Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

ELD.TO ·

Eldorado Gold Reports Q2 2024 Financial and Operational Results; Maintains 2024 Operating Guidance

Production Results Financials

NEWS RELEASE

TSX: ELD NYSE: EGO July 25, 2024

Eldorado Gold Reports Q2 2024 Financial and Operational Results;

Maintains 2024 Operating Guidance

VANCOUVER, BC - Eldorado Gold Corporation (“Eldorado” or “the Company”) today reports the Company’s

financial and operational results for the second quarter of 2024. For further information, please see the Company’s

Consolidated Financial Statements and Management’s Discussion and Analysis ("MD&A") filed on SEDAR+ at

www.sedarplus.com under the Company’s profile.

Second Quarter 2024 Highlights

Operations

• Gold production: 122,319 ounces in line with expectations for the quarter. Production increased 12% from

Q2 2023, reflecting increased gold production of 22% at Lamaque and 14% at Kisladag. Production was

slightly offset by lower production at Olympias as a result of intermittent work stoppages during ongoing

negotiations for a new Collective Bargaining Agreement ("CBA").

• Gold sales : 121,226 ounces at an average realized gold price per ounce sold 1 of $2,336. Gold sales

increased 10% from Q2 2023 primarily as a result of increased production at Lamaque and Kisladag.

• Production costs: $127.8 million in Q2 2024, compared to $116.1 million in Q2 2023. The increase was

due primarily to higher sales volumes, as well as slightly higher cash costs, the latter impacted by higher

royalty expense due to higher gold sales and higher gold price, as well as increases in contractor and

labour costs and higher fuel prices.

• Total cash costs 1: $940 per ounce gold sold compared to $928 per ounce gold sold in Q2 2023, with the

increases primarily due to higher royalties driven by higher gold prices and higher mining costs as well as

lower by-product credits.

• All-in sustaining costs ("AISC")1: $1,331 per ounce sold compared to $1,296 per ounce sold in Q2 2023,

with the increase due to higher total cash costs combined with higher sustaining capital.

• Total capital expenditures: $165.7 million, including $91.9 million of growth capital 1 invested at Skouries,

with activity focused on major earthworks and infrastructure construction. Growth capital at the operating

mines totalled $42.3 million and was primarily related to Kisladag for continued waste stripping, construction

of the North Heap Leach Pad and related infrastructure.

• Production and cost outlook : The Company is maintaining its 2024 annual production guidance of

505,000 to 555,000 ounces of gold. Production continues to be weighted to the second half of the year.

Total cash costs1 for the full year are expected to be between $840 to $940 per ounce sold and an average

AISC1 of $1,190 to $1,290 per ounce sold.

Financial

• Revenue: $297.1 million in Q2 2024, an increase of 30% from $229.0 million in Q2 2023, primarily due to

the higher averaged realized gold price and higher sales volumes.

• Net cash generated from operating activities from continuing operations: $112.2 million compared to

$75.3 million in Q2 2023, primarily due to higher revenue, partially offset by higher income taxes paid.

1

1 These financial measures or ratios are non-IFRS financial measures or ratios. Certain additional disclosure for non-IFRS financial measures

and ratios have been incorporated by reference and additional detail can be found at the end of this press release and in the section 'Non-IFRS

and Other Financial Measures and Ratios' in the Company's June 30, 2024 MD&A.

• Cash flow from operating activities before changes in working capital 2: $132.2 million compared to

$82.4 million in Q2 2023, primarily due to higher revenue, partially offset by higher income taxes paid.

• Cash, cash equivalents and term deposits: $595.1 million, as at June 30, 2024 as compared to $514.7

million as at March 31, 2024, with the cash increase attributable to strong operating cashflows combined

with the planned Skouries Term Facility drawdown, partially offset by the significant investing activities,

particularly at Skouries.

