Supreme Court of Spain Confirms Ruling Supporting Emerita’S Challenge to the Paymogo Zinc Project Tender Award

Legal & Disputes

65 Queen Street West, Suite 800, Toronto, ON, Canada, M5H 2M5

SUPREME COURT OF SPAIN CONFIRMS RULING SUPPORTING EMERITA’S CHALLENGE TO THE

PAYMOGO ZINC PROJECT TENDER AWARD

Toronto, Ontario, November 6, 2019 – Emerita Resources Corp. (TSX-V: EMO) (the “Company” or

“Emerita”) is pleased to announce that the Supreme Court of Spain has rejected the appeal by the

Junta of Andalusia and reaffirmed the ruling of the High Court of Justice of Andalusia (“the High

Court”) with respect to Emerita’s challenge of the awarding of the public tender for the Paymogo Zinc

Project (the “Project”) in Huelva Province, Andalusia Region in southern Spain. The Project which

occurs within the famous Iberian Pyrite Belt volcanogenic massive sulfide terrane, hosts two zinc

deposits (see below for details). The Project was subject to a public tender process in February 2014.

Subsequent to the awarding of the tender to a competing participant, Emerita filed an appeal of the

process due to irregularities with respect to the scoring of the bids. When the bids were initially

scored, the Junta awarded points to a competing bid in categories that were not part of the ten der

process. As such, other participants in the public tender were disadvantaged as they did not address

these points in their submissions.

The ruling by the High Court confirmed Emerita’s assertion and annulled the awarding of the tender

indicating that the bid results should be recalculated excluding the offending criteria (categories C and

H). Following is a summary of the hearings:

1. In September 2017, the High Court annulled the awarding of the Project to Matsa and

stated that the bids should be recalculated but excluding categories C and H, which were

illegal.

2. In October 2017, the Junta of Andalusia appealed the High Court’s ruling to the Spanish

Supreme Court.

3. In this most recent ruling, the Spanish Supreme Court dismissed the Junta’s appeal and

reaffirmed the High Court’s ruling.

4. If the bids are recalculated excluding categories C and H, as directed by the High Court and

confirmed by the Supreme Court, Emerita has 34.46 points and Matsa has 29.37, and

Emerita is the clear winner of the Public Tender (see table below).

65 Queen Street West, Suite 800, Toronto, ON, Canada, M5H 2M5

Joaquin Merino, P.Geo, President of Emerita stated : “Emerita is very happy with the decision of the

Supreme Court. We are prepared to meet immediately with the Mining Authorities in Huelva and

finalize the awarding of the Paymogo Public Tender to Emerita. We look forward to working with

them to initiate the work program for the Project as soon as possible. The Company will conduct its

exploration program to the highest environmental standards and with full regard for the health and

safety of the community and our employees.”

David Gower, P.Geo., CEO of Emerita stated: “The Company is excited by the outcome and prepared

to begin work on the Paymogo project as soon as the tender can be finalized, in line with the

instructions from the courts. We are highly encouraged by public statements from senior officials of

the new Government in Andalusia that they will abide b y the rulings of the court and that they look

forward to seeing the economic activity and potential job creation such a project can generate. The

Paymogo project is highly prospective in our view and we are excited to work on its development.”

About the Paymogo Project

The Paymogo project occurs within the famous Iberian Pyrite Belt, one of the most highly mineralized

volcanogenic massive sulfide (VMS) terranes in the world. The Project is located in the western part

of the belt, adjacent to the border with Portugal, approximately 70 km west of Seville and 50 km from

the port city of Huelva (Figure 1). The Project extends along a strike length of approximately 18 km.

Access is excellent via paved and all-weather gravel roads. Within the Project area, several base metal

occurrences have been identified by previous exploration, the most significant of which are the

Romanera and the La Infanta base metal deposits.

Original Calculation by Panel Calculation Based on Supreme Court Ruling

Matsa Bid Emerita Bid Matsa Bid Emerita Bid

a 6.97 10 6.97 10

b 7.4 8.1 7.4 8.1

c 4 1 0 0

d 5 5 5 5

e 0 5 0 5

f 5 5 5 5

g 5 1.36 5 1.36

h 10 0.24 0 0

TOTAL 43.37 35.7 29.37 34.46

65 Queen Street West, Suite 800, Toronto, ON, Canada, M5H 2M5

Figure 1. Location of the Paymogo Project.

