Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

EMM.V ·

July 2024 Demonstration Plant Construction Update

Mine Development & Operations Metallurgy & Processing

Page | 1

July 2024 Demonstration Plant Construction Update

TORONTO, Ontario, August 07, 2024 – Giyani Metals Corp. (TSXV:EMM, GR:A2DUU8) ("Giyani" or

the "Company"), developer of the K.Hill Battery-Grade Manganese Project in Botswana (" K.Hill" or

“the Project”), is pleased to provide an update on construction of the Demonstration Plant ( “Demo

Plant”).

Highlights:

• Substantial progress has been made at the Demo Plant in July with the installation of f ive

additional modular process skids (“ Process Modules”). Seven of the nine Process Modules

have now been installed.

• The five new Process Modules include:

o Three purification circuits (installed in two Process Modules), including reactors, filter

feed tanks and filtrate tanks. These modules form the core of the hydrometallurgical

process and allow the removal of impurities ahead of crystallisation.

o Reagent make-up, comprising powder debagging stations and dissolution tanks for

three primary reagent systems. Reagents will be dosed throughout the plant at the

required locations.

o The filtration Process Module, complete with four filter presses which serve the various

impurity removal processes.

o Water treatment and storage, including both process water and R everse Osmosis

water systems.

• Installation of the instrumentation and electrical cabling, as well as piping works have

commenced and are near complete for the Crystallizer Unit and the internal Crystallizer Process

Module. This intricate work will progress to the other Process Modules in sequence.

• In terms of services, the ventilation system installation is complete. This purpose-built system

is designed to ensure a safe and comfortable operating environment within the plant. The main

reticulation for the utility steam system has been installed and successfully pressure tested.

• Civil works for the external waste storage tank system are in progress . The waste storage

system collects process discharge and waste streams. These streams will be analysed to aid

in the design and cost optimisation of the water recovery system designs for the commercial

plant.

• Simulation test work continues on the Yokogawa Distributed Control System (“DCS”) software

that will be used to control the Demo Plant, which will operate as a continuous process flow,

rather than on batch or lock -cycle methods. This is a massive advantage of th e Demo Plant

allowing Giyani to understand how the Commercial Plant will respond ahead of construction.

• The Project remains on track for commissioning and production of battery -grade manganese

in Q4 2024 for offtaker testing and qualification.

Danny Keating, President and CEO of the Company, commented:

“It is exciting to see the Demo Plant coming together and appreciating the scale of the facility we are

constructing, which is expected to be one of the largest battery-grade manganese process testing and

optimization facilities in the world. Successful construction and operation of the Demo Plant is key to

demonstrating the inherent value of the Project to investors.

The Plant’s ability to operate continuously at this pre-commercial scale will allow Giyani to understand

how the Commercial Plant will respond ahead of construction, pre-emptively detecting and de-risking

potential issues that could arise during ramp-up.

Page | 2

The value of this facility as a tool to optimize our proprietary flowsheet and reduce operating costs will

be immeasurable. The most important feature will be that we will now be able to provide offtakers with

tonnes of product for testing, rather than providing samples measured in grams. This level of production

is not usually available until commercial production is achieved, further de-risking the Project for our

potential partners and financiers.”

Demo Plant Construction Update

The Demo Plant will consist of nine Process Modules, each a self-contained process system within a

fixed frame. An additional five of these Process Modules have been installed since the June update

(see June 20, 2024 news release), see Figures 1A, 1B, 2, 4 and 5 below

Figure 1A and 1B: Purification Process Modules 1 & 2

The Demo Plant construction process follows a set order of Module installation to allow sufficient

working space in the plant as well as simultaneous activities to speed up construction and ultimately

commissioning. The plant is built from the Crystallizer Units to the ore delivery and ball mill, with the

detailed piping and instrumentation following the Module installation. Within the Plant, the following

progress has been made:

• all nine bases/footings for the Process Modules have been installed;

• seven of nine Process Modules have been installed;

• all eight ventilation circuits have been installed;

• instrumentation & wiring is complete on the first Process Module and is in progress on the

second Process Module;

• the utility steam systems have been successfully pressure tested, and concrete has been poured

for the external waste storage tank system;

• assembly of the remaining Process Modules continues offsite for transportation and installation

at the Demo Plant.

