Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

ELD.TO ·

Eldorado Announces Preliminary 2016 Operational Results and 2017 Guidance

Corporate Updates

Throughout this press release we use cash operating cost per ounce and all -in sustaining cost per ounce as additional measures of Company performance. These are

non IFRS measures. Please re fer to the non IFRS measurements in our Third Quarter 2016 MD&A for an explanation and discussion of these non IFRS measures. All

dollar amounts in US$ unless stated otherwise.

1

NEWS RELEASE

TSX: ELD NYSE: EGO January 6, 2017

Eldorado Announces Preliminary 2016 Operational Results and 2017 Guidance

VANCOUVER, BC – Eldorado Gold Corporation, ( “Eldorado” or “the Company”) today announce s the

Company’s 201 6 operating results and preliminary cash costs, and provide s production and cash cost

guidance for 2017.

2016 Highlights

 Gold production of 48 5,994 ounces (including production from discontinued Chinese operations and

tailings retreatment); slightly lower than the revised third quarter guidance of 495,000 ounces.

 2016 cash operating costs averaged $578 per ounce; considerably lower than original 2016 guidance

of $585-620 per ounce.

 All in sustaining costs expected to be approximately $ 915 per ounce; also considerably lower than

original 2016 guidance of all in sustaining costs of $940-980 per ounce.

 Closed the year with total liquidity of approximately $1.1 billion, including $880 million in cash, cash

equivalents and term deposits, and $250 million in undrawn lines of credit.

 Completed sale of Chinese assets, which included: White Mountain and Tanjianshan Mines and Eastern

Dragon Development Project to an affiliate of Yintai Resources Co. Ltd, and the Jinfeng Mine to a wholly-

owned subsidiary of China National Gold Group Corporation.

 Olympias Phase II is set for commissioning in the first quarter 2017.

 Construction at Skouries continues on track for 2019 start-up .

 Continued improvement to the overall safety record with a reduction in the lost time injury rate for

the fifth consecutive year.

 Announced the planned retirement of President and Chief Executive Officer Paul Wright and named

George Burns as his successor, in addition to changes to the Board of Directors.

“I am very pleased to report the close of a successful 2016 , a transitional year for Eldorado. With the sale

of the Chinese assets now complete, our development projects in Greece progressing on schedule, and a

capital plan that now reflects the lower gold price envi ronment, I am confident that the next three years

will be transformational for the Company .” said Paul Wright, President and Chief Executive Officer. “Our

teams continue to operate to the highest international safety standards, and I would like to take this

opportunity to thank them for their hard work and diligence in this core area.”

“In response to our current gold price outlook and our priority development projects in Greece, we have

decided to reconfigure the mine plan at Kışladağ, eliminating the remaining capital expenditure associated

with the expansion and greatly reducing sustaining capital requirements over the next five years. The

revised operating plan greatly enhances free cash flow from the operation in the near and medium-term

while maintaining long-term operating integrity.”

