Element79 Gold Reports Multiple High Grade Results from Pillune Area, Lucero Project, Arequipa, Peru
Element79 Gold Reports Multiple High Grade Results from
Pillune Area, Lucero Project, Arequipa, Peru
Vancouver, BC – February 6, 2024 – Element79 Gold Corp. (CSE:ELEM)
(OTC:ELMGF) (FSE:7YS0) ("Element79 Gold", the "Company") is pleased to announce
additional underground chip sample assay results from the 2023 work campaign at the Pillune
Area of the Lucero mine project in Arequipa, Peru.
HIGHLIGHTS:
- Assays from 2023 underground grab- and channel samples completed by SLM
Resource Group from the Pillune Area of the past-producing Lucero mine project have
been received, reviewed and reporting here
- Multi-ounce Gold and Multi-ounce Silver, reinforce the significant potential of
restarting this past-producing mine today
o 10.5 oz/t Gold and >29 oz/t Silver in sample LUC2023-33
o 4.7 oz/t Gold and >29 oz/t Silver in Sample LUC2023-34
- Further lab assays from remaining 2023 work campaigns are being received shortly and
will be released as soon as available.
“This batch of 24 assay results from the 2023 underground sampling program conducted by
contractor SLM Resource Group completed on the Pillune Area of the Lucero project revealed
impressively high-grade gold and silver mineralization, up to 10.5 ounces per ton gold and >29
ounces per ton silver, in addition to some great base metals results. This is encouraging to us
as it further validates the potential for a significant high-grade future operation.” said James
Tworek, CEO and Director of Element79 Gold.
The assay results were collected during the 2023 program consists of underground chip
samples across several veins from the Apacheta Zone which retuned up to 11.7 oz/t gold and
247 oz/t silver (see April 27th 2024 news release), Pillune Area (the focus of this release), and
Sando Alcalde
Element79 Press Release
2 o7
Area, where local Informal miners have worked sporadically for the last several years. The
2023 work program carried out by SLM Resource Group revealed high- grade gold-silver
mineralization confirming two orientations of mineralized structures. These comprise a
roughly E-W orientation associated with higher precious metals and a more NW orientation
associated with higher base metals, both with economic grades (Table 1.).
Table 1. Underground chip sample assay results for the Pillune Area of the Lucero Project
Sample Au Au Ag Ag Cu Pb Zn Vein
Number g/tonne Oz/ton g/tonne Oz/ton % % % Width (m)
LUC2023-22 1.0 0.03 30 0.9 0.02 0.05 0.30 0.10
LUC2023-23 2.8 0.08 9 0.3 0.01 0.26 0.18 0.05
LUC2023-24 0.2 0.01 23 0.7 0.09 0.88 0.23 0.05
LUC2023-25 1.3 0.04 6 0.2 0.03 0.17 0.23 0.30
LUC2023-26 8.0 0.23 205 6.0 0.02 0.12 0.18 0.10
LUC2023-27 24.2 0.71 37 1.1 0.14 1.60 2.33 0.10
LUC2023-28 10.8 0.32 24 0.7 0.15 0.31 0.46 0.10
LUC2023-29 24.5 0.71 33 1.0 0.14 1.06 1.35 0.30
LUC2023-30 36.0 1.05 48 1.4 0.18 1.41 0.54 0.30
LUC2023-31 38.0 1.11 83 2.4 0.25 1.50 0.87 0.30
LUC2023-32 34.9 1.02 193 5.6 0.17 1.47 1.51 0.10
LUC2023-33 359.0 10.47 >1000* >29.2* 0.08 1.31 0.07 0.10
LUC2023-34 160.0 4.67 >1000* >29.2* 0.04 0.60 0.82 0.05
LUC2023-35 28.0 0.82 179 5.2 0.02 0.27 0.30 0.30
LUC2023-36 8.8 0.26 304 8.9 0.09 0.57 0.73 0.10
LUC2023-37 12.6 0.37 271 7.9 0.06 0.57 0.91 0.10
LUC2023-38 6.2 0.18 33 0.9 0.03 1.04 1.60 0.10
LUC2023-39 51.8 1.51 670 19.5 0.01 1.14 1.30 0.10
LUC2023-40 75.7 2.21 246 7.2 0.10 4.21 3.16 0.05
LUC2023-41 28.5 0.83 75 2.2 0.10 2.06 2.21 0.05
LUC2023-42 25.6 0.75 268 7.8 0.01 0.08 0.10 0.05
LUC2023-43 22.8 0.67 56 1.6 0.05 1.70 2.21 0.10
LUC2023-44 54.9 1.60 >1000* >29.2* 0.02 0.65 0.92 0.10
LUC2023-45 47.5 1.38 >1000* >29.2* 0.06 0.38 0.54 0.10
*Upper detection limit of silver analysis was 1,000 g/tonne
"The latest assay results confirm the high-grade nature of the Lucero project, consistent with
visible mineralization observed during our team’s site visits and by prior operators," said James
Tworek, CEO of Element79 Gold. "We have the benefit of a running start as the Lucero project
has been in production in the past, local artisanal miners are actively working in the region
Element79 Press Release
3 o7
today, and barring annual rainy season conditions, many underground workings remain
accessible. These new results provide high-grade results from SLM’s 2023 campaign on the
Pillune Area of Lucero and continue to encourage our belief that the project hosts significant
commercially exploitable veins as it has seen little modern exploration. We await one more
batch of assays from the SLM campaign, as well as the results of the mapping and more
thorough channel sampling campaign carried out by the Ore Discovery team, which ended on
December 31 st. We look forward to sharing additional results shortly, as lab results are
received."