• Net earnings attributable to shareholders from continuing operations: $56.4 million , or $0.28 per

share, compared to $1.5 million or $0.01 per share in Q2 2023, with the increase driven by higher revenue.

• Adjusted net earnings before interest, taxes, depreciation and amortization ("Adjusted EBITDA") 2:

$155.3 million compared to $106.8 million in Q2 2023, with the increase driven by higher revenue, partially

offset by the unrealized derivative losses as well as a lower foreign exchange gain.

• Adjusted net earnings 2: $66.6 million or $0.33 per share compared to $9.7 million or $0.05 per share in

Q2 2023. Adjustments in Q2 2024 include a $1.9 million gain on foreign exchange due to the translation of

deferred tax balances net of Turkiye inflation accounting and a $12.0 million unrealized loss on derivative

instruments.

• Free cash flow 2: Negative $32.0 million in Q2 2024 compared to negative $21.7 million in Q2 2023, with

the decrease driven by continued investment activities at Skouries, partially offset by higher operating cash

flow, primarily due to the higher average realized gold price and higher sales volumes.

• Free cash flow excluding Skouries2: $33.9 million in Q2 2024 compared to $13.7 million in Q2 2023, with

the increase driven by higher operating cash flow, primarily due to the higher average realized gold price

and higher sales volumes.

• Project Facility: Drawdowns on the Skouries Term Facility during Q2 2024 totalled €104.0 million and year

to date as at June 30, 2024 totalled €118.1 million.

Corporate

“Operationally, the second quarter was aligned with guidance, driven by higher grades at Kisladag, Lamaque and

Efemcukuru,” said George Burns, President and Chief Executive Officer. “At Olympias, as negotiations on a new

CBA progressed during the quarter, we experienced intermittent labour-initiated work stoppages, which had a small

impact on consolidated production. We remain confident we will come to a mutually beneficial agreement between

the Company and the union workforce, demonstrating our commitment to mutual respect and collaboration to

support Olympias becoming a long-term profitable business.”

“With production totaling 239,430 ounces through the first half of the year and unit costs expected to decrease over

the second half of the year, we remain on track to achieve 2024 guidance. Our continued focus on operational

efficiencies and productivity position us for stronger production and improved unit costs during the second half of

2024. In addition, we remain on budget and on track for first production at Skouries in the third quarter of 2025.”

“We published our Annual Sustainability Report which highlighted our continued focus on our commitment to

sustainability across our global sites. In addition, our teams in Turkiye completed external verification against the

Mining Association of Canada’s ‘Towards Sustainable Mining’ protocols, receiving very positive scores. More

specifically, at Efemcukuru, the site received AAA scores, signifying excellence and leadership, in Tailings, Health &

Safety, Biodiversity, and Indigenous and Community Relationships, and A, AA or AAA scores across all other

indicators. At Kisladag, the site received AAA scores in all Health & Safety protocol indicators, and A, AA, or AAA

scores across all other indicators. TSM scoring is a range from C through AAA with A indicating 'Good Practice' and

AAA indicating 'Excellence and Leadership' in practices. This completes our first round of TSM compliance

verifications across all Eldorado operations, which started with the Lamaque Complex in 2022 and the Kassandra

Mines in Greece completed in 2023. Notably, Eldorado scored AAA, the highest possible score, for Tailings

management across all of our global operations with tailings facilities.”

2

2 These financial measures or ratios are non-IFRS financial measures or ratios. Certain additional disclosure for non-IFRS financial measures

and ratios have been incorporated by reference and additional detail can be found at the end of this press release and in the section 'Non-IFRS

and Other Financial Measures and Ratios' in the Company's June 30, 2024 MD&A.

Skouries Highlights

Growth capital invested totalled $91.9 million in Q2 2024 and $144.4 million during the six months ended June 30,

2024. At June 30, 2024, the growth capital invested towards the overall capital estimate of $920 million totalled $329

million.

