Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

ELEF.TO ·

Silver Elephant: Gibellini Vanadium Project’s PEA Shows 25.4% After Tax IRR At $10/lb V2O5, Capex $147 million

Economic Studies

Silver Elephant: Gibellini Vanadium Project’s PEA Shows

25.4% After Tax IRR At $10/lb V2O5, Capex $147 million

Vancouver, British Columbia, August 30, 2021 –Silver Elephant Mining Corp. (“Silver

Elephant” or the “Company”) (TSX:ELEF, OTCQX:SILEF, Frankfurt:1P2N) is pleased to

announce the results of a preliminary economic assessment (the “2021 PEA”) for its Gibellini

vanadium project (“Gibellini project”) that demonstrates an after-tax internal rate of return

(“IRR”) of 25.4%, and after-tax cumulative cash flow of $260.8 million, assuming an average

vanadium pentoxide (V2O5) price of $10.00 per pound.

The Gibellini project is designed to be an open pit, heap leach operation in Nevada’s Battle

Mountain region (25 km south of Eureka) with initial capital cost of $1 47 million, average

annual production is 10.2 million pounds of V 2O5 , at an all-in sustaining cost of $6.04 per

pound with strip ratio of 0.18 to 1 (waste rock:leach material).

As of August 27, 2021, the European price of vanadium pentoxide (98%) was $9.60 per pound

according to www.asianmetal.com.

The 2021 PEA was prepared by Wood Group USA, Inc (Wood) and Mine Technical Services

Ltd. (MTS) . The technical report that summarizes the 2021 PEA will be filed under the

Company’s SEDAR profile and available within 45 days.

All dollar values are expressed in US dollars unless otherwise noted.

2021 PEA Highlights:

The 2021 PEA is preliminary in nature, and includes inferred mineral resources that are

considered too speculative geologically to have the economic considerations applied to them

that would enable them to be categorized as mineral reserves, and there is no certainty that

the PEA will be realized. Mineral resources are not mineral reserves and do not have

demonstrated economic viability.

Highlights of the 2021 PEA (after tax):

Internal rate of return 25.4%

Payback period 2.49 years

Life of mine 11.1 years

Total V2O5 recovered 114.6 million lbs

Average V2O5 selling price $10 per lb

Cash operating cost $4.70 per lb V2O5

All-in sustaining cost $6.04 per lb V2O5

Initial capital cost including 25% contingency $147 million

Average grade 0.271% V2O5

Strip ratio (waste:leach) 0.18:1

Mining operating rate 9,700 tons per day

Total material leached 33.4 million tons

Average V2O5 recovery through direct heap leaching 63.4%

Mineral Resources

The PEA Mineral Resource is based on Measured, Indicated and Inferred Mineral Resource

estimates for the Gibellini deposit and Inferred Mineral Resource estimate s for the Louie Hill

and Bisoni McKay deposits, totaling131.34 million pounds of contained V2O5 in the Measured

and Indicated categories, and 227.81 million pounds of contained V2O5 in the Inferred catetory.

Mineral Resource Statement, Gibellini

Confidence Category Domain Cut-off

V2O5 (%)

Tons

(kton)

Grade

V2O5 (%)

Contained

V2O5 (klb)

Measured

Oxide 0.101 3,960 0.251 19,870

Transition 0.086 3,980 0.377 29,980

Indicated

Oxide 0.101 7,830 0.222 34,760

Transition 0.086 7,190 0.325 46,730

Total Measured and Indicated 22,950 0.286 131,340

Inferred

Oxide 0.101 160 0.170 550

Transition 0.086 10 0.180 30

Reduced 0.116 14,800 0.175 51,720

Total Inferred 14,970 0.175 52,300

Notes:

1. The Qualified Person for the estimate is Mr. Todd Wakefield , RM SME of Mine Technical

Services Ltd. The Mineral Resources have an effective date of 5 June 2021 . The resource

model was prepared by Mr. E.J.C. Orbock III, RM SME.

2. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

3. Mineral Resources are reported at various cut -off grades for oxide, transition, and reduced

material.

4. Mineral Resources are reported within a conceptual pit shell that uses the following

assumptions: Mineral Resource V 2O5 price of $14.64/lb; mining cost: $2.21/st mined; process

cost: $13.62/st processed; general and administrative (G&A) cost: $0.99/st processed;

metallurgical recovery assumptions of 60% for oxide material, 70% for transition material and

52% for reduced material; tonnage factors of 16.86 ft3/st for oxide material, 16.35 ft 3/st for

transition material and 14.18 ft3/st for reduced material; royalty: 2.5% net smelter return (NSR);

shipping and conversion costs: $0.37/lb. An overall 40° pit slope angle assumption was used.

