Giyani Announces Positive PEA Results for its K.Hill Manganese Project in Botswana with an After-Tax Net Present Value of C$379 Million (US$285 Million)

Economic Studies

Giyani Announces Positive PEA Results for its K.Hill Manganese Project in

Botswana with an After-Tax Net Present Value of C$379 Million (US$285 Million)

Not for distribution to U.S. newswire services or for dissemination in the United States

OAKVILLE, Ontario, Aug. 15, 2019 -- Giyani Metals Corp. (TSXV:EMM) (FRANKFURT:KT9) (WKN:A2DUU8) (“Giyani” or the

“Company”) is pleased to announce the results of the preliminary economic assessment (“PEA”) for its K.Hill manganese

project.

Robin Birchall, CEO of Giyani Metals Corp. commented:

“We are extremely pleased with the completion of the PEA for K.Hill, our first deposit in Botswana, and we are even more

delighted with the findings of this report which demonstrates the strong economic potential of the K.Hill manganese project.

Our immediate next steps are to continue hydrometallurgical testing with electro-refining to produce high purity EMM samples

for testing by battery makers. We will move forward with a definitive feasibility study in order to upgrade K.Hill into a mineral

reserve through a targeted reserve drilling campaign, and ultimately develop a mine plan for the K.Hill project.”

Highlights:

• PEA based on the 1.1 million tonnes inferred mineral resource estimate that the Company announced on September

28, 2018

• 9-year potential project operating life producing 245,000 tonnes of high-purity electrolytic manganese metal (“HPEMM”)

• Pre-tax NPV of C$491 million (US$369 million) and after tax NPV of C$379 million (US$285 million), using a 10%

discount rate

• Estimated C$144.4 million (US$108.5 million) in pre-production capital, C$13.2 million (US$9.9 million) in sustaining

capital, C$23.7 million (US$17.8 million) in contingency at 15%, and C$6.7 million (US$5 million) closure costs for a

total project capital of C$188 million (US$141.3 million)

• After-tax IRR of 90.6% and a 1.5 year payback period

• Project economics are based on a projected average price of US$4,700/tonne for HPEMM of 99.9% Mn over the project

life

• Access to established logistics chain and infrastructure in a well-developed and mining friendly jurisdiction

• Initial attractive project economics and growing market demand for battery-grade manganese products should attract

multiple offers of project financing from the mining investment community

• Opportunities exist to improve returns through further enhancement of K.Hill mineral resources into a mineral reserve

and the addition of other deposits within the greater Giyani licence area including the existing Otse and Lobatse

deposits

• Immediate next steps: continue hydrometallurgical testing with electro-refining to produce HPEMM samples for testing

by battery makers and upgrade K.Hill into a mineral reserve through a targeted reserve drilling campaign and a

feasibility study

• Further next steps: commence environmental impact assessment and feasibility study in preparation for the mine

permit application in 2020

The PEA was undertaken by SRK Consulting (UK) Limited (“SRK”), with metallurgical testwork and design input from Lab 4

Inc. (“Lab4”), a metallurgy consulting firm managed by Dr. Ian Flint, the Department of Geology of Dalhousie University and the

Minerals Engineering Centre of Dalhousie University, all in Halifax, Nova Scotia, Canada. The PEA is also based on an inferred

mineral resource estimate as detailed in the NI 43-101 report prepared by MSA Group (Pty) Ltd. (“MSA”) in November 2018.

An updated NI 43-101 Technical Report on the K.Hill manganese project including results of the PEA will be filed on SEDAR

within 45 days of the issuance of this news release and made available on the Company’s website.

The PEA is considered preliminary in nature and includes inferred mineral resources that are considered too speculative

geologically to have the economic considerations applied to them that would enable them to be categorized as mineral

reserves, and accordingly there is no certainty that the preliminary economic assessment will be realized. The expected

accuracy of costs in the PEA are within a -35% to +45% level of confidence, as is appropriate for the level of study and

accuracy of the input data provided. Mineral Resources that are not Mineral Reserves do not by definition have demonstrated

economic viability.

Summary of PEA Results

The following sections are extracted from the SRK PEA document.