In 2024, the capital spend is expected to be between $375 and $425 million, with a higher expected spend in the

second half of the year as contractor mobilization continues to ramp up and multiple work fronts open up.

As at June 30, 2024:

• The current Phase 2 of the project was 49% complete and the entire project was 76% complete, when

including the first phase of construction;

• Detailed engineering, since project restart, was 72% complete and procurement was substantially complete;

• Project execution and ramp-up continued for major earthworks with work progressing on water

management ponds, and top soil stripping and underdrain construction in the low-grade ore stockpile basin.

In addition, the coffer dam spillway construction has commenced;

• Work continues to advance on the tailings filtration infrastructure. The earthworks and KT2 channel

construction are substantially complete, the piling for the filter plant building is over 95% complete and the

piling for the tank farm area is 37% complete;

• Progress advanced on the foundation construction of the primary crusher, as planned, with the upper

retaining walls now completed and the concrete slab for the base of the crusher building expected to be

poured in Q3 2024;

• Construction of several non-process plant buildings commenced during Q2 2024, and relining of flotation

cells are 50% complete;

• Placement of concrete has increased from 445m3/month in Q1 2024 to 2,469m3/month in Q2 2024. The first

thickener base concrete pour was completed on July 13, 2024;

• Awarded the underground development and test stoping contract; and

• As previously noted, the upgrade of the underground power supply to 690V and the ventilation upgrade are

both completed.

On-track with milestones in 2024, which include:

Procurement and Engineering

• Substantial completion of procurement and engineering

Process Plant

• Construction of the control room and electrical room building - commenced in Q1 2024

• Construction of the tailings thickeners - commenced in Q1 2024

Tailings Filter Facility

• Awarding of the filter facility construction contract

• Preassembly of the filter press plates and frames - commenced in Q1 2024

• Completion of the structural steel

Integrated Extractive Waste Management Facility ("IEWMF")

• Completion of the coffer dam

Underground

• Awarding of the underground development and test stoping contract - completed in Q2 2024

• Completion of approximately 2,200 metres of underground development

Construction Progress

Work continues to ramp up on construction of major earthworks structures including the haul roads, water

management ponds, low-grade stockpile, primary crusher, process facilities, filter building and the IEWMF.

Productivity improvement initiatives by the earthworks contractor, including adding a partial second shift, has yielded

significant improvements. Work is also progressing on the underground development to support test stope mining in

2025.

3

On the critical path is the filter plant building which continues to advance, wi th 871 piles required for the filter plant

building and supporting infrastructure . To date, 270 piles have been completed, including 95% of the piles for the

filter plant building. There are currently two active drills with a third drill having recently arrived on site. In July 2024,

preparation work for the concrete foundations on the filter plant building have commenced, with assembly of the

building structure to commence in Q3 2024 following the awarding of the filter plant construction contract. The

contract will include the building structure, assembly of equipment within the building, including air compressors,

conveyors, filter presses and other ancillary equipment and piping and electrical work. The filter press plates

continue to be preassembled with 225 now completed out of a total of 588. The fabricated frames for the filter press

plates arrived on site during Q2 2024.

Work in the mill/flotation building continues to progress. Commissioning of all overhead cranes was completed

during Q2 2024. Construction lighting, scaffolding, steel and concrete work are all progressing according to plan. In

addition, off-site pipe spool fabrication and contractor mobilization continue on plan. Work has also commenced on

support infrastructure including the process control room building, process plant sub-station, water pump station,

lime plant, air blowers building and flotation reagent areas.

During Q2 2024, earthworks were completed to allow access to the coffer dam site and construction has now

commenced. In addition, the low-grade ore stockpile fill placement also commenced.

By the end of 2024, the Company expects to have completed the first of two water management ponds, IEWMF

coffer dam and significantly advanced the IEWMF earthworks, process plant and filter plant earthworks.