2

2016 Operating Results Highlights (including discontinued operations)

Q4 2016 YE 2016

Total

Realized gold price ($/oz) 1,213 1,254

Gold sold (oz) 105,021 483,460

Gold produced (oz) 1,2 103,113 485,994

Cash operating cost ($/oz) 3,5 525 578

Total cash cost ($/oz) 4 549 620

Kisladag Mine

Gold sold (oz) 59,416 211,284

Gold produced (oz) 59,591 211,161

Tonnes to pad 3,918,426 16,566,763

Grade (g/t) 0.74 0.80

Cash operating cost ($/oz) 3,5 449 472

Total cash cost ($/oz) 4 457 486

Efemcukuru Mine

Gold sold (oz) 25,265 99,743

Gold produced (oz) 23,182 98,333

Tonnes milled 120,347 473,060

Grade (g/t) 6.62 7.21

Cash operating cost ($/oz) 3,5 505 512

Total cash cost ($/oz) 4 516 529

Jinfeng Mine 6

Gold sold (oz) - 66,902

Gold produced (oz) - 68,195

Tonnes milled - 766,697

Grade (g/t) - 3.32

Cash operating cost ($/oz) 3,5 - 705

Total cash cost ($/oz) 4 791

Tanjianshan Mine 7

Gold sold (oz) 10,912 49,266

Gold produced (oz) 10,912 49,266

Tonnes milled 121,237 869,964

Grade (g/t) 1.70 1.90

Cash operating cost ($/oz) 3,5 785 819

Total cash cost ($/oz) 4 892 970

White Mountain Mine7

Gold sold (oz) 9,428 56,265

Gold produced (oz) 9,428 56,265

Tonnes milled 95,278 717,145

Grade (g/t) 2.99 2.78

Cash operating cost ($/oz) 3,5 759 731

Total cash cost ($/oz) 4 813 773

3

2016 Operating Results Highlights Continued

Q4 2016 YE 2016

Olympias Mine

Gold sold (oz) - -

Gold produced (oz) 2 - 2,774

Tonnes milled - 87,350

Grade (g/t) - 2.47

Cash operating cost ($/oz) 3,5 - -

Total cash cost ($/oz) 4 -

1 Gold production includes both continuing and discontinued operations.

2 Ounces produced include production from tailings retreatment at Olympias.

3 Cost figures calculated in accordance with the Gold Institute Standard.

4 Cash operating costs, plus royalties and the cost of off-site administration.

5 Cash operating costs and total cash costs are non-IFRS measures. Please see our Q3 MD&A for an explanation and discussion of these.

6 Figures shown for YE 2016 reflect the sale of Jinfeng on September 6, 2016.

7 Figures shown for Q4 and YE 2016 reflect the sale of Tanjianshan and White Mountain on November 22, 2016.

2017 Guidance

 Expected gold production of 365 ,000-400,000 ounces, in addition to substantial by-product credits

from Olympias Phase II production.

 2017 all-in sustaining cash costs expected to remain low at $845-875 per ounce; and cash operating

costs expected to decline significantly, averaging $485-535 per ounce.

 Expected capital expenditures of $425 million; considerably lower than the September 2016 guidance.

Reductions were primarily at Skouries due to flexibility in the capital deployment timeline, along with

anticipated cost savings, and at Tocantinzinho in response to the current gold price environment and

permitting delays.

Mine/Project Production

(Au oz)

Cash Costs

($/oz)

Sustaining Capital

Expenditure ($M)

Kisladag 230,000 - 245,000 500-550 45

Efemcukuru 95,000 - 105,000 525-575 25

Olympias 40,000 - 50,0001 250-4502 30

Total 365,000-400,000 485-535 100

1 Includes pre-commercial production of ~10k oz.

2 Range due to variability of by-product credits; commercial ounces only.

4

2017 Capital Expenditure

Principal assumptions used in the preparation of guidance for 2017 include:

Gold price: $1,150/oz Lead price: $2,250/t CAD vs USD 1.30 USD vs EUR 1.10

Silver price: $20/oz Zinc price: $2,500/t REAL vs USD 3.50 TRL vs USD 3.40

2017 Financial Outlook

The Company’s balance sheet remains one of the strongest in its peer group, with approximately $880

million in cash, cash equivalents and term deposits and $250 million in undrawn credit lines. Sustaining

capital for gold mining operations in 201 7 is e stimated to be approximately $100 million. Planned

expenditures for mining development total $315 million. Exploration expenditures in 2017 are budgeted at

$35 million (65% expensed and 35% capitalized), with a balanced focus on resource delineation and

brownfield drilling at existing operations, testing known structures, and project generation.

Depreciation, depletion and amortization expense is expected to be approximately $300 per ounce of gold

sold, subject to the Company completing its year end 201 6 reserve and resource calculation. General and

administrative expense is expected to be approximately $45 million.

Gold Operations Review and Future Outlook

TURKEY

Kisladag

In 2016 the original production budget for Kisladag was estimated between 225,000-240,000 ounces of gold

at cash costs of $550-600 per ounce. Total production of 211,161 ounces was due to slower than expected

leach rates from certain ore types mined earlier in the year. While gold production improved in the final

quarter to 59,416 ounces, inventory levels over the year increased by 37,000 ounces. A reduction of over

6,000 ounces occurred during the fourth quarter due to the installation of new leach trains. The average

ore grade placed on the leach pad during the year was 0.80 grams per tonne gold and the average cash

operating cost was $472 per ounce.