5. Rounding as required by reporting guidelines may result in apparent summation differences

between tons, grade and contained metal content. Tonnage and grade measurements are in

US units. Grades are reported in percentages.

Mineral Resource Statement, Louie Hill

Confidence Category Cut-off

V2O5 (%)

Tons

(kton)

Grade

V2O5 (%)

Contained

V2O5 (klb)

Inferred 0.101 7,520 0.276 41,490

Notes:

1. The Qualified Person for the estimate is Mr. Todd Wakefield , RM SME, of Mine Technical

Services Ltd. The Mineral Resources have an effective date of 5 June 2021 . The resource

model was prepared by Mr. Mark Hertel, RM SME.

2. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

3. Oxidation state was not modeled.

4. Mineral Resources are reported within a conceptual pit shell that uses the following

assumptions: Mineral Resource V 2O5 price of $14.64/lb; mining cost: $2.21/st mined; process

cost: $13.62/st processed; general and administrative (G&A) cost: $0.99/st processed;

metallurgical recovery assumptions of 60% for mineralized material; tonnage factors of 16.86

ft3/st for mineralized material; royalty: 2.5% net smelter return (NSR); shipping and conversion

costs: $0.37/lb. An overall 40° pit slope angle assumption was used.

5. Rounding as required by reporting guidelines may result in apparent summation differences

between tons, grade and contained metal content. Tonn age and grade measurements are in

US units. Grades are reported in percentages.

Mineral Resource Statement, Bisoni–McKay

Area Confidence

Category Domain Cut-off

V2O5 (%)

Tons

(kton)

Grade

V2O5 (%)

Contained

V2O5 (klb)

North Area A Inferred

Oxide 0.107 6,970 0.29 39,720

Transition 0.124 1,500 0.33 9,900

Reduced 0.139 9,080 0.39 70,580

Total North Area A Inferred All Variable 17,540 0.34 120,210

South Area B Inferred

Oxide 0.107 1,470 0.28 8,160

Transition 0.124 320 0.40 2,540

Reduced 0.139 510 0.30 3,100

Total South Area B Inferred All Variable 2,300 0.30 13,810

Total Inferred All Variable 19,850 0.34 134,020

Notes:

1. The Qualified Person for the estimate is Mr. Todd Wakefield , RM SME, of Mine Technical

Services Ltd. The Mineral Resources have an effective date of 5 June 2021.

2. Mineral Resources are reported at various cut -off grades for oxide, transition, and reduced

material.

3. Mineral Resources are reported within a conceptual pi t shell that uses the following

assumptions: Mineral Resource V 2O5 price of $11.50/lb; mining cost: $2.90/st mined; process

cost: $13.75/st; general and administrative (G&A) cost: $1.00/st processed; metallurgical

recovery assumptions of 65% for oxide mat erial, 56% for transition material and 50% for

reduced material; tonnage factors of 16.86 ft3/st for oxide material, 16.35 ft 3/st for transition

material and 14.18 ft3/st for reduced material; royalty: 2.5% net smelter return (NSR); shipping

and conversion costs: $0.625/lb. An overall 40° pit slope angle assumption was used.

4. Rounding as required by reporting guidelines may result in apparent summation differences

between tons, grade and contained metal content. Tonnage and grade measurements are in

US units. Grades are reported in percentages.

Mining & Processing

A subset of the Gibellini and Louie Hill Mineral Resource estimates were adopted in the 2021

PEA mine plan. Bisoni McKay Mineral Resource estimate was not included in the mine plan

in the 2021 PEA to better reflect the Company’s already submitted plan of operation in its

permitting efforts.

Subset of the Gibellini Mineral Resource Estimate within the 2021 PEA Mine Plan

Leach Material Domain Cutoff

V2O5 (%)

Tons

('000)

V2O5 Grade

(%)

Contained

V2O5 Lbs

('000)

Measured

Oxide 0.135 3,890 0.253 19,684

Transition 0.135 3,944 0.378 29,824

Reduced 0.135 - 0.000 -

Indicated

Oxide 0.135 6,246 0.240 30,024

Transition 0.135 7,056 0.316 44,624

Reduced 0.135 - 0.000 -

Total Measured and

Indicated 21,136 0.294 124,156

Inferred

Oxide 0.135 116 0.174 403

Transition 0.135 - 0.000 -

Reduced 0.135 5,183 0.163 16,919

Total Inferred 5,299 0.163 17,323

Subset of the Louie Hill Mineral Resource Estimate within the 2021 PEA Mine

Plan

Leach Material Domain Cut-off

(%)