Mining

The envisaged mining method for the K.Hill Project is traditional truck and shovel.  Due to the low processing throughput, and

reasonable strip ratio, the volume of total material moved (TMM) is easily manageable.  For the mining part of the PEA, the

key tasks that were undertaken are listed below.

• Analysis of the geological model and adaptation for mine planning purposes

• Definition of key operating cost components, revenue and applicable royalties

• Open pit optimization to generate a pit shell

• Practical design of the pit including ramp access

• Practical waste dump design

• Layout of haul roads

• Generation of a mining schedule, including pushbacks

• Equipment calculations to determine fleet requirements

• Determination of mining fleet based on similar operations worldwide

The pit optimization parameters are shown in Table 1 and are discussed below.

The mining cost was calculated based on the S&P database for published 2018 mining costs for similar small-scale mining

operations around the world, as well as a similar-sized SRK client operation in Africa. 

Dilution and recovery were estimated based on similar results achieved using relatively small scale equipment. It is anticipated

that an efficient operation of the project may improve project economics.

The processing recovery used in the pit optimization was based on initial results from the metallurgical test work on leaching. 

Processing costs are elevated due to the electrowinning and electrorefining processes. Separation of the Mn requires

significant electricity, estimated at 6,800 kWh/tonne processed. 

The sale price of US$4,700/t has been assumed for a 99.9% HPEMM product.

Giyani estimates that the project should be able to operate comfortably at a G&A operating cost of US$3M/yr. The royalty in

Botswana from the sale of manganese is 3%.

Table 1: Pit Optimization Parameters

Parameters Units Base Case Basis

Production      

  Production Rate (tpa) 150,000 SRK Assumption - RoM

Geotechnical      

  Overall Slope (Deg) 45 SRK Assumption Angle Oxide

  Overall Slope (Deg) 45 SRK Assumption Angle Fresh

Mining Factors      

  Dilution (%) 5.0 SRK Calculation

  Recovery (%) 95.0 SRK Calculation

Processing      

  Recovery MnO (%) 94.0 Giyani provided

Operating Costs      

  Mining Cost (US$/trock) 3.14 SRK Calculation

  Incremental (US$/ 1m bench) 0.01 SRK Assumption Mining Cost

  Reference Level (Z Elevation) 1385 

  Replacement (US$/tRoM)   Not used Capital

  Rehabilitation (US$/tRoM)   Not used Cost

  Processing (US$/tRoM) 250.00 SRK Calculation

  Selling Cost Mn (%) 3.0 Botswana

    (US$/t) 141 

  G&A (US$M/Year) 3,000,000 Client assumption

    (US$/tRoM) 20.00 

Metal Price      

  EMM (US$/t) 4,700 Client provided

Other      

  Discount Rate (%) 10 

Cut-Off Grade      

  Marginal (% MnO) 8.81 SRK Calculation

Figure 1 shows the total material movement by Cutback on a quarterly basis

Figure 1: Total Material movement by Cutback on a quarterly basis:

https://www.globenewswire.com/NewsRoom/AttachmentNg/13b19400-4e47-44b6-b2d3-a8b44cca4ad3

Figure 2 shows run of mine tonnage to plant split by Cutback by quarter

Figure 2: Run of mine tonnage to plant split by Cutback by quarter:

https://www.globenewswire.com/NewsRoom/AttachmentNg/da11c7b9-644b-4bdb-9f08-91ec97ff25a5

The mining schedule for total movement is shown in Figure 3 below

Figure 3: Total Material Movement:

https://www.globenewswire.com/NewsRoom/AttachmentNg/83f96d39-431c-4c05-875c-dc4d0ec8b76c

Based on the work undertaken in the PEA the following key conclusions are made:

• The mining of the K.Hill deposit is a relatively straightforward affair, with no known or expected issues

• Mining equipment, maintenance and support services to the mining operation are easily obtained in the local region and

are easily brought to site

• The site has good access to quality infrastructure

• No blasting is anticipated to be required, but a hydraulic breaker will need to be used to break the breccia cap

• A relatively small mining fleet will be able to deal with the required volumes that need to be moved

• A relatively light labour crew is required

Metallurgy and Mineral Processing

A simplified block diagram for the proposed process for the production of electrolytic manganese metal is shown in Figure 4

Figure 4: Process Block Diagram:

https://www.globenewswire.com/NewsRoom/AttachmentNg/fb923611-62ce-4987-94f8-88b340803824

Comminution

The comminution circuit will consist of several stages of crushing and grinding to achieve the target grind size, which is a P 80

of 200 mm subject to further optimization.