In 2017, Kisladag is expected to place 13.1 million tonnes of ore on the leach pad at a grade of 0. 94 grams

per tonne gold. It is anticipated that with a continued increase in gold grade to 0.94 grams per tonne, the

inventory levels are expected to remain constant year over year. Mining in the pit throughout 2017 will

return to areas with expected higher metallurgical recoveries. Projected cash costs of $500-550 per ounce

Development Capital ($M) Total Capital ($M)

Tocantinzinho 35 Total Development 315

Olympias 55 Total Capitalized Exploration 10

Skouries (170 – 200) 185 Total Sustaining 100

Stratoni 20 Total 425

Certej 20

Total 315

5

are based on minimal tonnes of run of mine material being treated in 201 7, in combination with reduced

waste mining requirements under the new mine plan. Sustaining capital expenditures for the year are

estimated to be $45.0 million, similar to the 2016 actual spend of $41.5 million.

Due to its long-term outlook for gold, the Company has reconfigured the pit design and decided to

indefinitely defer the completion of the Kişladağ expansion; eliminating the considerable sustaining capital

that would have been required. Production is expected to average 285,000 ounces during 2018 and 2019.

Efemcukuru

During 2016 Efemcukuru met its original production guidance of 90,000-100,000 ounces of gold with cash

costs between $550 -600 per ounce, finish ing the year with 98,333 ounces of gold produced at cash

operating costs of $512 per ounce.

In 2017, Efemcukuru is expected to mine and process over 450,000 tonnes of ore at an average grade of 7.3

grams per tonne gold, producing between 95,000-105,000 ounces of gold, at operating costs between $525-

575 per ounce . Sustaining capital expenditures for 201 7 are approximately $ 25.0 million (2016: $23.3

million), spent primarily on underground mine development , waste handling and tailings facilities

construction.

GREECE

Olympias

Olympias Phase II continues as per schedule, with commissioning of the process plant expected in the first

quarter 2017. Total capital spending for 2017 of $85.0 million includes completion of the Phase II plant,

general sustaining capital expenditures, and capital associated with advancement to Phase III including the

continued construction of the Kokkinolakas tailings facility along with underground development and water

management.

Skouries

Capital expenditures at Skouries for 2017 are expected to be between $170.0 and $200.0 million, lower

than September 2016 guidance mainly due to the flexibility in the capital plan in combination w ith cost

initiatives that are underway. Funds will be used to continue the construction of the process plant and the

integrated waste management facility. Development of the decline is continuing, which will allow for

extraction of material from the underground soon after the open pit start- up – currently scheduled for

2019.

Stratoni

During 2017, Stratoni is expected to process 200,000 tonnes of ore at grades of 6. 0% lead, 9.7% zinc and

155 grams per tonne silver. Capital costs for the year are expected to total $20.0 million, which includes

underground equipment rebuilds and replacement, and underground development.

6

ROMANIA

Certej

The Company’s plans for Certej are progressing on schedule. The Company will spend approximately $20.0

million in capital during 2017 with a focus on continuing infrastructure projects, advancing permitting and

support engineering as defined in the 2015 Fe asibility Study. Permitting required includes an amendment

to the EIA to allow for improvements to the metallurgical process; converting the current Albion process to

pressure oxidation.

BRAZIL

Tocantinzinho

Consideration of a decision to commence construction at Tocantinzinho has been deferred until all permits

are in place, and in the context of gold price outlook at that time and the progress of other priority

development projects in the Company. Compared to previous September 2016 guidance of $95.0 to $105.0

million in capital expenditures for 2017, the Company now expects to spend $35.0 million in capital during

2017. The focus will be primarily on completing construction of the access road to site, permitting, basic

engineering and general site costs.