Construction and Commission

Five additional Process Modules have been installed since June and are shown in Figures 1A, 1B, 2, 4

and 5 below.

Page | 3

Figure 2: Reagent Make-up Process Module

The Demo Plant is at 1:10 engineering scale of the planned commercial plant in Kanye, Botswana

(“Commercial Plant”). For example, the leach tanks have a 60cm diameter in the Demo Plant and this

is expected to be 8-10x larger at approximately 5m in the Commercial Plant.

Figure 3: Demo Plant Render

The detailed construction program takes advantage of sequential mechanical, piping, electrical, and

instrumentation installation to allow cold commissioning to follow the Process Module sequence in a

highly efficient manner.

Page | 4

Figure 4: Filtration Process Module

Construction of Process Modules continues from the South end of the facility to the North. Once

installed, Process Modules are completed mechanically, electrically and then fitted out with piping and

instrumentation. After this, the initial stages of commissioning C1, C2 and C3 are undertaken at an

individual Process Module level. Commissioning of the full process flow (C4 & C5) will only be

concluded once all of the individual Process Modules are complete.

Stages of construction:

• C1 - Mechanical Completion

• C2 - Dry testing, direction testing, loop testing

• C3 - Cold/Water Commissioning, software testing

• C4 - Hot Commissioning with reagents and steam

• C5 - Production Ramp-up

Figure 5: Water Treatment & Storage Process Module

Page | 5

As part of the construction process, the Company and Met63 Ltd (“Met63”), the EPCM contractor for

the Demo Plant, have agreed to restructure the two site teams and create a single, combined team to

improve efficiencies and management of the project. The existing agreement between the two

companies (previously announced on September 6, 2022), already envisaged a transition and hand-

over of the plant from Met63 to Giyani and this process will now commence as the plant commissioning

phase approaches. The revised agreements will bring synergies as the combined team provides direct

experience in the final phases of construction and importantly assist Giyani in its preparations for

commissioning and ultimately operation of the Plant.

Demo Plant Operations Update

Giyani is continuing with software development and simulation test work on the Yokogawa DCS

software that will be used to operate Giyani’s fully continuous process facility. The ability to continuously

operate at this pre-commercial scale will allow Giyani to understand how the Commercial Plant will

respond ahead of construction, minimizing issues that could arise during ramp-up. Unlike a lab- or pilot-

scale operation, a full, industrial control system is required to operate this large-scale, automated,

hydrometallurgical plant.

The development of all process standard operating procedures (“SOPs”) is now complete. As the Demo

Plant is a duplicate of the anticipated Commercial Plant, the overall operating requirements and system

requirements are very similar. Alongside the engineering, commercial and research benefits of the

Demo Plant, the development of SOPs will facilitate a smooth transition to full-scale production.

Finalization of the contract for the on-site, independent, ISO-certified, hydrometallurgical laboratory is

imminent. This laboratory, which includes ICP-OES and XRF equipment, will allow full commercial-level

metal accounting and provide rapid assay turnaround times to enable effective operation of the Demo

Plant.

About Giyani

Giyani is focussed on becoming the dominant western-world producer of sustainable, low carbon high

purity battery grade manganese for the electric vehicle (“EV”) industry. The Company has developed a

proprietary hydrometallurgical process to produce battery grade manganese (HPMSM), a lithium-ion

battery cathode precursor material critical for EVs.

The Company has secured US$26m in financing from two strategic partners, ARCH Sustainable

Resources Fund LP and the Industrial Development Corporation of South Africa, as it aims to progress

the K.Hill battery-grade manganese project in Botswana to construction by building and operating the

Demo Plant and completing a Definitive Feasibility Study by H1 2025.

Additional information and corporate documents may be found on www.sedarplus.ca and on Giyani

Metals Corp. website at https://giyanimetals.com/.

Qualified Persons / NI 43-101 Disclosures

A National Instrument 43-101 (“NI 43-101”) technical report including results of the PEA and the MRE

can be found on SEDAR+ at www.sedarplus.ca and made available on the Company's website at

https://giyanimetals.com/.

Mr. Justin Taylor CEng FIMMM QMR BSc Eng (Chem) is a qualified person, as defined by NI 43-101.

Mr. Taylor is the Company’s Group Process Engineer and has reviewed and approved the scientific

and technical content contained in this news release but is not independent for the purposes of NI 43-

101.

