Euro Manganese Reports Fourth Quarter and Year-End 2022 Financial Results and Project Developments
1
NR 2022-26
Euro Manganese Reports Fourth Quarter and Year-End 2022 Financial Results
and Project Developments
VANCOUVER, British Columbia (December 18, 2022) – Euro Manganese Inc. (TSX-V and ASX: EMN; OTCQX:
EUMNF; Frankfurt: E06) (the "Company" or "EMN") is pleased to announce key developments during the
fourth fiscal quarter and to date. The Company has now filed its September 30, 2022 year-end Financial
Statements, Management’s Discussion and Analysis, and other financial reports.
Key Developments During and Subsequent to the Quarter
• Commissioning of Demonstration Plant underway with on -spec samples expected in Q1 2023 .
Following arrival of the Demonstration Plant modules at the Chvaletice site in early September, the
modules were installed within two fully refurbished buildings adjacent to the intended site of the
commercial Chvaletice processing plant. Commissioning commenced in early November and is
advancing on a module -by-module basis. Commissioning is expected to be completed in the first
quarter of 2023 with on-spec samples also expected then. Thereafter, deliverie s of bulk samples to
customers will commence.
- View a video of the demonstration plant modules in process flow order.
Six companies from across the EV supply chain have requested samples from the Demonstration Plant
as they look to qualify the Company’s high -purity manganese products. A further six companies,
including European and North American automotive OEMs, battery manufacturers, and cathode
manufacturers, who are currently testing initial-run Pilot Plant samples, are expecte d to request
Demonstration Plant samples as part of their strategy to move to local supply chains with full
traceability and the highest sustainability standards.
• Pilot Plant samples ready for shipment. The Company’s smaller-scale Pilot Plant in China completed
a second run to produce additional samples for customers.
• Formal off-take tender process underway. A structured off-take tender process, which has included
site visits and making a customer data room available, is ongoing. Multiple indicative bids have been
received, in addition to the five MoUs currently in place . Active discussions are occurring with
numerous consumers of high -purity manganese products, which include battery, chemical and
automobile manufacturers, in Asia, Europe and North America.
• EPCM tender process advancing. The Company has issued an Engineering, Procurement, Construction
Management ("EPCM") tender package to solicit bids from firms interested in developing the
commercial Chvaletice processing plant. The Company aims to partner with a firm who has experience
in developing similar types of projects in Europe. Bids have been received from five tier 1 EPCM firms
and the EPCM contract is expected to be awarded in Q1 2023. Selection of the EPCM contractor will
allow for advancement of basic engineering design and procurement of long lead process equipment.
2
• Completion of two separate Life Cycle Assessment ("LCA") studies for the Chvaletice Manganese
Project. The initial LCA measured the environmental impacts of producing 1kg of HPEMM and 1kg of
HPMSM at Chvaletice. Results were released in August and validated the environmental proposition
of the Project, namely its low carbon footprint and that remediation of the historic tailings area
improves soil and freshwater quality over the lifetime of the Project.
The second LCA compared the global warming potential ("GWP" or "carbon footprint") of 1kg of
HPEMM and 1kg of HPMSM to be produced at Chvaletice with the same produced by the incumbent
industry. Currently, 95% of global high-purity manganese products are processed in China. Highlights
of this LCA, released in December, showed the Company’s high-purity manganese products have a
carbon footprint that is approximately one-third of the China-based incumbent industry.
The results of both LCA studies demonstrate the Company’s commitment to producing low -carbon
battery-grade manganese products. They also sup port conversations with potential off-takers, who
are testing and qualifying both the chemistry and environmental credentials of the Company’s high -
purity manganese products.
• MoU with Statkraft signed to form a renewable energy supply agreement for the Chvaletice Project.
In September, t he Company signed a non -binding Memorandum of Understanding ( "MoU") with
Norwegian state-owned company Statkraft for the long-term supply of carbon-free renewable energy
for the Chvaletice Project. The MoU lays the foundation for the strategic cooperation between Euro
Manganese and Statkraft to support the ongoing net-zero objectives of the Project’s proposed
processing plant. Statkraft is Europe’s largest generator of renewable energy.