All 19 company-owned Cat 745 trucks are now onsite and operational. During construction, these trucks are used

as part of an integrated fleet with the earthwork's construction contractor for construction of the water management

ponds one and two, low-grade ore stockpile, IEWMF and facilities. These trucks will continue to be used once

Skouries is in operation to build the IEWMF lifts that will be required for stacking of produced dry tailings.

Underground Development

The upgrade of the underground power supply from 400V to 690V has been completed. The ventilation upgrade is

also complete, and the new contact water pumping system will be fully operational in 2024.

The first phase of underground development, which included the West Decline and access to the test stopes was

completed with a local contractor. The second underground development contract was awarded and the contractor

mobilized to site as planned in Q2 2024, taking their first blast on June 17, 2024. This second contract includes the

test stope work as well as additional development and services work to support the development of the

underground mine. The Company expects to complete approximately 2,200 metres of underground development by

the end of 2024.

Engineering

Following the transition of engineering to Greece at the end of 2023, it is currently 72% complete as at the end of

Q2 2024 and remains on track for substantial completion at the end of Q3 2024. Detailed engineering work

continues to advance in all areas. The release of structural steel for fabrication is nearing completion with

approximately 60% of the total steel fabricated to date.

Procurement

At the end of Q2 2024, procurement is substantially complete, with all long lead items procured and the focus on

managing fabrication and deliveries.

Operational Readiness

The experienced commissioning, operational readiness and operations leadership team, which includes seven

specialists, is currently focused on finalizing the commissioning plan integration with the project construction

schedule. In addition, development of a Management Operating System, which provides operations with a system

and processes to manage production, is ongoing. Several process mapping workshops were held to map current

processes, which are analyzed and then integrated to ensure industry best practices to improve safety, reliability

and effective decision making to drive efficiencies.

The Skouries operations team now consists of 133 personnel; including 118 in leadership, sustainability, operations

and support services roles, and 15 embedded in the construction projects teams for open pit mining, underground

mining and dry stack tailings construction. The operations recruitment profile was completed, and recruitment

4

activities are on track with the Operational Workforce Plan. Finalization of operational and maintenance training

solutions is ongoing.

The Mavres Petres Training Centre was utilized for ventilation training, business process mapping, document

management and integration of Metso operations and training solutions into training and development programs. An

agreement was reached with the technical and operational teams on a competency framework. This framework

provides industry focused, comprehensive theoretical and hands-on practical training. Trainees are assessed on

both theoretical and practical knowledge before being qualified to work independently in the mine. The training

program is consistent with and compliments the applicable standards outlined in the Greek Mining Code and labour

legislation. Training solutions for the open pit and processing operations and maintenance were identified, scoped

and mutually agreed to. Mine operators and maintenance progression systems were also developed.

Workforce

In addition to the Operational Readiness team, as at June 30, 2024, there were 841 personnel on site which is

expected to ramp up to 1,300 during 2024.