Tonnage

(kton)

V2O5

(%)

V2O5

(klb)

Inferred

Oxide 0.155 6,963 0.282 39,315

Transition 0.155 — 0.000 -

Reduced 0.155 — 0.000 -

Total Inferred 6,963 0.282 39,315

Capital and operating costs for the 2021 PEA are based on suppl ying 3 Mt of crushed and

agglomerated leach material annually from two open pits at Gibellini and Louie Hill. Initial

mine development will be focused on Gibellini, with Louie Hill following nine years later.

Mining at the Gibellini and Louie Hill deposits is planned to be a conventional open pit mine

using a truck and loader fleet consisting of 100-ton trucks and front-end loaders. A power line

would be constructed from an existing transmission line and water will be leased from a private

ranch. Both water and power sources are within five miles of the planned mining operations.

The average annual mine production during the 11.1 year mine life will be 3.56 million tons of

leach material (3 Mst) and waste (0.56 Mst) at a strip ratio of 0.18 (w:l).

Period Total Rock

Waste

Oxide

Leach

Transition

Leach

Reduced

Leach

Leach

Total V2O5 Contained

V2O5

Produced

V2O5

(kt) (kt) (kt) (kt) (kt) (kt) (% V2O5) (mbls) (mbls)

YR1 3,002 2 2,573 424 2 3,000 0.298 17,877 10,915

YR2 3,072 72 2,025 974 1 3,000 0.320 19,221 12,297

YR3 3,117 117 766 2,185 50 3,000 0.401 24,059 16,293

YR4 3,096 96 2,423 577 0 3,000 0.227 13,602 8,638

YR5 3,081 81 1,096 1,862 42 3,000 0.281 16,881 11,252

YR6 3,011 11 395 2,158 447 3,000 0.292 17,519 11,824

YR7 5,943 2,943 641 1,817 542 3,000 0.224 13,447 8,926

YR8 4,232 1,232 308 960 1,732 3,000 0.178 10,657 6,409

YR9 3,203 203 591 44 2,365 3,000 0.187 11,214 6,121

YR10 3,067 67 3,000 0 0 3,000 0.364 21,857 12,999

YR11 4,191 1,191 3,000 0 0 3,000 0.218 13,057 7,922

YR12 518 121 397 0 0 397 0.177 1,405 870

YR13 101

Total 39,533 6,136 17,215 11,000 5,183 33,397 0.271 180,794 114,568

Mining will be completed using contract mining, with Silver Elephant’s mining staff overseeing

the contracted mining operation and performing the mine engineering and survey work.

The processing method envisioned will be to feed leach material from the mine via loade r to

a hopper that will feed a crushing plant. The leach material will be fed to the agglomerator

where sulfuric acid, flocculent and water will be added to achieve adequate agglomeration.

The agglomerated leach material will be transported to a stacker on the leach pad, which will

stack the material to a height of 15 feet. Once the material is stacked, solution will be added

to the leach heap at a rate of 0.0025 gallons per minute per square foot. The solution will be

collected in a pond and this pregnant leach solution (“PLS”) will be sent to the process building

for metal recovery. In the process building, the PLS will go through solvent extraction (“SX”)

and stripping processes to produce vanadium pentoxide.

Capital and Operating Costs

During the capital period, an initial leach pad having a capacity of 16.7 Mst will be constructed,

and will be followed by one expansion of approximately 16.7 Mst. The total initial capital cost

is estimated at approximately $147 million.

Project Capital Cost Estimate

Cost Description Total ($000s)

Open Pit Mine

Mobile equipment 122

On Site Infrastructure

Cost Description Total ($000s)

Site preparation 2,740

Roads 1,577

Water supply 2,263

Sanitary system 69

On-site electrical 2,325

Communications 187

Contact water ponds 186

Non-process facilities - buildings 8,594

Process Facilities

Material handling 21,730

Heap leach system 22,033

Process plant 24,167

Off-Site Infrastructure

Water system 5,095

Electrical supply system 3,657

First fills 975

Total Direct Cost 95,720

Construction indirect costs 5,355

Sales Tax/OH&P 5,333

EPCM 11,178

Contingency 29,396

Total Project Cost 146,982

Note: OH&P = overhead and profit, EPCM = engineering, procurement and construction management

Sustaining capital is estimated at $25.2 million.