Leaching

Leaching will be undertaken in a series of open topped tanks.  The test work indicates a total leach residence time of two

hours.  Filtered solids from the comminution circuit will be mixed with barren electrolyte returned from the EW stage, with

reagent sulphuric acid added to meet the target acid strength (260 g/l based on the test work), as well as the reductant

sucrose, which is consumed during the leach reaction.

Liquid/Solid Separation

A vacuum belt filter is envisaged for the solid / liquid separation between leaching and solvent extraction (SX).  This stage will

incorporate a cake washing stage, in order to both acquire maximum soluble Mn recovery, and to minimize the residual acid

content of the filter cake.

Solvent Extraction (SX)

The filtrate from the leaching stage will be subjected to SX for impurity removal.  The SX circuit will consist of one or more

extraction stages, one or more stripping stages, plus washing / scrubbing stage/s as appropriate.

Purified electrolyte from the SX circuit will be advanced to the EW circuit.  Raffinate will be recycled internally within the SX

circuit.  A bleed stream of raffinate will be removed for water balance and impurity (principally Ca and Mg) removal purposes. 

As part of the bleed stream treatment, a manganese-containing precipitate will be produced, which will be recycled to the

leach or extraction circuits to minimize Mn losses.

Electrowinning

Manganese metal will be recovered from the purified solution from SX by electrowinning.  Due to the particular electrochemical

behaviour of manganese, the EW cells will be configured with a membrane to separate the anodic and cathodic reaction

zones.

Electrorefining

In order to produce high purity (>99.7%) Electrolytic Manganese Metal (EMM), a second stage of electrorefining is required. 

The grades of the first stage EMM is typically suitable for electrorefining in halide-based solutions.  The final product EMM will

be produced in typical flake form.

Based on the scoping level work completed for this assignment, SRK concludes the following:

• There is a viable process route for the proposed EMM product

• Further detailed test work is required to support the product specification, recoveries, operating costs, plant flow sheets

and capital cost estimation

Financial Evaluation

The following general assumptions have been applied to the Technical Economic Model (“TEM”) for the Project:

• is expressed in real terms

• is presented at 2019 money terms for Net Present Value (NPV) calculation purposes;

• applies a Base Case discount rate of 10%

• is based on long term manganese prices of US$4,700 /t for a 99.9% HPEMM product

• is expressed in after-tax and pre-financing terms and assumes 100% equity

• Giyani’s tax advisers have indicated that they consider it likely that a flat Botswanan corporate tax rate of 22% can be

applied, accordingly a base corporate tax rate of 22% has been used

• selling costs have been approximated at 3.0% of revenue

• for tax purposes, capital investments are depreciated immediately, and unredeemed capital is carried forward

indefinitely as permitted for mining projects in Botswana.

Table 2 below summarizes the expected capital costs based on the PEA

Table 2: Summary of unit operating costs

Operating Costs LoM (US$/t milled)

Mining 26.2

Rehandle 0.0

Processing 276.5

G&A 20.0

Selling Costs 37.3

Contingency 0.0

Total Operating Costs 360.0

Total capital costs are estimated to be US$141.3M over the Life of Project.  Mining capital costs are estimated at US$3.6M. 

Processing capital costs amount to US$95.9M. Infrastructure capital amounts to US$6.3M. Sustaining capital and closure

cost provisions amount to US$9.3M and US$5M respectively. Contingency has been included at 15% and amounts to

US$17.7M.  Table 3 summarizes the capital costs over the Project life.