Tworek added, "These positive results, along with historical data are being modeled and
analyzed to produce underground and surface drill targets for our upcoming drill program. We
look forward to updating our investors on additional results from the 2023 work campaigns as
we receive and analyze them. "
Figure 1. Lucero Project showing major historic mining areas, including Pillune Area
Element79 Press Release
4 o7
Figure 2. Satellite image showing the Pillune Area of the Lucero Project, mine workings and
veins that were sampled during the 2023 work program.
Element79 Press Release
5 o7
Figure 3. Photographs of select underground chip sample locations: A LUC2023-33 (10.5 oz/t
gold, >29 oz/t silver), B LUC2023-34 (4.7 oz/t gold, >29 oz/t silver), C LUC2023-40, 41 &
42 (2.2 oz/t gold / 7 oz/t silver, 0.8 oz/t gold / 2 oz/t silver & 0.8 oz/t gold / 8 oz/t silver
respectively), D LUC2023-45 (1.4 oz/t gold, >29 oz/t silver.
About the Lucero Project
Formerly operated as the Shila mine from 1989 to 2005 by Buenaventura (NASDAQ:BVN),
Lucero consists of 10,813 hectares located in the Shila range of southern Peru, which contains
several historic high-grade gold-silver mines. Lucero consistently delivered high grades during
16 years of operations, and between 1998 and 2004 reported production averaging
approximately 18,800 ounces of gold and 435,000 ounces of silver per year at grades of 14.0
g/t gold and 373 g/t silver, with recoveries at the ore processing facility averaging 94.5% for
gold and 85.5% for silver.
Element79 Press Release
6 o7
QA/QC
All samples were collected by Helmut Herrera of SLM Mining Services S.A.C of Peru (Lima)
and submitted to Certimin S.A. of Peru (Lima). Samples were prepared by crushing to 90%
passing <2mm, with a 250-gram split pulverized to 85% passing 75 micrometers, and analysed
by four acid digestion followed by Inductively Couple Plasma with an Optical Emission
Spectrophotometry detector (ICP-OES) for 35 elements including silver, while gold was
analyzed by Fire Assay with a 30-gram sample with an Atomic Absorption Spectrophotometry
detector (AAS) finish for assay up to 10 g/t. Overlimit gold was analysed by fire assay with a
gravimetric finish. Overlimit Silver (>100 g/t) was analysed by four acid digestion and AAS
finish. Overlimit lead and zinc were analysed by ore grade techniques using four acid digestion
and ICP-OES finish.
Qualified Person
The technical information in this release has been reviewed and verified by Neil Pettigrew,
M.Sc., P. Geo., Director of Element79 Gold and a "qualified person" as defined by National
Instrument 43-101.
About Element79 Gold Corp
Element79 Gold Corp is a gold and silver mining company committed to maximizing
shareholder value through responsible mining practices and sustainable development of its
projects. Element79 Gold's core focus is on developing its past-producing, high-grade gold
and silver mine, the Lucero project located in Arequipa, Peru, with the intent to restart
production in 2024. In January 2024 the Company entered into a non-binding LOI with
Compañía de Minas Buenaventura regarding the potential offtake of minerals produced from
the Lucero project.
The Company also holds a portfolio of 5 properties along the Battle Mountain trend in Nevada,
with the Clover and West Whistler projects believed to have significant potential for near-term
resource development. Three properties in the Battle Mountain Portfolio are under contract for
sale to Valdo Minerals Ltd., with an anticipated closing date in the first half of 2024. The
Company has also signed an Option Agreement to sell the Maverick Springs project, an
advanced-stage exploratory property with an Inferred Resource of 3.71Moz AuEq (1.37Moz
Au and 175Moz Ag) and anticipates completing this sale on or before July 21, 2024.
In British Columbia, Element79 Gold has executed a Letter of Intent and funded a drilling
program to acquire a private company that holds the option to 100% interest of the Snowbird
High-Grade Gold Project, which consists of 10 mineral claims located in Central British
Columbia, approximately 20km west of Fort St. James.
Element79 Press Release
7 o7
The Company has an option to acquire a 100% interest in the Dale Property, 90 unpatented
mining claims located approximately 100 km southwest of Timmins, Ontario, and has recently
announced that it has transferred this project to its wholly-owned subsidiary, Synergy Metals
Corp, and is advancing through the Plan of Arrangement spin-out process.
The Company’s 2023 review and Corporate Update can be reviewed HERE
For more information about Element 79 Gold Corp., please visit www.element79.gold.
For corporate matters, please contact:
James C. Tworek, Chief Executive Officer
Email: [email protected]
For investor relations inquiries, please contact:
Investor Relations Department
Phone: +1 (403)850.8050
Email: [email protected]
Neither the Canadian Securities Exchange nor the Market Regulator (as that term is defined in
the policies of the Canadian Securities Exchange) accepts responsibility for the adequacy or
accuracy of this release.
Forward-Looking Statements
This press release may contain forward- looking statements within the meaning of applicable securities law.
Forward-looking statements are frequently characterized by words such as “plan”, “expect”, “project”, “intend”,
“believe”, “anticipate”, “estimate” and other similar words, or statements that certain events or conditions
“may” or “will” occur.
Although the Company believes that the expectations reflected in applicable forward- looking statements are
reasonable, there can be no assurance that such expectations will prove to be correct. Such forward- looking
statements are subject to risks and uncer tainties that may cause actual results, performance or developments
to differ materially from those contained in such statements.