5

Consolidated Financial and Operational Highlights

3 months ended June 30, 6 months ended June 30,

2024 2023 2024 2023

Revenue $297.1 $229.0 $555.1 $456.8

Gold produced (oz) 122,319 109,435 239,430 220,944

Gold sold (oz) 121,226 110,134 237,234 219,951

Average realized gold price ($/oz sold) (2) $2,336 $1,953 $2,214 $1,943

Production costs 127.8 116.1 250.8 225.8

Total cash costs ($/oz sold) (2,3) 940 928 931 893

All-in sustaining costs ($/oz sold) (2,3) 1,331 1,296 1,297 1,252

Net earnings for the period (1) 55.5 0.9 89.1 20.2

Net earnings per share – basic ($/share) (1) 0.27 — 0.44 0.11

Net earnings per share – diluted ($/share) (1) 0.27 — 0.44 0.11

Net earnings for the period continuing operations (1,4) 56.4 1.5 91.6 20.9

Net earnings per share continuing operations –

basic ($/share)(1,4) 0.28 0.01 0.45 0.11

Net earnings per share continuing operations –

diluted ($/share)(1,4) 0.27 0.01 0.45 0.11

Adjusted net earnings continuing operations – basic (1,2,4) 66.6 9.7 121.8 26.4

Adjusted net earnings per share continuing operations

($/share)(1,2,4) 0.33 0.05 0.60 0.14

Net cash generated from operating activities (4) 112.2 75.3 207.5 115.6

Cash flow from operating activities before changes in working

capital (2,4) 132.2 82.4 240.5 175.6

Free cash flow (2,4) (32.0) (21.7) (63.0) (56.7)

Free cash flow excluding Skouries (2,4) 33.9 13.7 67.6 (6.2)

Cash, cash equivalents and term deposits (4) 595.1 456.6 595.1 456.6

Total assets 5,280.6 4,742.1 5,280.6 4,742.1

Debt (4) 748.0 546.0 748.0 546.0

(1) Attributable to shareholders of the Company.

(2) These financial measures or ratios are non-IFRS financial measures or ratios. See the section 'Non-IFRS and Other Financial Measures and Ratios' of

our MD&A for explanations and discussions of these non-IFRS financial measures or ratios.

(3) Revenues from silver, lead and zinc sales are off-set against total cash costs.

(4) Amounts presented for 2024 and 2023 are from continuing operations only and exclude the Romania segment. See Note 4 of our condensed

consolidated interim financial statements for the three and six months ended June 30, 2024.

Total revenue increased to $297.1 million in Q2 2024 from $229.0 million in Q2 2023 and to $555.1 million in the six

months ended June 30, 2024 , from $456.8 million in the six months ended June 30, 2023 . The increases in both

three and six-month periods were primarily due to the higher average realized gold price as well as the higher sales

volumes.

Production costs increased to $127.8 million in Q2 2024 from $116.1 million in Q2 2023 and to $250.8 million in the

six months ended June 30, 2024 from $225.8 million in the six months ended June 30, 2023 . Increases in both

periods were driven primarily by higher sales volume as well as slightly higher cash costs, the latter impacted by

higher royalty expense due to higher gold sales and higher gold price, as well as increases in contractor and labour

costs and higher fuel prices.

Total cash costs3 averaged $940 per ounce sold in Q2 2024, an increase from $928 in Q2 2023, and $931 the six

months ended June 30, 2024 from $893 in the six months ended June 30, 2023 . The increases in both the three

and six-month periods were primarily due to higher royalties (driven by higher gold prices) and mining costs as well

as lower by-product credits.

6

3 These financial measures or ratios are non-IFRS financial measures or ratios. Certain additional disclosure for non-IFRS financial measures

and ratios have been incorporated by reference and additional detail can be found at the end of this press release and in the section 'Non-IFRS

and Other Financial Measures and Ratios' in the Company's June 30, 2024 MD&A.

AISC per ounce sold4 averaged $1,331 in Q2 2024, an increase from $1,296 in Q2 2023, and $1,297 the six months

ended June 30, 2024 from $1,252 in the six months ended June 30, 2023, with the increases in both the three and

six-month periods due to higher total cash costs combined with higher sustaining capital and G&A.

Eldorado reported net earnings attributable to shareholders from continuing operations of $56.4 million ($0.28

earnings per share) in Q2 2024 compared to net earnings of $1.5 million ($0.01 earnings per share) in Q2 2023 and

net earnings of $91.6 million ($0.45 earnings per share) in the six months ended June 30, 2024 compared to net

earnings of $20.9 million ($0.11 earnings per share) in the six months ended June 30, 2023 . The increases in net

earnings in both the three and six-month periods were driven by higher operating income due primarily to higher

average realized gold price as well as stronger gold sales, partially offset by higher unrealized derivative losses.