• Positive Feasibility Study filed for the Chvaletice Project. During the quarter, the Company filed the
Technical Report and Feasibility Study, prepared in accordance with National Instrument 43-101, on
SEDAR, and filed the Public Report and Feasibility Study, prepared in accordance with the JORC Code,
on the ASX announcement platform . The Feasibility Study outlines robust base case project
economics of after-tax NPV8% of US1.34 billion and an ungeared IRR of 21.9% with a 4.1-year payback
period. Initial capital is estimated at US$757.3 million, including total contingencies of $106.5 million.
Forecast life of project net revenues are US$13.3 billion with an EBITDA of US$8.1 billion.
• Opportunity to produce battery-grade manganese in Canada for the North American market being
explored. Site due diligence is underway on a proposed 15-hectare land parcel within the Port of
Bécancour in Québec. The Company has signed an option agreement w ith the Société du Parc
Industriel et Portuaire de Bécancour allowing it to purchase the site for a period of up to 21 months
subject to the outcome of the due diligence and other conditions. Concurrently, a scoping study is
underway to evaluate the development of an HPEMM dissolution plant to produce a HPMSM powder
and/or a high-purity manganese sulphate solution in Bécancour. The study will leverage the extensive
process development and engineering work already completed at the Chvaletice Project.
• Third and final tranche of EIT InnoEnergy’s investment received. The Company received €62,500
(CAD$80,606) during the quarter, bringing the aggregate funds received from EIT InnoEnergy, an EU-
backed institution, to €250,000. The Company will issue 237,077 shares to EIT InnoEnergy at the price
of CAD$0.34 per share being the 10 -day volume weighted average stock price on the TSX Venture
Exchange ("TSXV") prior to receipt of the third investment tranche. The issuance of the shares is not
expected to oc cur until early January 2023 , and in accordance with Canadian securities laws and
policies of the TSXV, the shares will be subject to a four month and one day statutory hold from their
date of issuance. The funds were used to support work on the Chvaletice Project’s definitive feasibility
study and on the Chvaletice demonstration plant.
3
• Euro Manganese’s manganese metal validated as feedstock in Nano One’s patented one-pot
process. The Company has a joint development agreement with Nano One Materials Corp. , a clean
technology company with patented processes for the low -cost, low -environmental footprint
production of high-performance cathode materials used in lithium-ion batteries. The collaboration is
aimed at developing low-cost, environmentally sustainable applications of high-purity manganese in
next-generation cathode materials.
In August 2022, the Company was approved to receive advisory services and up to $165,000 in funding
from the National Research Council of Canada Industrial Research Assistance P rogram ("IRAP"). The
funding supports the initiative the Company is undertaking with Nano One Materials Corp. ("Nano
One"), Metal direct to Cathode Active Material, as well as the evaluation of the manganese metal by-
product from the battery black mass recycling.
• Joined the Global Battery Alliance ("GBA"). During the quarter, the Company announced its
membership of the Global Battery Alliance, a partnership of leading organizations from across the
battery value chain, governments, academics and NGOs who have mobilized to ensure that battery
production not only supports green energy, but also safeguards human rights and promotes
environmental sustainability. Euro Manganese is the first high-purity manganese company to join the
GBA.
Financial Position
• Cash and cash equivalents of approximately C$21.6 million as at fiscal year -end (September 30,
2022); compared to $31.2 million at fiscal year-end 2022. The decrease in cash of $9.7 million year
over year is a result of $9.6 million used in operating activities and $8.2 million used in investing
activities, which included the payment for the royalty buy back, the demonstration plant and certain
land related payments. The decrease was partially offset by cash generated fro m financing activities
of $8.1 million. The proceeds of cash in financing activities represents the private placement by the
European Bank for Reconstruction and Development.
• Working capital of C$19.8 million as at fiscal year-end (September 20, 2022), compared with C$26.1
million at September 30, 2021.
• Sufficient funding for delivery of key project milestones including completion of environmental
studies, permitting, commissioning of the Chvaletice Demonstration Plant and its operation for one
year. Additional funding will be required for the continuous operation of the Demonstration Plant,
additional land acquisitions, as well as potential future construction of infrastructure and facilities for
the Project and the progress of the Company's North American strategy.
Corporate Team Growth
• Appointment of VP Commercial. Dr. James Fraser joined Euro Manganese as Vice President,
Commercial on October 31, 2022, bringing over 25 years of experience from the geosciences,
consulting, mining, carbon credit and automotive sectors. After completing his doctorate in Earth
Sciences at Oxford, James worked as a strategy consultant for McKinsey & Company and then held a
range of senior positions during his 11 years at Rio Tinto in commercial and technical fields across
different commodities. He subsequently worked for Permian Global, an i nvestment fund focused on
forest carbon and most recently held Head of Sales & Sourcing and Managing Director roles with two
UK-based specialist automotive/motorsport engineering firms.
