mill capable of processing up to 500 tpd. Please see Altaley’s
website (www.altaleymining.com) for further details on the announcement of pre-production.
On June 27, 2022, Altaley updated their shareholders on the commissioning, pre-production, and
construction progress at Tahuehueto. Please see Altaley’s website (www.altaleymining.com) for
further details on the Tahuehueto ramp-up. Highlights are as follows:
• Altaley stated t he operations team have been diligently resolving various start -up
issues related to the water supply pipeline and mill commissioning and, over the past
week have successfully achieved ongoing pre -production with the first 500 tpd ball
mill. Recently, processing has been stabilized with the mill achieving ore throughput
up to 350 tpd and averaging approximately 195 tpd over the past 5 days. Mill
throughput is estimated to remain at current levels over the next two weeks with
crushing being handled with a provisional cone crusher while the permanent crushing
circuit installation is being finalized and anticipated to be operational within the next
two weeks and thereafter the ball mill throughput will be ramped up to capacity.
• Altaley further updated on production that to date approximately 260 tonnes of bulk
concentrate has been produced at Tahuehueto. Two shipments of approximately 30
tonnes each have been shipped and received to the point of sale. These initial
batches of concentrate were produced from low- grade ore on purpose as original
feed testing at the ball mi ll start-up. Revenue received from the first shipment was
approximately US$42,000 paid for gold, silver, and lead. The second delivery
payment is pending. Another 70 tons of concentrate is in the process of being shipped
from Tahuehueto to Tepehuanes subsequently to be trucked in the coming days. The
Tahuehueto operations team estimate that there are approximately another 150
tonnes of concentrate available, drying on the mill patio and within the thickeners
available to be filtered for drying on the patios.
• The tailings storage facility is in the final stages of construction and expected to be
ready to receive dry stack tailings within 45 days. Tailings currently being generated
are being filtered and stored as additional backfill underground. The Tahuehueto
WWW.EMPRESSROYALTY.COM PAGE 4
Laboratory is essentially ready to be operational and technicians are calibrating ICP
and ancillary equipment expected to be fully operational over the next few days.
• Installation of the second 500 tpd ball mill is scheduled over the next several months
and the Company anticipates the project will be able to commission this mill during
Q4 2022 and ramp up production towards the mine’s designed capacity of 1,000 tpd
near the end of 2022.
QUALIFIED PERSON
Technical information in this news release originates in the public disclosure set out above and
has been reviewed and approved by Richard Mazur , P.Geo. , a Qualified Person as defined in
National Instrument 43-101, Standards of Disclosure for Mineral Projects.
ABOUT EMPRESS ROYALTY CORP.
Empress is a global royalty and streaming creation company providing investors with a diversified
portfolio of gold and silver investments. Since listing in December 2020, Empress has built a
portfolio of 17 precious metal investments and is actively investing in mining companies with
development and production stage projects who require additional non -dilutive capital. The
Company has strategic partnerships with Endeavour Financial and Terra Capital which allow
Empress to not only access global investment opportunities but also bring unique mining finance
expertise, deal structuring and access to capital markets. Empress is looking forward to
continuously creating value for its shareholders through the prove n royalty and streaming
models.
ON BEHALF OF EMPRESS ROYALTY CORP.
Per: Alexandra Woodyer Sherron, CEO and President
For further information, please visit our website at www.empressroyalty.com or contact Kaitlin
Taylor, Investor Communications, by email at [email protected] or by phone at
+1.604.331.2080.
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. This news release contains
statements about Empress’ expectations regarding the economics of the Tahuehueto mine which are forward-looking
in nature and, as a result, are subject to cert ain risks and uncertainties. Generally, forward- looking statements can
be identified by the use of forward-looking terminology such as “expects”, “believes”, “anticipates”, “aims to”, “plans
to” or “intends to” or variations of such words and phrases or statements that certain actions, events or results “will”
WWW.EMPRESSROYALTY.COM PAGE 5
occur. Although Empress believes that the expectations reflected in these forward -looking statements are
reasonable, undue reliance should not be placed on them as actual results may differ materially from the forward -
looking statements. Factors that could cause the actual results to differ materially from those in forward- looking
statements include the timing and success in Altaley completing the successful commissioning of the plant and
bringing the Tahuehueto project into commercial production as planned. The forward-looking statements contained
in this news release are made as of the date hereof, and Empress undertakes no obligation to update publicly or
revise any forward- looking statements or info rmation, except as required by law. Readers should not place undue
reliance on forward-looking statements or information.