Table 3: Summary of capital costs

Capital Costs LoM (US$M)

Mining 3.6

Processing 95.9

Tailings 2.7

Infrastructure 6.3

Sustaining Capital 9.9

Contingency - Capital 17.9

Closure Costs 5.0

Total Capital 141.3

Net Present Value

The NPV of the cash flows are shown in Tables 4 and 5 using discount rates from 0% to 15% in an after-tax and pre-tax

context.  At a discount rate of 10%, the after-tax NPV for the Project is US$285M.

Table 4: Summary of NPV’s – After Tax pre-finance

Base Case Summary of NPV's            

Discount Rate 0% 5% 8% 10% 12% 15%

NPV (US$M) 451 356 311 285 261 230

Table 5: Summary of NPV’s Pre-Tax pre-finance

Base Case Summary of NPV's            

Discount Rate 0% 5% 8% 10% 12% 15%

NPV (US$M) 580 459 402 369 339 300

Conclusion

Based on the work carried out for the PEA, SRK concludes the following:

• The Project reflects a positive NPV of US$285M at a 10% discount rate.  Further investment and technical studies are

therefore warranted

• Average operating costs have been estimated at US$360/t milled

• Total capital expenditure has been estimated at US$141.3M

• The Project NPV is most sensitive to revenue (grade or commodity price) but has lower sensitivity to operating costs

and is least sensitive to capital costs

• The Project critically depends on achieving production of a HPEMM product.  If this grade of product cannot be

achieved, the value of the saleable product falls significantly

Qualified Persons / NI 43-101 Statements

The Qualified Person (as that term is defined by National Instrument 43-101) responsible for preparing the PEA for the K.Hill

manganese project is Michael John Beare, BEng, CEng, MIOM of SRK Consulting (UK) Ltd. Mr. Beare has reviewed and

approved the scientific and technical content contained in this press release and verified the underlying technical data. Mr.

Beare is independent of the Company.

Hydrometallurgical testwork was performed on three samples taken from drill cores extracted from the K.Hill deposit during the

Company’s drilling program in 2018. The drill cores were placed in a plastic bag along with a sample tag. Bags were sealed

with a single use tie. Samples were securely stored prior to shipping to Lab 4 Inc. in Halifax, Nova Scotia, Canada.

Leach testing procedure

All three samples were ground to a d80 of 200 microns.  From each main sample, five sub-samples were drawn.  One sub-

sample was set aside and assayed later as the head grade and the four remaining sub-samples were used for acid leaching

tests with reductant. All tests were performed using the same size of rock sample, with H 2SO4 solution at a certain

temperature.  Four independent leaches were performed with the reductant with only residence time being varied.  All five sub-

samples were assayed.

Extraction testing procedure

The output of the leaching circuit (leach solution) was fed into the extraction circuit and mixed with an organic solution where

metals transfer from the leach solution to the organic solution. These two solutions were then separated and fed into a

stripping circuit and a precipitation circuit where the majority of unwanted metals get precipitated leaving the manganese with

traces of other metals in the solution.

Electrowinning testing procedure

The output solution from the extraction circuit was fed into an electrowinning cell and processed for a period of time operated

in batch mode.  This was repeated on the same electrode with an additional quantity of the solution for an additional period of

time. An initial voltage level was applied between the anode and cathode.  This voltage was controlled to maintain a constant

current density. The voltage was subsequently increased with time as the conductivity of the solution changed with the

removal of the Mn2+ ions. The process results in manganese plated on the cathode of the cell and some solids along with the

spent solution. A filter separated the solids from the solution. The solution gets treated and recycled to the leach circuit along

with the solids.

About Giyani

Giyani Metals Corp. is a Canadian based junior exploration company focused on creating shareholder value by accelerating

the development of its battery-grade manganese projects in the Kanye Basin, Botswana, Africa.

Additional information and corporate documents may be found on www.sedar.com and on Giyani Metals Corp. website:

http://giyanimetals.com/ .

On behalf of the Board of Directors of Giyani Metals Corp.

Robin Birchall, CEO

Contact:

Giyani Metals Corporation

Robin Birchall

CEO, Director

+447711313019

[email protected]

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX

Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.

