Prophecy’s Upcoming Drill Program to Increase Current Resources of Gibellini Vanadium Project in Nevada with Wood (AMEC)

Exploration Programs

Prophecy’s Upcoming Drill Program to Increase Current

Resources of Gibellini Vanadium Project in Nevada with

Wood (AMEC)

Vancouver, British Columbia, February 14, 2019 – Prophecy Development Corp.

(“Prophecy” or the “ Company”) ( TSX:PCY, OTCQX:PRPCF, Frankfurt:1P2N)

announces that it has retained Amec Foster Wheeler E&C Services Inc. (Wood) to

undertake updating of the mineral resource and mining section for the Company’s

upcoming Feasibility Study (“ FS”) to be completed to the st andards of National

Instrument 43 -101 (“ NI 43 -101”) for its Gibellini vanadium project located in Nevada,

USA. The FS is anticipated to be completed by year end 2019.

Vanadium is a product classified as a strategic metal by the US Government and is

primarily used for strengthening structural steel, but is also used in the aerospace

industry for Ti-Al alloys. More recently, there has been an increase in demand to supply

the new era of redox flow batteries for long-term energy storage, which has long been a

challenge for the renewable energy sector.

Gibellini is the most advanced primary vanadium deposit in the United States, with a

contained NI 43 -101 compliant combined measured and indicated resource of 22.95

million tons at 0.286% V2O5 (technical re port filed on SEDAR titled “Gibellini

Vanadium Project, Eureka County, Nevada, NI 43 -101 Technical Report on Preliminary

Economic Assessment” effective May 29, 2018). The drilling program is expected to

start following approval from the Bureau of Land Mana gement (BLM), and will include

up to 10 holes drilled 150 to 250 feet long in the higher -grade portions of the Gibellini

deposit. It is hoped that by characterizing this mineralization with greater confidence ,

the Company can quantify more value for the project overall.

The remaining drill holes will focus on the Louie Hill deposit. There is strong indication

from historical drilling that the Louie Hill deposit can be a high -value vanadium asset.

However, much of this historical drilling could not be veri fied as archive drill samples

were not available and thus , could not be used in the verification of the database

supporting the resource estimation. Only the 9 holes that were drilled more recently

were used in the Louie Hill Mineral Resource estimate that was reported in May 2018.

The Company is confident that the 2019 drilling described herein could result in a

significant addition of measured and indicated vanadium -bearing material to the project

and add to the Gibellini project’s overall value and antic ipated mine life. These drill

holes will also be used for geochemical characterization of the deposit in support of

future permitting.

This FS work will include optimized pit designs, mine plan layouts and the production

schedule for an anticipated annual production of approximately 2.5 to 3.0 million tons

per year, as well as a full accounting of the capital and operating costs, including mining

equipment. It will incorporate the results of the Company’s current EPCM work being

conducted by M3 that will i nclude detailed engineering and equipment specifications.

This refined level of information is intended to facilitate a bankable -level Feasibility

Study by year end 2019 that is expected to facilitate project financing going into 2020.

The project permitting has been fully integrated into the study to ensure that the project

design also reduces environmental impact and ensures full compliance with all

regulatory requirements.

Qualified Persons

Kirk Hanson, Wood’s nominated mining Qualified Person (QP) is independent of

Prophecy, and has reviewed the information regarding Wood’s involvement in the

Gibellini Feasibility Study.

Additional technical contents of this news release have been prepared under the

supervision of Danniel Oosterman, VP, Exploration of Prophecy. Mr. Oosterman is not

independent of the Company in that he is an employee of the Company and most of his

income is derived from the Company. Mr. Oosterman is a Qualified Person as defined

in NI 43-101.

About Wood

The John Wood Group PLC is a global leader in the delivery of project, engineering and

technical services to energy and industrial markets. Wood Group operates in more than

60 countries, employing around 55,000 people, with revenues of over $10 billion.

About Prophecy

Prophecy is developing the Gibellini project – the only large-scale, open-pit, heap-leach

vanadium project of its kind in North America. Located in Eureka County, Nevada,

Gibellini has the largest primary vanadium Measured and Indicated Mineral Resource

known in the USA and is currently undergoing EPCM and permit development. Further

information on Prophecy can be found at www.prophecydev.com.

PROPHECY DEVELOPMENT CORP.

ON BEHALF OF THE BOARD

“Gerald Panneton”

President and CEO

For more information about Prophecy, please contact Investor Relations:

+1.888.513.6286

[email protected]

www.prophecydev.com

Neither the Toronto Stock Exchange nor its Regulation Services Provider (as that term

is defined in the policies of the Toronto Stock Exchange) accepts responsibility for the

adequacy or accuracy of this release.

Cautionary Note Regarding Forward-Looking Statements

Certain statements contained in this news release, including statements which may

contain words such as “expects”, “anticipates”, “intends”, “plans”, “believes”,

“estimates”, or simi lar expressions, and statements related to matters which are not

historical facts, are forward -looking information within the meaning of applicable

securities laws. Such forward -looking statements, which reflect management’s

expectations regarding Prophecy ’s future growth, results of operations, performance,

business prospects and opportunities, are based on certain factors and assumptions

and involve known and unknown risks and uncertainties which may cause the actual

results, performance, or achievements to be materially different from future results,

performance, or achievements expressed or implied by such forward -looking

statements.

These factors should be considered carefully, and readers should not place undue

reliance on the Prophecy’s forward -looking statements. Prophecy believes that the

expectations reflected in the forward -looking statements contained in this news release

and the documents incorporated by reference herein are reasonable, but no assurance

can be given that these expectations will p rove to be correct. In addition, although

Prophecy has attempted to identify important factors that could cause actual actions,

events or results to differ materially from those described in forward looking statements,

there may be other factors that cause actions, events or results not to be as anticipated,

estimated or intended. Prophecy undertakes no obligation to release publicly any future

revisions to forward-looking statements to reflect events or circumstances after the date

of this news or to refle ct the occurrence of unanticipated events, except as expressly

required by law.