2016 Fourth Quarter and Year End Financials Announcement

The 2016 Fourth Quarter and Year End Financials will be released after the market closes on February 23,

2017. A conference call to discuss the details will be held by senior management on February 24, 2017 at

8:30 AM PT ( 11:30 AM ET). The call will be webcast and can be accessed at Eldorado Gold’s website:

www.eldoradogold.com

Conference Call Details Replay (available until March 10, 2017)

Date: Friday February 24, 2016 Toronto: 416 849 0833

Time: 8:30 am PT (11:30 am ET) Toll Free: 855 859 2056

Dial in: 647 427 7450 Pass code: 4916 2097

Toll free: 888 231 8191

Certain of the statements made herein may contain forward- looking statements or information within the meaning of the United States Private

Securities Litigation Reform Act of 1995 and applicable Canadian securities laws. Often, but not always, forward- looking statements and forward-

looking information can be identified by the use of words such as “plans”, “expects”, “is expected”, “budget”, “scheduled”, “estimates”, “forecasts”,

“intends”, “anticipates”, or “believes” or the negatives thereof or variations of such words and phrases or statements that certain actions, events or

results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. Forward-looking statements or information herein include, but are

not limited, to statements or information with respect to the Company’s Preliminary 2016 Operational Results and 2017 Guidance.

Forward-looking statements and forward- looking information by their nature are based on assumptions and involve known and unknown risks,

uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from

any future results, performance or achievements expressed or implied by such forward- looking statements or information. We have made certain

assumptions about the forward-looking statements and information, including the ability to acquire Shares in the market through the NCIB and in

compliance with regulatory requirements, the political and economic environment that we operate in, the future price of commodities, anticipated

costs and expenses and the impact of the disposition on the Company’s business. Although our management believes that the ass umptions made

and the expectations represented by such statements or information are reasonable, there can be no assurance that the forward-looking statements

or information will prove to be accurate. Furthermore, should one or more of the risks, uncertainties or other factors materialize, or should underlying

assumptions prove incorrect, actual results may vary materially from those described in forward- looking statements or information. These risks,

uncertainties and other factors include, among others, the following: the ability to acquire shares through the NCIB; politic al, economic,

environmental and permitting risks, regulatory restrictions, gold price volatility, discrepancies between actual and estimated production, estimated

7

mineral reserves and resources and metallurgical recoveries; mining operational and development risks, litigation risks, regulatory restrictions,

including environmental and permitting regulatory restrictions and liabilities, internal and external approval risks, risks of sovereign investment, and

impact of the completion of the sale of our interests in the Jinfeng, Tanjianshan and White Mountain Mines and the Eastern Dragon Development

Project on the Company; assumptions about the completion of post-closing conditions of the China National Gold and Yintai Transactions, including

liability and timing of meeting the closing conditions; changes in the use of proceeds; currency fluctuations; speculative nature of gold exploration,

global economic climate; dilution, share price volatility; competition, loss of key employees, additional funding requirement s, and defective title to

mineral claims or property, as well as those factors discussed in the sections entitled “Forward- Looking Statements” and "Risk Factors" in the

Company's Annual Information Form & Form 40-F dated March 30, 2016.

There can be no assurance that forward-looking statements or information will prove to be accurate, as actual results and future events could differ

materially from those anticipated in such statements. Accordingly, you should not place undue reliance on the forward- looking statements or

information contained herein. Except as required by law, we do not expect to update forward- looking statements and information continually as

conditions change and you are referred to the full discussion of the Company's business contained in the Company's reports filed with the securities

regulatory authorities in Canada and the U.S.

All forward looking statements and information contained in this News Release are qualified by this cautionary statement.

About Eldorado Gold

Eldorado is a leading low cost gold producer with mining, development and exploration operations in

Turkey, Greece, Romania, Serbia and Brazil. The Company’s success to date is based on a low cost strategy,

a highly skilled and dedicated workforce, safe and responsible operations, and long-term partnerships with

the communities where it operates. Eldorado’s common shares trade on the Toronto Stock Exchange (TSX:

ELD) and the New York Stock Exchange (NYSE: EGO).

Contact

Krista Muhr

Vice President Investor Relations and Corporate Communications

Eldorado Gold Corporation

604.601.6701 or 1.888.353.8166

[email protected]