Page | 6

On behalf of the Board of Directors of Giyani Metals Corp.

Danny Keating, President and CEO

Contact:

Tel: +1289-291-7632

Danny Keating, President & CEO

[email protected]

Charles FitzRoy, Head of Corporate Development & Strategy

[email protected]

Neither the TSX Venture Exchange (the "TSXV") nor its Regulation Services Provider (as that term is defined in the

policies of the TSXV) accepts responsibility for the adequacy or accuracy of this news release.

The securities described herein have not been registered under the United States Securities Act of 1933, as amended

(the "U.S. Securities Act"), or any state securities laws, and accordingly, may not be offered or sold to, or for the account

or benefit of, persons in the United States or "U.S. persons," as such term is defined in Regulation S promulgated under

the U.S. Securities Act ("U.S. Persons"), except in compliance with the registration requirements of the U.S. Securities

Act and applicable state securities requirements or pursuant to exemptions therefrom. This news release does not

constitute an offer to sell or a solicitation of an offer to buy any of the Company's securities to, or for the account of benefit

of, persons in the United States or U.S. Persons.

Forward Looking Information

This news release contains "forward-looking information" within the meaning of applicable Canadian securities legislation.

All statements in this news release, other than statements of historical fact, that address events or developments that

Giyani expects to occur, are "forward-looking statements". Forward-looking statements are statements that are not

historical facts and are generally, but not always, identified by the words "expects", "does not expect", "plans",

"anticipates", "does not anticipate", "believes", "intends", "estimates", "projects", "potential", "scheduled", "forecast",

"budget" and similar expressions, or that events or conditions "will", "would", "may", "could", "should" or "might" occur.

Such statements include without limitation: the Company the ongoing construction, commissioning and operation of the

Demo Plant, installation of additional Process Modules, design and finalization of the lab, and timing thereof, completion

and timing of the DFS or at all.

All such forward-looking statements are based on the opinions and estimates of the relevant management as of the date

such statements are made and are subject to certain assumptions, important risk factors and uncertainties, many of which

are beyond Giyani's ability to control or predict. Forward-looking statements are necessarily based on estimates and

assumptions that are inherently subject to known and unknown risks, uncertainties and other factors that may cause

actual results, level of activity, performance or achievements to be materially different from those expressed or implied by

such forward-looking statements. In the case of Giyani, these facts include anticipated operations in future periods,

planned exploration and development of its properties, and plans related to its business and other matters that may occur

in the future. This information relates to analyses and other information that is based on expectations of future

performance and planned work programs.

Forward-looking information is subject to a variety of known and unknown risks, uncertainties and other factors which

could cause actual events or results to differ from those expressed or implied by the forward-looking information, including,

without limitation: inherent exploration hazards and risks; risks related to exploration and development of natural resource

properties; uncertainty in Giyani's ability to obtain funding; commodity price fluctuations; recent market events and

conditions; risks related to the uncertainty of Mineral Resource calculations and the inclusion of Inferred Mineral

Resources in economic estimation; risks related to governmental regulations; risks related to obtaining necessary licences

and permits; risks related to Giyani's business being subject to environmental laws and regulations; risks related to the

Company's mineral properties being subject to prior unregistered agreements, transfers, or claims and other defects in

title; risks relating to competition from larger companies with greater financial and technical resources; risks relating to

the inability to meet financial obligations under agreements to which they are a party; ability to recruit and retain qualified

personnel; and risks related to the Company's directors and officers becoming associated with other natural resource

companies which may give rise to conflicts of interests. This list is not exhaustive of the factors that may affect Giyani's

forward-looking information. Should one or more of these risks and uncertainties materialize, or should underlying

assumptions prove incorrect, actual results may vary materially from those described in the forward-looking information

or statements.

Giyani's forward-looking information is based on the reasonable beliefs, expectations and opinions of the Company's

respective management on the date the statements are made, and Giyani does not assume any obligation to update

forward looking information if circumstances or management's beliefs, expectations or opinions change, except as

required by law. For the reasons set forth above, investors should not place undue reliance on forward-looking information.

Page | 7

For a complete discussion with respect to Giyani and risks associated with forward-looking information and forward-

looking statements, please refer to Giyani's continuous disclosure documents which are filed on SEDAR+ at

www.sedarplus.ca.