4
Dr. Matthew James, President & CEO of Euro Manganese, commented:
“The Chvaletice project gained real momentum in 2022. We achieved several project milestones in the
fourth fiscal and calendar quarter of this year , including de livery, installation, and commencement of
commissioning of the Demonstration Plant, advancing selection of an EPCM contractor for the next stage
of project development, and advancing a formal off -take tender process for our high -purity manganese
products. We also completed two Life Cycle Assessments , which not only validated the environmental
credentials of the Project but also sho wed that our high -purity manganese products have a carbon
footprint significantly lower than the current China-based incumbent industry.
The growth opportunities that the North American market presents are compelling, and I look forward to
providing updates on our growth plans in Canada as they evolve. This is an exciting time for the battery
raw materials sector and Euro Manganese is very well-positioned to take advantage of the localisation of
supply to the EV market with high-purity manganese for lithium-ion batteries.
We remain focused on completing commissioning of the Demonstration Plant, producing on-spec samples,
and delivering those samples to prospective customers in the New Year. Equally, we are driving towards
the establishment of long -term commercial offtake agreements and continue to hold active discussions
with interested parties across the battery value chain.
I am extremely proud of the ongoing commitment of our Team to advance the Chvaletice Project and look
forward to continued delivery of key catalysts in 2023 and beyond. Together, we are moving closer to our
vision of being a leading and environmentally responsible producer of high-purity manganese.”
Q4 and Year-End 2022 Conference Call Details
Euro Manganese will host two separate Fourth Quarter and Year -End 2022 conference calls to serve
stakeholders in their respective time zones. Content of both calls will be the same. Replays and transcripts
of both calls will be available on Euro Manganese’s website: www.mn25.ca
CALL #1 – For North American and UK/European Audiences
North America UK/Europe
Date Monday, Dec 19, 2022 Monday, Dec 19, 2022
Time 8:30am PST | 11:30am EST 4:30pm GMT | 5:30pm CET
Registration: https://us06web.zoom.us/webinar/register/WN_vAv0NLdSQvmTnaMeTGgnKg
CALL #2 – For Australian Audiences
Australia North America
Date Tuesday, Dec 20, 2022 Monday, Dec 19, 2022
Time 6:00am AWST | 9:00am AEDT 2:00pm PST | 5:00pm EST
Registration: https://us06web.zoom.us/webinar/register/WN_Z_H3BRPlT4y-CuN54W76vw
About Euro Manganese Inc.
Euro Manganese Inc. is a battery materials company focused on becoming a leading, competitive, and
environmentally superior producer of high -purity manganese for the electric vehicle industry and other
high-technology applications. The Company is advancing development of the Chvaletice Manganese
5
Project in the Czech Republic, which is a unique waste -to-value recycling and remediation opportunity
involving reprocessing old tailings from a decommissioned mine. The Chvaletice project is the only sizable
resource of manganese in Europe, strategically positioning the Company to provide battery supply chains
with critical raw materials to support the global shift to a circular, low-carbon economy.
Authorized for release by the CEO of Euro Manganese Inc.
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies
of the TSX Venture Exchange) or t he ASX accepts responsibility for the adequacy or accuracy of t his
release.
Inquiries
Dr. Matthew James
President & CEO
+44 (0)747 229 6688
Louise Burgess
Senior Director, Investor Relations & Communications
+1 (604) 312-7546
Company Address: #709 -700 West Pender St., Vancouver, British Columbia, Canada, V6C 1G8
Website: www.mn25.ca
Forward-Looking Statements
Certain statements in this news release constitute “forward -looking statements” or “forward -looking
information” within the meaning of applicable securities laws. Such statements and information involve
known and unknown risks, uncertainties and other factors that may cause the actual results, performance
or achievements of the Company, its Chvaletice Project, its North American growth strategy, or industry
results, to be materially different from any future results, performance or achievements expressed or
implied by such forward-looking statements or information. Such statements can be identified by the use
of words such as “may”, “would”, “could”, “will”, “intend”, “expect”, “believe”, “plan”, “anticipate”,
“estimate”, “scheduled”, “forecast”, “predict” and other similar terminology, or state that certain actions,
events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved.