Forward-Looking Information

This press release contains “forward-looking information” within the meaning of applicable Canadian securities legislation. All

statements in this news release, other than statements of historical fact, that address events or developments that Giyani

expects to occur, are “forward-looking statements”. Forward-looking statements are statements that are not historical facts

and are generally, but not always, identified by the words “expects”, “does not expect”, “plans”, “anticipates”, “does not

anticipate”, “believes”, “intends”, “estimates”, “projects”, “potential”, “scheduled”, “forecast”, “budget” and similar expressions,

or that events or conditions “will”, “would”, “may”, “could”, “should” or “might” occur. Specific forward-looking statements and

forward-looking information herein includes completion of the purchase and sale of the Giyani’s 45% interest in Rock Island

and receipt of regulatory approvals to close.

All such forward-looking statements are based on the opinions and estimates of the relevant management as of the date such

statements are made and are subject to certain assumptions, important risk factors and uncertainties, many of which are

beyond Giyani’s ability to control or predict. Forward-looking statements are necessarily based on estimates and assumptions

that are inherently subject to known and unknown risks, uncertainties and other factors that may cause actual results, level of

activity, performance or achievements to be materially different from those expressed or implied by such forward-looking

statements. In the case of Giyani, these facts include their anticipated operations in future periods, planned exploration and

development of its properties, and plans related to its business and other matters that may occur in the future. This information

relates to analyses and other information that is based on expectations of future performance and planned work programs.

As well, all of the results of PEA constitute forward-looking information or statements, including the envisaged mining method

of truck and shovel, the estimated NPV of the K.Hill Project, the estimated average operating costs, the estimated total capital

expenditures, the estimated IRR, estimated future production, that further investment and technical studies are warranted at

this time, and the timing, results and completion of future studies. Furthermore, with respect to this specific forward-looking

information concerning the development of the K.Hill Project, Giyani has based its assumptions and analysis on certain

factors that are inherently uncertain. Uncertainties include among others: (i) the adequacy of infrastructure; (ii) unforeseen

changes in geological characteristics; (iii) changes in the metallurgical characteristics of the mineralization; (iv) the ability to

develop adequate processing capacity; (v) commodity prices; (vi) the availability of equipment and facilities necessary to

complete development; (vii) the cost of consumables and mining and processing equipment; (viii) unforeseen technological and

engineering problems; (ix) accidents or acts of sabotage; (x) currency fluctuations; (xi) changes in laws or regulations; (xii) the

availability and productivity of skilled labour; (xiii) the regulation of the mining industry by various governmental agencies; and

(xiv) political factors, including political stability.

Forward-looking information is subject to a variety of known and unknown risks, uncertainties and other factors which could

cause actual events or results to differ from those expressed or implied by the forward-looking information, including, without

limitation: inherent exploration hazards and risks; risks related to exploration and development of natural resource properties;

uncertainty in Giyani’s ability to obtain funding; commodity price fluctuations; recent market events and conditions; risks

related to the uncertainty of mineral resource calculations and the inclusion of inferred mineral resources in economic

estimation; risks related to governmental regulations; risks related to obtaining necessary licenses and permits; risks related

to their business being subject to environmental laws and regulations; risks related to their mineral properties being subject to

prior unregistered agreements, transfers, or claims and other defects in title; risks relating to competition from larger

companies with greater financial and technical resources; risks relating to the inability to meet financial obligations under

agreements to which they are a party; ability to recruit and retain qualified personnel; and risks related to their directors and

officers becoming associated with other natural resource companies which may give rise to conflicts of interests. This list is

not exhaustive of the factors that may affect Giyani’s forward-looking information. Should one or more of these risks and

uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those

described in the forward-looking information or statements.

Giyani’s forward-looking information is based on the reasonable beliefs, expectations and opinions of their respective

management on the date the statements are made, and Giyani does not assume any obligation to update forward-looking

information if circumstances or management’s beliefs, expectations or opinions change, except as required by law. For the

reasons set forth above, investors should not place undue reliance on forward-looking information. For a complete discussion

with respect to Giyani and risks associated with forward-looking information and forward-looking statements, please refer to

Giyani’s financial statements and related MD&A, all of which are filed on SEDAR at www.sedar.com.