Sustaining Capital Costs

Description Total ($000s)

Leach pad expansions 23,069

Haul road to Louie Hill 814

Storm water controls Louie Hill pit/waste rock facility/roads 386

Equipment annual allowance 971

Total Sustaining Capital 25,240

Operating costs are estimated to average $16.12 per ton leached, or $4.7/lb V2O5 recovered

Operating Costs

Total Cash Operating Cost $ per Ton Leached $ per lb of V2O5 Recovered

G&A 0.97 0.28

Mining Cost 3.36 0.98

Total Processing Cost 11.79 3.44

Total 16.12 4.70

The cash operating costs in the first half of the Gibellini project covering years 1 –7 is $4.20

per lb of V 2O5 produced and for years 8 –12 is $5.87 per lb of V 2O5 produced, resulting in a

weighted average cash cost of $4.70 per lb of V 2O5 produced and all -in sustaining cost of

$6.04/lb. The cash operating cost is lower in the first half of the Gibellini project due to

processing of higher-grade material.

Vanadium Recoveries and Metallurgical Testing

Approximately 114.6 million pounds of V2O5 is expected to be produced from the Gibellini and

Louie Hill leaching operations at an average recovery of 6 3.4% (oxide: 60%, transition: 70%

and reduced: 52%). The heap leaching will be performed at ambient temperature and

atmospheric pressure without pre -roasting or other beneficiation process. The PLS will be

continuously collected with leach material undergoing, on average, a 150 day heap-leaching

cycle.

The direct heap leach vanadium recovery estimates used in the 2021 PEA were based on

extensive metallurgical test work performed by SGS Lakefield Research Laboratories,

Dawson Minerals Laboratories, and McClelland Laboratories. Samples were selected from a

range of depths within the Gibellini deposit, and are considered t o be representative of the

various types and styles of mineralization within that deposit . Samples were obtained to

ensure that tests were performed on sufficient sample mass. The end results demonstrated

low acid consumption (less than 100 lb acid consumption per ton leached) and high recovery

through direct leaching.

Solvent extraction processing was conducted to recover vanadium from sulfuric acid PLS

generated during pilot column testing on bulk leach samples from the Gibellini project.

Laboratory-scale testing was conducted on select solutions generated during the pilot SX

processing, to optimize the SX processing conditions. Additional laboratory scale testing was

successfully conducted on the loaded strip solution to purify, precipitate and extract final

marketable vanadium-bearing products.

Sensitivity Analysis

The tables below show the sensitivity analysis to the vanadium pentoxide price, grade, and to

the PEA capital cost and operating costs . A sensitivity analysis to vanadium price indicates

strong project economics even in very challenging conditions, and that the Gibellini project is

well positioned to benefit from the current rising vanadium price environment. A 30% increase

in the vanadium price to $13/lb V2O5 relative to the b ase case translates to a 42% IRR and

$295.4 million after-tax net present value at a 7% discount rate.

Sensitivity Analysis to Changes Vanadium Price

V2O5 Price Change V2O5 Price After-tax IRR After-tax NPV After-tax Cashflow

(%) (US$/lb) (%) (US$ M @ 7%) (US$ M)

45 14.50 49% 377.0 671.5

30 13.00 42% 295.4 536.8

15 11.50 34% 212.3 399.7

Base Case 10.00 25% 127.9 260.8

-15 8.50 14% 42.1 122.3

-30 7.00 0% (55.8) (38.9)

-45 5.50 0 (155.1) (202.0)

Sensitivity Analysis to Changes in Vanadium Grades

Grade Change After-tax IRR After-tax NPV After-tax Cashflow

(%) (%) (US$ M @ 7%) (US$ M)

45 48% 363.8 649.7

30 41% 286.6 522.2

15 34% 207.7 392.2

Base Case 25% 127.9 260.8

-15 15% 46.9 130.0

-30 0% (45.2) (21.4)

-45 0 (139.0) (175.5)

Sensitivity Analysis to Changes in Capital Cost Estimates

CAPX Change After-tax IRR After-tax NPV After-tax Cashflow

(%) (%) (US$ M @ 7%) (US$ M)

45 14% 69.2 197.5

30 17% 89.2 218.6

15 21% 108.6 239.7

Base Case 25% 127.9 260.8

-15 31% 146.9 281.9

-30 38% 165.8 303.0

-45 0 184.7 324.1

Sensitivity Analysis to Changes in Operating Cost Estimates OPEX

Change After-tax IRR After-tax NPV After-tax Cashflow

(%) (%) (US$ M @ 7%) (US$ M)

45 8% 3.6 50.6