Results of the Feasibility Study constitutes forward-looking information or statements, including but not
limited to estimates of internal rates of return (including any pre-tax and after-tax internal rates of return),
payback periods, net present values, future production, assumed prices for HPMSM and HPEMM, ability
of the Company to achieve a pricing premium for its products, proposed extraction plans and methods,
operating life estimates, cash flow forecasts, metal recoveries and estimates of capital and operating
costs. Such forward -looking information or statements also include, but are not limited to, statements
regarding the Company’s intentions regarding the development of the Chvaletice Project in the Czech
Republic, anticipated timelines for commi ssioning of the Demonstration Plant and on -spec sample
availability, excepted demand for Demonstration Plant samples, the ability to source green power and
other requirements for the Chvaletice Project, anticipated timelines for EPCM contract award, the
benefits of remediating the historic tailings areas, the growth and development of the high purity
manganese products market, the desirability of the Company’s products, the growth of the EV industry,
the use of manganese in batteries, the ability to enter into long term off-take agreements, and statements
regarding the Company’s North American growth strategy.
6
Readers are cautioned not to place undue reliance on forward -looking information or statements.
Forward-looking statements are subject to a number of risks and uncertainties that may cause the actual
results of the Company to differ materially from those d iscussed in the forward-looking statements and,
even if such actual results are realized or substantially realized, there can be no assurance that they will
have the expected consequences to, or effects on, the Company .
Factors that could cause actual re sults or events to differ materially from current expectations include,
among other things: the ability to develop adequate processing capacity; the availability and reliability of
equipment, facilities, and suppliers necessary to complete development; the cost of consumables and
extraction and processing equipment; risks and uncertainties related to the ability to obtain, amend, or
maintain necessary licenses, or permits, risks related to acquisition of surface rights; risks and
uncertainties related to expected production rates; timing and amount of production and total costs of
production; the potential for unknown or unexpected events to cause contractual conditions to not be
satisfied; the failure of parties to contracts with the Company to perform as agreed; risks and uncertainties
related to the accuracy of mineral resource and reserve estimates, the price of HPEMM and HPMSM,
power supply sources and price, reagent supply resources and prices, future cash flow, total costs of
production, and diminishin g quantities or grades of mineral resources and reserves; changes in project
parameters as plans continue to be refined; risks related to global epidemics or pandemics and other
health crises, including the impact of the novel coronavirus (COVID -19); availability and productivity of
skilled labour; risks and uncertainties related to interruptions in production; unforeseen technological and
engineering problems; the adequacy of infrastructure; risks related to project working conditions,
accidents or labour disputes; social unrest or war; the possibility that future results will not be consistent
with the Company's expectations; risks relating to variations in the mineral content and grade within
resources from that predicted; variations in rates of recovery and extraction; developments in EV battery
markets and chemistries; and risks related to fluctuations in currency exchange rates, changes in laws or
regulations; and regulation by various governmental agencies. For a further discussion of risks relevant to
The Company, see "Risk Factors" in the Company's annual information form for the year ended September
30, 2022, available on the Company's SEDAR profile at www.sedar.com.
All forward -looking statements are made based on the Company's current beliefs as well as various
assumptions made by the Company and information currently available to the Company. Generally, these
assumptions include, among others: the presence of and co ntinuity of manganese at the Chvaletice
Project at estimated grades; the ability of the Company to obtain all necessary land access rights; the
ability of the Company obtain all required environmental and other permits; the availability of personnel,
machinery, and equipment at estimated prices , in good order, and within estimated delivery times;
currency exchange rates; manganese sales prices and exchange rates assumed; growth in the manganese
market; appropriate discount rates applied to the cash flows in economic analyses; tax rates and royalty
rates applicable to the proposed operations; the availability of acceptable financing for the Chvaletice
Project and for continued operations ; anticipated extraction losses and dilution; success in realizing
proposed operations in the Czech Republic and for the Company’s North American growth strategy ; and
demand for the Company’s products.
Although the forward -looking statements contained in this news release are based upon what
management of the Company believes are reasonable assumptions, the Company cannot assure investors
that actual results will be consistent with these forward -looking statements. These forward -looking
statements are made as of the date of this news release and are expressly qualified in the ir entirety by
this cautionary statement. Subject to applicable securities laws, the Company does not assume any
obligation to update or revise the forward -looking statements contained herein to reflect events or
circumstances occurring after the date of this news release.