Adjusted net earnings4 was $66.6 million ($0.33 earnings per share) in Q2 2024 compared to adjusted net earnings

of $9.7 million ($0.05 earnings per share) in Q2 2023. Adjustments in Q2 2024 include a $1.9 million gain on foreign

exchange due to the translation of deferred tax balances net of Turkiye inflation accounting and a $12.0 million

unrealized loss on derivative instruments.

Adjusted net earnings was $121.8 million ( $0.60 earnings per share) in the six months ended June 30, 2024

compared to adjusted net earnings of $26.4 million ($0.14 earnings per share) in the six months ended June 30,

2023. Adjustments in the six months ended June 30, 2024 include a $3.4 million loss on foreign exchange due to

the translation of deferred tax balances net of Turkiye inflation accounting, a $28.9 million unrealized loss on

derivative instruments and a $2.0 million gain on the non-cash revaluation of the derivative related to redemption

options in our Senior Notes.

7

4 These financial measures or ratios are non-IFRS financial measures or ratios. Certain additional disclosure for non-IFRS financial measures

and ratios have been incorporated by reference and additional detail can be found at the end of this press release and in the section 'Non-IFRS

and Other Financial Measures and Ratios' in the Company's June 30, 2024 MD&A.

Quarterly Operations Update

3 months ended June 30, 6 months ended June 30,

2024 2023 2024 2023

Consolidated

Ounces produced 122,319 109,435 239,430 220,944

Ounces sold 121,226 110,134 237,234 219,951

Production costs $127.8 $116.1 $250.8 $225.8

Total cash costs ($/oz sold) (1,2) $940 $928 $931 $893

All-in sustaining costs ($/oz sold) (1,2) $1,331 $1,296 $1,297 $1,252

Sustaining capital expenditures (2) $30.9 $26.1 $59.9 $52.1

Kisladag

Ounces produced 38,990 34,180 76,513 71,340

Ounces sold 39,646 32,280 76,344 69,673

Production costs $38.2 $27.5 $69.2 $58.0

Total cash costs ($/oz sold) (1,2) $941 $827 $883 $809

All-in sustaining costs ($/oz sold) (1,2) $1,055 $937 $988 $904

Sustaining capital expenditures (2) $3.1 $2.8 $5.2 $5.0

Lamaque

Ounces produced 47,391 38,745 89,690 76,629

Ounces sold 43,625 39,904 88,245 78,547

Production costs $33.6 $28.3 $68.8 $57.5

Total cash costs ($/oz sold) (1,2) $759 $701 $769 $722

All-in sustaining costs ($/oz sold) (1,2) $1,233 $1,117 $1,248 $1,166

Sustaining capital expenditures (2) $20.1 $16.2 $41.1 $34.1

Efemcukuru

Ounces produced 22,397 22,644 40,898 42,572

Ounces sold 22,462 22,466 41,076 42,217

Production costs $24.8 $20.4 $46.6 $38.1

Total cash costs ($/oz sold) (1,2) $1,087 $915 $1,117 $924

All-in sustaining costs ($/oz sold) (1,2) $1,288 $1,111 $1,220 $1,103

Sustaining capital expenditures (2) $3.6 $3.7 $6.0 $5.9

Olympias

Ounces produced 13,541 13,866 32,329 30,403

Ounces sold 15,493 15,484 31,568 29,514

Production costs $31.3 $40.0 $66.3 $72.2

Total cash costs ($/oz sold) (1,2) $1,231 $1,746 $1,260 $1,496

All-in sustaining costs ($/oz sold) (1,2) $1,522 $2,036 $1,524 $1,797

Sustaining capital expenditures (2) $4.1 $3.4 $7.6 $7.1

(1) Revenues from silver, lead and zinc sales are off-set against total cash costs.

(2) These financial measures or ratios are non-IFRS financial measures or ratios. See the section 'Non-IFRS and Other Financial Measures and Ratios' of our

MD&A for explanations and discussions of these non-IFRS financial measures or ratios.

8