The Romanera deposit was drilled primarily by Minera Rio Tinto in the 1990s and is reported to

contain 34 million tonnes grading 0.42% copper, 2.20% lead, 2.3% zinc 44.4g/t silver and 0.8 g/t gold

within which there is a higher grade resource of 11.21 million tonnes grading 0.40% copper, 2.47%

lead, 5.50% zinc, 64.0 g/t silver and 1.0 g/t gold (The Volcanic Hosted Massive S ulphide Deposits of

the Iberian Pyrite Belt, Garcia-Cortes ed., 2011). A qualified person, as defined in National Instrument

43-101, has not done sufficient work on behalf of Emerita to classify the historical estimate reported

above as current mineral r esources or mineral reserves and Emerita is not treating the historical

estimate as current mineral resources or mineral reserves. The historical estimate should not be relied

upon. The deposit extends from surface to approximately 350 meters depth based on historical

drilling. The mineralization remains open for further expansion down dip beyond the limits of the

existing drilling.

The La Infanta mineralized zone has been drilled from surface where it outcrops to a depth of

approximately 100 meters. Numerous high-grade intercepts (see table below) occur within the zone

and it remains open for expansion at shallow depths. Drilling was completed by Phelps Dodge in the

mid 1980s. La Infanta is located approximately 8 km to the east of the La Romanera deposit.

65 Queen Street West, Suite 800, Toronto, ON, Canada, M5H 2M5

Qualified Person

The scientific and technical information in this news release has been reviewed and approved by Mr.

Joaquin Merino, P.Geo, President of the Company and a Qualifie d Person as defined by National

Instrument 43-101 of the Canadian Securities Administrators.

65 Queen Street West, Suite 800, Toronto, ON, Canada, M5H 2M5

About Emerita Resources Corp.

Emerita is a natural resource company engaged in the acquisition, exploration and development of

mineral properties in Europe, with a primary focus on exploring in Spain. The Company’s corporate

office and technical team are based in Sevilla, Spain with an administrative office in Toronto, Canada.

For further information, contact:

Helia Bento

+1 (416) 566-8179 (Toronto)

Joaquin Merino

+34 (628) 1754 66 (Spain)

[email protected]

Cautionary Note Regarding Forward-looking Information

This press release contains “forward-looking information” within the meaning of applicable Canadian

securities legislation. Forward-looking information includes, without limitation, statements regarding

the Company’s ability to be awarded the Project, the mineralization of the Project, the Company’s

ability to develop the Project, the prospectivity of the Project, the Company’s ability to complete a NI

43-101 resource estimate and feasibility study, the timing of legal processes in Spain and the

Company’s future plans . Generally, forward -looking information can b e identified by the use of

forward-looking terminology such as “plans”, “expects” or “does not expect”, “is expected”, “budget”,

“scheduled”, “estimates”, “forecasts”, “intends”, “anticipates” or “does not anticipate”, or “believes”,

or variations of such words and phrases or state that certain actions, events or results “may”, “could”,

“would”, “might” or “will be taken”, “occur” or “be achieved”. Forward- looking information is subject

to known and unknown risks, uncertainties and other factors that may cause the actual results, level

of activity, performance or achievements of Emerita, as the case may be, to be materially different

from those expressed or implied by such forward -looking information, including but not limited to:

general business, eco nomic, competitive, geopolitical and social uncertainties; the actual results of

current exploration activities; risks associated with operation in foreign jurisdictions; ability to

successfully integrate the purchased properties; foreign operations risks; and other risks inherent in

the mining industry. Although Emerita has attempted to identify important factors that could cause

actual results to differ materially from those contained in forward-looking information, there may be

other factors that cause r esults not to be as anticipated, estimated or intended. There can be no

assurance that such information will prove to be accurate, as actual results and future events could

differ materially from those anticipated in such statements. Accordingly, readers s hould not place

undue reliance on forward-looking information. Emerita does not undertake to update any forward-

looking information, except in accordance with applicable securities laws.

65 Queen Street West, Suite 800, Toronto, ON, Canada, M5H 2M5

NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS

DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE

ADEQUACY OR ACCURACY OF THIS RELEASE.