Emerita Reports Albion Process Achieves 81% GOLD and 96% Silver Recovery from Post Flotation Material Samples at Ibw Project
1
EMERITA REPORTS ALBION PROCESS ACHIEVES 81% GOLD AND 96% SILVER RECOVERY
FROM POST FLOTATION MATERIAL SAMPLES AT IBW PROJECT
TORONTO, March 02, 2026 -- Emerita Resources Corp. (TSX -V: EMO; OTCQX: EMOTF; FSE: LLJA)
(the “Company” or “Emerita”) is pleased to announce results from metallurgical tests using the Albion
hydrometallurgical process and has achieved 81% recovery of gold and 96% recovery of silver at its
wholly-owned Iberian Belt West Project (“IBW” or the “Project”).
These results exceed the previously reported metallurgical results (see press release dated May 27, 2025),
which reported gold recoveries of 81.5% and 64.1% using the optimized CLEVR post-flotation process.
The Albion Process ™ for La Romanera deposit is a post -flotation stage metallurgical process.
Specifically, the samples tested were the residual material remaining after the flotation process removed
the base metal concentrates. Some gold and silver reports to the copper and lead concentrates, however,
more than 80% is in the post flotation material. The Albion Process™ is a commercially proven and widely
implemented technology for the treatment of refractory gold concentrates, based on ultra-fine grinding and
oxidative leaching. The process was developed in 1994 at Core’s laboratories and is licenced worldwide
by Glencore Technology.
Albion Process Results
The Albion Process™ test work was conducted at CORE Resources’ laboratories in Australia. The
Albion-based flowsheet tested consisted of three key steps:
1. Ultrafine grinding and atmospheric oxidation using the Albion Process™
2. Oxidative Neutral leaching within at mildly acidic to near‑neutral pH
3. Precious metals recovery via Carbon-in-Pulp (“CIP”) recovery circuit followed by elution
The Albion Process™ test results achieved:
• 81% gold recovery
• 96% silver recovery
These results demonstrate that the Albion hydrometallurgical oxidation route effectively liberates
precious metals contained within refractory sulphide matrices at the IBW Project and significantly
enhances silver recovery.
Comparison with Pyrometallurgical Oxidation + CLEVR Route
The alternative route previously evaluated for the IBW Project consists of:
1. Single-step pyrolysis and thermal oxidation (pyrometallurgical treatment)
2. Cooling, then acid washing
3. Gold leaching using CLEVR Process™ non-cyanide technology
The CLEVR Process™ test results achieved (refer to press release dated May 27, 2025 for additional
details):
• 81.5% gold recovery
• 64% silver recovery
Table 1 provides a comparison of the post-flotation technologies evaluated by the Company for the IBW
Project.
2
Table 1. Precious metals recoveries for Albion Process + CIP compared to Pyrolosis + CLEVR technologies.
Parameter Albion + Neutral Leach + CIP Thermal Oxidation + CLEVR
Gold Recovery 81% 81.5%
Silver Recovery 96% 50-64%
Oxidation Type Hydrometallurgical (atmospheric) Pyrometallurgical
Gold Leaching CIP CLEVR (non-cyanide)
Emerita Resources will continue to test several other technologies in 2026 to determine the most optimal
flowsheet for the Project.
The metallurgical results achieved with both pyrometallurgical and hydrometallurgical routes significantly
enhances the technical robustness of the IBW Project. The availability of two technically viable
processing alternatives reduces metallurgical risk and increases flexibility in the selection of the final
process flowsheet. The results offer potential to further optimize the flotation process and base metals
recoveries and is currently being evaluated by the ongoing test work. The Company will decide on one of
these options for the ongoing Prefeasibility Study (PFS), however there will be opportunity to incorporate
further optimization of the process prior to a final design.
Joaquin Merino, P.Geo., President of Emerita, states “The Albion post flotation optimization process for
the IBW Project is a key piece to unlocking the value of the mineralization that we continue to expand
through our drill campaigns. Both technologies that we have examined demonstrate comparable gold
recoveries of approximately 81%. However, the Albion route maximizes silver recovery, which in the
current market may add significant value to the IBW Project. To define the optimal post flotation
processing route to maximize the value of the IBW Project, Emerita is evaluating alternatives not only
based on precious metals recovery, but also with respect to operational efficiency, environmental
performance, scalability and long-term project economics.”
Emerita remains committed to technical excellence and aims to position the IBW Project as a reference
project in the responsible and efficient development of mineral resources.
Qualified Person
Scientific and technical information in this news release has been reviewed and approved by each of
Joaquin Merino, P.Geo., President of the Company and. Jorge A. Blanco, MChem., Director of
Metallurgy of the Company and each a Qualified Person as defined by NI 43-101. Messrs Merino and
Blanco are not considered independent of the Company.
About Emerita Resources Corp.
Emerita is a natural resource company engaged in the acquisition, exploration, and development of
mineral properties in Europe, with a primary focus on exploring in Spain. The Company’s corporate office
and technical team are based in Sevilla, Spain with an administrative office in Toronto, Canada
For further information, contact:
Ian Parkinson
3
+1 647 910-2500 (Toronto)
www.emeritaresources.com
Cautionary Note Regarding Forward-looking Information
This press release contains “forward -looking information” within the meaning of applicable Canadian
securities legislation. Forward -looking information includes, without limitation, statements regarding the
metallurgy of the IBW project, the viability of metallurgical recoveries, the prospectivity of the IBW project,
the mineralization and the IBW project, the economic viability of the IBW project, the metallurgy of the IBW
project, the Company’s ability to produce and publish an economic study for the Project , the Company’s
future exploration plans and the Company’s future plans. Generally, forward -looking information can be
identified by the use of forward -looking terminology such as “plans”, “expects” or “does not expect”, “is
expected”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates” or “does not anticipate”,
or “believes”, or variations of such words and phrases or state that certain actions, events or results “may”,
“could”, “would”, “might” or “will be taken”, “occur” or “be achieved”. Forward- looking information is subject
to known and unknown risks, uncertainties and other factors that may cause the actual results, level of
activity, performance or achievements of Emerita, as the case may be, to be materially different from those
expressed or implied by such forward -looking information, including but not limited to: general business,
economic, competitive, geopolitical and social uncertainties; the actual results of current exploration
activities; risks associated with operation in foreign jurisdictions; ability to successfully integrate the
purchased properties; foreign operations risks; and other risks inherent in the mining industry. Although
Emerita has attempted to identify important factors that could cause actual results to differ materially from
those contained in forward-looking information, there may be other factors that cause results not to be as
anticipated, estimated or intended. There can be no assurance that such information will prove to be
accurate, as actual res ults and future events could differ materially from those anticipated in such
statements. Accordingly, readers should not place undue reliance on forward-looking information. Emerita
does not undertake to update any forward -looking information, except in a ccordance with applicable
securities laws.